TxDOT contract A00130760 bid tabulation
Surfacing/Roadway Restoration, SH 275 (IH 45 to 14th Street). Let by Texas DOT on June 4, 2025, Galveston, Houston District. 5 bids received; low bid $9,764,259 by Posillico Civil, Inc., -23% against the engineer's estimate of $12,707,852.
- Owner
- Texas DOT
- Letting
- 04 JUN 2025
- Pay items
- 109
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Posillico Civil, Inc. | $9,764,259 | Low | -23% |
| 2 | Isi Contracting, Inc. | $10,770,222 | +10% | -15% |
| 3 | MC2 Civil, LLC | $11,793,455 | +21% | -7.0% |
| 4 | Ragle Construction, Inc. | $12,251,805 | +25% | -4.0% |
| 5 | MBN Enterprises LLC | $12,330,789 | +26% | -3.0% |
Engineer's estimate: $12,707,852.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Posillico Civil, Inc. | 2. Isi Contracting, Inc. | 3. MC2 Civil, LLC | 4. Ragle Construction, Inc. | 5. MBN Enterprises LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 2,157 | $44.99 | $6.00 | $20.00 | $15.00 | $14.00 | $10.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 281 | $29.49 | $8.00 | $28.00 | $20.00 | $18.00 | $25.00 |
| 3 | Removing concrete (curb & gutter) (104-7017) | LF | 1,557 | $27.65 | $2.35 | $6.00 | $10.00 | $7.00 | $9.00 |
| 4 | Remove (7"-11") TRT/untrt base & asphalt pavement (105-7007) | SY | 6,154 | $21.08 | $5.00 | $3.90 | $15.00 | $6.50 | $12.50 |
| 5 | Excavation (roadway) (110-7001) | CY | 1,000 | $50.65 | $25.00 | $45.00 | $40.00 | $250.00 | $20.00 |
| 6 | Embankment (final)(OC)(type A) (132-7001) | CY | 500 | $250.09 | $25.00 | $75.00 | $40.00 | $40.00 | $30.00 |
| 7 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 131 | $403.08 | $360.00 | $271.00 | $320.00 | $318.00 | $350.00 |
| 8 | Lime TRT (existing material)(8") (260-7007) | SY | 7,273 | $17.80 | $5.00 | $3.00 | $10.00 | $6.25 | $5.50 |
| 9 | Asphalt TRT base (GR 2)(PG 64) (292-7006) | TON | 1,601 | $165.00 | $128.00 | $200.00 | $170.00 | $160.00 | $160.00 |
| 10 | D-GR HMA type D PG70-22 (level-UP) (341-7051) | TON | 8,510 | $200.00 | $148.00 | $138.00 | $146.00 | $180.00 | $170.00 |
| 11 | D-GR HMA type D sac-A PG76-22 (341-7057) | TON | 6,907 | $175.29 | $195.00 | $169.00 | $165.00 | $200.00 | $185.00 |
| 12 | Tack coat (341-7082) | GAL | 5,025 | $5.09 | $5.00 | $4.90 | $4.25 | $4.75 | $5.00 |
| 13 | Flexible pavement structure repair(21") (351-7020) | SY | 1,020 | $97.00 | $190.00 | $193.00 | $240.00 | $155.00 | $150.00 |
| 14 | Planing asphalt concrete pavement(3") (354-7052) | SY | 83,723 | $7.52 | $1.80 | $1.60 | $4.75 | $2.70 | $5.00 |
| 15 | Concrete pavement(transition slab) (10") (360-7033) | SY | 409 | $282.43 | $200.00 | $179.00 | $160.00 | $120.00 | $150.00 |
| 16 | Concrete pavement (CRCP)(hes) (10") (360-7049) | SY | 6,856 | $188.38 | $125.00 | $135.00 | $120.00 | $110.00 | $130.00 |
| 17 | Full-depth repair CRCP (16") (361-7048) | SY | 9,523 | $200.00 | $245.00 | $270.00 | $195.00 | $350.00 | |
| 18 | Cem stabil BKFL (400-7010) | CY | 109 | $248.87 | $70.00 | $350.00 | $70.00 | $143.00 | $100.00 |
| 19 | Class C concrete (collar) (420-7061) | EACH | 15 | $1,085.76 | $944.44 | $4,005.00 | $1,600.00 | $2,250.00 | $1,200.00 |
| 20 | Riprap (concrete)(4 in) (432-7001) | CY | 242 | $420.00 | $560.00 | $464.00 | $750.00 | $560.00 | $700.00 |
| 21 | Clean & paint existing STR (system III-A) (446-7010) | LS | 1 | $160,000 | $250,000 | $1,500,000 | $1,597,000 | $200,000 | |
| 22 | RC pipe (CL V)(18 in) (464-7032) | LF | 60 | $259.13 | $300.00 | $220.00 | $400.00 | $360.00 | $100.00 |
| 23 | Inlet (complete)(curb)(type C1)(none)(hou) (465-7309) | EACH | 8 | $8,790.23 | $8,500.00 | $7,196.00 | $10,000 | $8,000.00 | $8,000.00 |
