TxDOT contract A00186405 bid tabulation
Bridge Replacement, US 181 (0.6 MI S of CR 1206 to 0.9 MI S of CR 1206). Let by Texas DOT on February 5, 2026, San Patricio, Corpus Christi District. 12 bids received; low bid $1,812,290 by Liska Construction Company, Inc., -5.0% against the engineer's estimate of $1,908,595.
- Owner
- Texas DOT
- Letting
- 05 FEB 2026
- Pay items
- 80
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Liska Construction Company, Inc. | $1,812,290 | Low | -5.0% |
| 2 | Garret Shields Infrastructure | $1,927,564 | +6.0% | +1.0% |
| 3 | STX Civil | $2,039,745 | +13% | +7.0% |
| 4 | J E Construction Services, LLC | $2,064,230 | +14% | +8.0% |
| 5 | CK Newberry, LLC | $2,098,585 | +16% | +10% |
| 6 | Salinas Construction Technologies, LTD. | $2,156,548 | +19% | +13% |
| 7 | E-Z Bel Construction, LLC | $2,174,689 | +20% | +14% |
| 8 | Lucania Contractors LLC | $2,248,903 | +24% | +18% |
| 9 | Acee Construction LLC. | $2,282,403 | +26% | +20% |
| 10 | J. Carroll Weaver, Inc. | $2,349,103 | +30% | +23% |
| 11 | Hunter Industries, LTD. | $2,372,410 | +31% | +24% |
| 12 | 3LW Civil LLC | $2,437,988 | +35% | +28% |
Engineer's estimate: $1,908,595.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Liska Construction Company, Inc. | 2. Garret Shields Infrastructure | 3. STX Civil | 4. J E Construction Services, LLC | 5. CK Newberry, LLC | 6. Salinas Construction Technologies, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 5 | $2,500.00 | $3,000.00 | $1,000.00 | $2,385.00 | $3,200.00 | $1,000.00 | $2,635.94 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 2,317 | $14.00 | $3.70 | $10.00 | $12.00 | $6.00 | $5.00 | $5.47 |
| 3 | Remove (23") TRT/untrt base & asphalt pavement (105-7043) | SY | 2,248 | $20.00 | $6.00 | $45.00 | $6.50 | $14.00 | $15.00 | $10.10 |
| 4 | Excavation (roadway) (110-7001) | CY | 21 | $26.50 | $10.00 | $20.00 | $10.00 | $7.00 | $25.00 | $181.52 |
| 5 | Embankment (final)(DC)(type C) (132-7006) | CY | 265 | $28.00 | $19.50 | $20.00 | $40.00 | $15.00 | $25.00 | $79.98 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 17,720 | $5.00 | $1.75 | $4.00 | $7.00 | $1.00 | $1.00 | $4.28 |
| 7 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 17,720 | $1.00 | $0.35 | $0.65 | $0.25 | $1.00 | $0.40 | $0.32 |
| 8 | Broadcast seed (temporary_warm) (164-7005) | SY | 8,420 | $1.00 | $0.15 | $0.65 | $0.25 | $1.00 | $0.30 | $0.45 |
| 9 | Vegetative watering (168-7001) | TGL | 476.40 | $30.00 | $40.00 | $10.00 | $50.00 | $32.00 | $15.00 | $38.73 |
| 10 | FL BS (cip)(type A GR 1-2 or 5) final pos (247-7348) | CY | 912 | $110.00 | $120.00 | $60.00 | $90.00 | $130.00 | $135.00 | $118.25 |
| 11 | Lime (com or QK)(slurry) (260-7005) | TON | 32 | $394.00 | $335.00 | $350.00 | $370.00 | $380.00 | $325.00 | $622.36 |
| 12 | Lime TRT (existing material)(6") (260-7006) | SY | 2,346 | $5.00 | $6.20 | $25.00 | $4.50 | $9.00 | $10.00 | $8.12 |
