METAL BEAM GUARD FENCE REPAIR, IH0045 (Various to Various). Let by Texas DOT on December 9, 2025, Freestone, Bryan District. 4 bids received; low bid $296,311 by T&L Cleaning Services LLC, -24% against the engineer's estimate of $389,575.
- Owner
- Texas DOT
- Letting
- 09 DEC 2025
- Pay items
- 44
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | T&L Cleaning Services LLC | $296,311 | Low | -24% |
| 2 | Rhino Equity, LLC | $299,615 | +1.0% | -23% |
| 3 | Above All Contracting LLC | $348,395 | +18% | -11% |
| 4 | BK Field Operations LLC | $352,240 | +19% | -10% |
Engineer's estimate: $389,575.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. T&L Cleaning Services LLC | 2. Rhino Equity, LLC | 3. Above All Contracting LLC | 4. BK Field Operations LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Riprap (mow strip)(4 in) (432-7013) | CY | 10 | $700.00 | $300.00 | $100.00 | $600.00 | $1.00 |
| 2 | Mobilization (callout) (500-7002) | EACH | 20 | $1,000.00 | $1.00 | $100.00 | $1.00 | $1.00 |
| 3 | TMA (stationary) (505-7001) | DAY | 50 | $500.00 | $1,000.00 | $1,200.00 | $200.00 | $5,000.00 |
| 4 | Metal W-beam guard fence (timber post) (540-7001) | LF | 500 | $35.00 | $36.00 | $35.00 | $35.00 | $14.00 |
| 5 | Metal W-beam guard fence (steel post) (540-7002) | LF | 200 | $40.00 | $1.00 | $20.00 | $50.00 | $15.00 |
| 6 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 5 | $2,200.00 | $1,000.00 | $750.00 | $3,000.00 | $350.00 |
| 7 | Metal W-beam guard fence adjustment (540-7009) | LF | 25 | $20.00 | $1.00 | $1.00 | $20.00 | $1.00 |
| 8 | Downstream anchor terminal section (540-7015) | EACH | 5 | $1,700.00 | $1,200.00 | $1.00 | $1,900.00 | $1.00 |
| 9 | Remove metal beam guard fence (542-7001) | LF | 500 | $6.00 | $0.01 | $1.00 | $5.00 | $1.00 |
| 10 | Remove terminal anchor section (542-7002) | EACH | 5 | $300.00 | $1.00 | $1.00 | $200.00 | $1.00 |
| 11 | Remove downstream anchor terminal (542-7003) | EACH | 5 | $260.00 | $1.00 | $1.00 | $200.00 | $1.00 |
| 12 | Guardrail end treatment (install) (544-7001) | EACH | 5 | $3,400.00 | $3,000.00 | $3,200.00 | $3,100.00 | $2,000.00 |
| 13 | Guardrail end treatment (remove) (544-7003) | EACH | 5 | $470.00 | $1.00 | $1.00 | $500.00 | $1.00 |
| 14 | Replace rail element (W-beam) (770-7001) | LF | 1,500 | $25.00 | $24.00 | $30.00 | $28.00 | $8.00 |
| 15 | Replace rail element (thrie-beam) (770-7002) | LF | 50 | $50.00 | $20.00 | $10.00 | $55.00 | $1.00 |
| 16 | Repl rail elmnt(thrie-BM trans to W-BM) (770-7003) | EACH | 20 | $80.00 | $1.00 | $100.00 | $400.00 | $1.00 |
| 17 | Replace timber post W/O concrete FND (770-7006) | EACH | 100 | $60.00 | $1.00 | $50.00 | $50.00 | $1.00 |
| 18 | Replace steel post W/O concrete FND (770-7007) | EACH | 25 | $80.00 | $1.00 | $75.00 | $75.00 | $1.00 |