| 13 | Prime coat (MC-30) (310-7004) | GAL | 470 | $9.00 | $7.50 | $9.00 | $8.00 | $7.00 | $8.00 | $7.42 |
| 14 | Aggregate (type-PB, GR-4S or 4)(sac-B) (316-7212) | CY | 18 | $123.00 | $632.00 | $320.00 | $150.00 | $500.00 | $400.00 | $625.74 |
| 15 | Asphalt (multi option) (316-7263) | GAL | 787 | $7.00 | $5.10 | $8.00 | $10.00 | $5.00 | $5.00 | $6.65 |
| 16 | D-GR HMA type-B PG70-22 (exempt) (341-7014) | TON | 640 | $120.00 | $167.00 | $200.00 | $180.00 | $134.00 | $150.00 | $147.07 |
| 17 | D-GR HMA type D sac-B PG 76-22 (exempt) (341-7063) | TON | 296 | $160.00 | $190.00 | $210.00 | $205.00 | $170.00 | $180.00 | $169.79 |
| 18 | Tack coat (341-7082) | GAL | 460 | $4.00 | $4.20 | $8.00 | $7.50 | $6.00 | $4.00 | $8.08 |
| 19 | Cem stabil BKFL (400-7010) | CY | 38 | $250.00 | $140.00 | $200.00 | $85.00 | $172.00 | $325.00 | $216.08 |
| 20 | Drilled shaft (24 in) (416-7004) | LF | 588 | $200.00 | $180.00 | $220.00 | $205.00 | $220.00 | $200.00 | $183.20 |
| 21 | Class C concrete (abutment) (420-7012) | CY | 26.60 | $1,300.00 | $1,000.00 | $1,300.00 | $1,050.00 | $1,500.00 | $2,000.00 | $1,858.34 |
| 22 | Class C concrete (cap) (420-7022) | CY | 20.80 | $1,750.00 | $1,400.00 | $1,300.00 | $1,650.00 | $2,400.00 | $1,725.00 | $2,090.90 |
| 23 | Class C concrete (column) (420-7038) | CY | 7 | $1,500.00 | $1,300.00 | $1,400.00 | $1,500.00 | $2,300.00 | $2,100.00 | $3,227.96 |
| 24 | Reinforced concrete slab (slab beam) (422-7007) | SF | 3,793 | $26.00 | $22.50 | $20.00 | $24.00 | $26.00 | $33.00 | $34.93 |
| 25 | Approach slab (422-7013) | CY | 64.40 | $1,250.00 | $615.00 | $800.00 | $1,110.00 | $960.00 | $750.00 | $926.38 |
| 26 | Prestressed concrete slab beam (4SB15) (425-7018) | LF | 265.50 | $225.00 | $223.00 | $270.00 | $270.00 | $270.00 | $250.00 | $292.31 |
| 27 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 531 | $250.00 | $200.00 | $290.00 | $245.00 | $270.00 | $225.00 | $245.36 |
| 28 | Riprap (concrete)(5 in) (432-7002) | CY | 57 | $550.00 | $560.00 | $600.00 | $590.00 | $765.00 | $650.00 | $730.84 |
| 29 | Riprap (mow strip)(4 in) (432-7013) | CY | 92.30 | $560.00 | $535.00 | $600.00 | $650.00 | $765.00 | $650.00 | $738.71 |
| 30 | Rail (type T223) (450-7008) | LF | 204 | $200.00 | $135.00 | $200.00 | $150.00 | $400.00 | $250.00 | $254.41 |
| 31 | Armor joint (sealed) (454-7003) | LF | 76 | $150.00 | $150.00 | $200.00 | $125.00 | $145.00 | $175.00 | $189.27 |
| 32 | Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307) | EACH | 1 | $2,500.00 | $2,100.00 | $1,200.00 | $1,800.00 | $2,700.00 | $4,000.00 | $1,775.30 |
| 33 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $25,000 | $27,500 | $25,000 | $20,000 | $27,000 | $60,000 | $50,199 |
| 34 | Mobilization (500-7001) | LS | 1 | $160,000 | $129,000 | $150,000 | $154,000 | $90,000 | $200,000 | $203,492 |
| 35 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $7,000.00 | $3,350.00 | $5,000.00 | $3,000.00 | $3,000.00 | $10,000 | $1,564.79 |