| 19 | Replace timber post W/ concrete FND (770-7008) | EACH | 50 | $85.00 | $1.00 | $100.00 | $50.00 | $20.00 |
| 20 | Replace steel post W/ concrete FND (770-7009) | EACH | 10 | $95.00 | $1.00 | $1.00 | $75.00 | $1.00 |
| 21 | Realign posts (770-7010) | EACH | 100 | $35.00 | $1.00 | $1.00 | $50.00 | $1.00 |
| 22 | Rem obsolete get & repl W/ SGT (770-7013) | EACH | 25 | $4,400.00 | $4,000.00 | $3,200.00 | $3,200.00 | $2,000.00 |
| 23 | Repl single gdrail terminal impact head (770-7015) | EACH | 5 | $1,000.00 | $1,000.00 | $750.00 | $900.00 | $150.00 |
| 24 | Replace single gdrail terminal rail (770-7016) | LF | 500 | $50.00 | $50.00 | $20.00 | $35.00 | $12.00 |
| 25 | Replace single gdrail terminal post (770-7017) | EACH | 10 | $150.00 | $100.00 | $50.00 | $100.00 | $20.00 |
| 26 | Replace blockout (770-7018) | EACH | 100 | $40.00 | $1.00 | $50.00 | $50.00 | $1.00 |
| 27 | Repair steel post with base plate (770-7019) | EACH | 5 | $150.00 | $200.00 | $100.00 | $300.00 | $1.00 |
| 28 | Reset SGT impact head (770-7020) | EACH | 5 | $240.00 | $50.00 | $1.00 | $100.00 | $1.00 |
| 29 | Replace SGT object marker (770-7021) | EACH | 5 | $20.00 | $30.00 | $1.00 | $30.00 | $1.00 |
| 30 | Replace SGT cable anchor (770-7022) | EACH | 5 | $20.00 | $1.00 | $1.00 | $100.00 | $1.00 |
| 31 | Replace SGT cable assembly (770-7023) | EACH | 5 | $40.00 | $1.00 | $1.00 | $100.00 | $1.00 |
| 32 | Replace SGT strut (770-7024) | EACH | 5 | $70.00 | $1.00 | $1.00 | $100.00 | $1.00 |
| 33 | Raise rail (770-7025) | LF | 100 | $10.00 | $1.00 | $1.00 | $10.00 | $1.00 |
| 34 | Replace downstream anchor terminal (770-7026) | EACH | 5 | $1,000.00 | $1,200.00 | $1,000.00 | $1,900.00 | $200.00 |
| 35 | Repair rail element (curved rail) (770-7027) | LF | 20 | $35.00 | $50.00 | $30.00 | $80.00 | $10.00 |
| 36 | Replace posts (TL-4)(gibraltar) (771-7005) | EACH | 50 | $190.00 | $150.00 | $180.00 | $180.00 | $40.00 |
| 37 | Replace posts (TL-4)(NU-cable) (771-7006) | EACH | 50 | $190.00 | $1.00 | $1.00 | $150.00 | $1.00 |
| 38 | Replace posts (TL-4)(trinity) (771-7007) | EACH | 50 | $190.00 | $180.00 | $250.00 | $200.00 | $40.00 |
| 39 | Cable splice / turnbuckle (TL-4) (771-7010) | EACH | 5 | $95.00 | $100.00 | $1.00 | $250.00 | $1.00 |
| 40 | Repair concrete foundation (TL-4) (771-7012) | EACH | 5 | $130.00 | $1.00 | $1.00 | $700.00 | $1.00 |
| 41 | Repair or replace cable barrier terminal sec(TL-4) (771-7014) | EACH | 10 | $1,500.00 | $500.00 | $800.00 | $2,800.00 | $400.00 |
| 42 | Replace cable (TL-4) (771-7016) | LF | 100 | $10.00 | $0.01 | $0.50 | $10.00 | $1.00 |
| 43 | Check / RE-tension cable (TL-4) (771-7018) | EACH | 20 | $230.00 | $1.00 | $10.00 | $150.00 | $1.00 |
| 44 | Replace post hardware (TL-4) (771-7020) | EACH | 50 | $70.00 | $1.00 | $1.00 | $50.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.