| 36 | Portable changeable message sign (503-7002) | EACH | 2 | $14,000 | $10,500 | $5,000.00 | $5,000.00 | $4,200.00 | $10,000 | $12,650 |
| 37 | TMA (stationary) (505-7001) | DAY | 60 | $350.00 | $200.00 | $300.00 | $165.00 | $295.00 | $25.00 | $185.41 |
| 38 | TMA (mobile operation) (505-7002) | HR | 32 | $110.00 | $100.00 | $50.00 | $1.00 | $64.00 | $25.00 | $87.12 |
| 39 | Rock filter dams (install) (type 2) (506-7002) | LF | 80 | $40.00 | $50.00 | $40.00 | $40.00 | $48.00 | $70.00 | $74.75 |
| 40 | Rock filter dams (remove) (506-7011) | LF | 80 | $20.00 | $15.00 | $10.00 | $1.00 | $24.00 | $23.00 | $17.00 |
| 41 | Temporary sediment control fence (install) (506-7039) | LF | 160 | $5.00 | $5.00 | $5.00 | $3.00 | $4.00 | $10.00 | $5.87 |
| 42 | Temporary sediment control fence (remove) (506-7041) | LF | 160 | $2.00 | $2.00 | $1.00 | $1.00 | $2.00 | $2.00 | $1.67 |
| 43 | Constructing detours (508-7001) | SY | 2,974 | $65.00 | $139.00 | $90.00 | $155.00 | $150.00 | $130.00 | $127.25 |
| 44 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 2,514 | $1.00 | $3.60 | $1.10 | $1.00 | $4.00 | $3.00 | $3.19 |
| 45 | Fill milled asphalt rumble strips (shoulder) (533-7005) | LF | 1,772 | $9.00 | $2.00 | $1.75 | $5.50 | $1.00 | $3.50 | $1.63 |
| 46 | Metal W-beam guard fence (timber post) (540-7001) | LF | 300 | $28.00 | $34.50 | $40.00 | $30.00 | $35.00 | $29.00 | $31.32 |
| 47 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $2,500.00 | $2,475.00 | $1,500.00 | $2,150.00 | $2,500.00 | $2,100.00 | $2,416.65 |
| 48 | Metal W-beam guard fence adjustment (540-7009) | LF | 816 | $12.00 | $19.50 | $5.00 | $10.00 | $19.00 | $16.50 | $13.77 |
| 49 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,600.00 | $1,385.00 | $1,500.00 | $1,700.00 | $1,400.00 | $1,200.00 | $1,778.84 |
| 50 | Remove metal beam guard fence (542-7001) | LF | 300 | $5.00 | $3.00 | $1.00 | $1.00 | $3.00 | $3.25 | $5.58 |
| 51 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $250.00 | $500.00 | $500.00 | $235.00 | $280.00 | $250.00 | $414.89 |
| 52 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 2 | $410.00 | $300.00 | $100.00 | $275.00 | $320.00 | $275.00 | $364.95 |
| 53 | Cable barrier system (install)(TL-4) (543-7002) | LF | 1,947 | $16.00 | $25.00 | $15.00 | $18.00 | $25.00 | $21.00 | $24.20 |
| 54 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 2 | $3,700.00 | $3,525.00 | $3,000.00 | $3,250.00 | $3,500.00 | $3,000.00 | $3,462.45 |
| 55 | Cable barrier (remove) (543-7037) | LF | 1,947 | $5.00 | $3.85 | $5.00 | $6.00 | $4.00 | $4.00 | $5.83 |
| 56 | Cable barrier terminal section (remove) (543-7038) | EACH | 1 | $550.00 | $500.00 | $500.00 | $785.00 | $470.00 | $400.00 | $414.89 |
| 57 | Guardrail end treatment (install) (544-7001) | EACH | 3 | $3,800.00 | $3,960.00 | $3,500.00 | $3,750.00 | $4,000.00 | $3,300.00 | $4,157.20 |
| 58 | Guardrail end treatment (remove) (544-7003) | EACH | 3 | $400.00 | $250.00 | $500.00 | $800.00 | $400.00 | $325.00 | $348.30 |
| 59 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 2 | $1,000.00 | $1,250.00 | $800.00 | $525.00 | $1,500.00 | $1,250.00 | $1,362.45 |
| 60 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 2 | $1,200.00 | $1,500.00 | $800.00 | $625.00 | $1,800.00 | $1,500.00 | $1,624.95 |
| 61 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $170.00 | $50.00 | $500.00 | $120.00 | $490.00 | $175.00 | $208.72 |
| 62 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 3 | $40.00 | $50.00 | $40.00 | $25.00 | $67.00 | $55.00 | $91.05 |
| 63 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 3 | $40.00 | $50.00 | $40.00 | $25.00 | $16.00 | $55.00 | $91.05 |
| 64 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 7,831 | $2.00 | $0.50 | $1.20 | $0.45 | $1.00 | $1.00 | $0.45 |
| 65 | Work zone pavement marking removing (Y)6"(solid W/marker) (662-7109) | LF | 7,636 | $4.00 | $0.50 | $1.20 | $0.45 | $1.00 | $1.00 | $0.45 |
| 66 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 1,401 | $1.60 | $1.06 | $1.00 | $0.95 | $1.00 | $1.00 | $1.00 |
| 67 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 72 | $10.00 | $19.50 | $11.50 | $18.00 | $19.00 | $16.00 | $18.19 |
| 68 | Pavement sler 6" (666-7347) | LF | 290 | $0.60 | $4.20 | $0.82 | $5.00 | $4.00 | $3.50 | $4.02 |
| 69 | Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407) | LF | 2,150 | $1.50 | $1.32 | $0.82 | $1.15 | $1.00 | $1.25 | $1.20 |
| 70 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 8,559 | $1.50 | $0.79 | $0.82 | $0.78 | $1.00 | $1.00 | $0.77 |
| 71 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 8,339 | $1.50 | $0.79 | $0.82 | $0.78 | $1.00 | $1.00 | $0.77 |
| 72 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 4 | $350.00 | $220.00 | $235.00 | $250.00 | $240.00 | $200.00 | $234.97 |
| 73 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 4 | $390.00 | $330.00 | $300.00 | $350.00 | $360.00 | $300.00 | $339.97 |
| 74 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 14 | $70.00 | $27.50 | $45.00 | $30.00 | $30.00 | $25.00 | $33.39 |
| 75 | Reflectorized pavement marker type I-C (672-7002) | EACH | 71 | $8.00 | $8.00 | $4.70 | $8.50 | $9.00 | $8.00 | $9.28 |
| 76 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 109 | $10.00 | $8.00 | $4.70 | $8.50 | $9.00 | $8.00 | $8.79 |
| 77 | Eliminating existing PM & markers (4") (677-7001) | LF | 8,047 | $1.30 | $0.42 | $1.00 | $0.50 | $1.00 | $1.00 | $0.38 |
| 78 | Eliminating existing PM & markers (8") (677-7004) | LF | 810 | $2.00 | $0.78 | $1.20 | $0.70 | $1.00 | $1.00 | $0.81 |
| 79 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 1 | $110.00 | $80.00 | $70.00 | $85.00 | $90.00 | $75.00 | $178.64 |
| 80 | Eliminating existing PM & markers (word) (677-7015) | EACH | 1 | $120.00 | $80.00 | $70.00 | $85.00 | $90.00 | $75.00 | $178.64 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 5, 2026. Compiled by Mirage Metrics.