| 24 | Inlet (complete)(curb)(type C1)(left)(hou) (465-7310) | EACH | 3 | $10,230 | $8,500.00 | $7,299.00 | $10,000 | $8,250.00 | $8,000.00 |
| 25 | Inlet (complete)(curb)(type C1)(right)(hou) (465-7311) | EACH | 2 | $9,325.30 | $8,500.00 | $7,322.00 | $10,000 | $8,250.00 | $8,000.00 |
| 26 | Inlet (complete)(curb)(type C1)(both)(hou) (465-7312) | EACH | 2 | $8,695.60 | $9,500.00 | $7,619.00 | $10,000 | $8,750.00 | $8,000.00 |
| 27 | Adjusting manholes (479-7001) | EACH | 79 | $1,808.19 | $550.00 | $1,500.00 | $400.00 | $1,175.00 | $1,400.00 |
| 28 | Removing structure (inlet) (496-7002) | EACH | 15 | $1,913.33 | $300.00 | $2,500.00 | $750.00 | $620.00 | $800.00 |
| 29 | Removing structure (pipe) (496-7007) | LF | 60 | $33.18 | $100.00 | $150.00 | $100.00 | $18.00 | $50.00 |
| 30 | Mobilization (500-7001) | LS | 1 | $1,304,435 | $850,000 | $1,000,000 | $1,100,000 | $1,200,000 | $1,100,000 |
| 31 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $12,049 | $16,000 | $30,000 | $20,000 | $36,500 | $13,000 |
| 32 | Portable changeable message sign (503-7001) | DAY | 240 | $195.28 | $75.00 | $211.00 | $75.00 | $100.00 | $150.00 |
| 33 | TMA (stationary) (505-7001) | DAY | 240 | $506.13 | $450.00 | $1,000.00 | $250.00 | $400.00 | $230.00 |
| 34 | TMA (mobile operation) (505-7003) | DAY | 15 | $42.78 | $700.00 | $694.00 | $600.00 | $600.00 | $300.00 |
| 35 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 3,360 | $3.75 | $7.00 | $8.50 | $8.00 | $8.00 | $5.00 |
| 36 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,360 | $0.41 | $2.00 | $2.80 | $2.00 | $1.00 | $1.00 |
| 37 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 60 | $129.77 | $85.00 | $75.00 | $150.00 | $100.00 | |
| 38 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 40 | $119.00 | $94.00 | $75.00 | $150.00 | $100.00 | |
| 39 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 840 | $7.93 | $1.80 | $25.00 | $15.00 | $20.00 | |
| 40 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 560 | $11.90 | $1.80 | $25.00 | $20.00 | $20.00 | |
| 41 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 60 | $42.05 | $15.00 | $25.00 | $20.00 | $50.00 | |
| 42 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 40 | $47.38 | $6.90 | $25.00 | $25.00 | $50.00 | |
| 43 | Concrete curb (type II) (529-7002) | LF | 4,307 | $63.48 | $7.89 | $12.40 | $20.00 | $9.00 | $10.00 |
| 44 | Intersections (ACP) (530-7002) | SY | 173 | $35.00 | $150.00 | $185.00 | $79.00 | $125.00 | $100.00 |
| 45 | Driveways (concrete) (hes) (530-7007) | SY | 495 | $395.00 | $120.00 | $292.00 | $120.00 | $125.00 | $110.00 |
| 46 | Driveways (ACP) (530-7010) | SY | 131 | $86.30 | $128.00 | $223.00 | $97.00 | $125.00 | $100.00 |
| 47 | Aluminum signs (type A) (636-7001) | SF | 1,001 | $22.10 | $28.00 | $25.00 | $24.25 | $26.00 | |
| 48 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 93 | $823.66 | $1,066.00 | $1,050.00 | $1,010.00 | $1,100.00 | |
| 49 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 14 | $935.46 | $1,287.00 | $1,150.00 | $1,130.00 | $1,300.00 | |
| 50 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 5 | $918.63 | $1,179.00 | $1,200.00 | $1,175.00 | $1,500.00 | |
| 51 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 4 | $976.50 | $1,287.00 | $1,350.00 | $1,335.00 | $1,800.00 | |
| 52 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 1 | $1,255.35 | $1,644.00 | $1,550.00 | $1,500.00 | $1,800.00 | |
| 53 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 2 | $1,338.48 | $1,839.00 | $1,800.00 | $1,750.00 | $5,000.00 | |
| 54 | Remove SM RD SN sup&AM (644-7073) | EACH | 123 | $78.92 | $130.00 | $100.00 | $95.00 | $120.00 | |
| 55 | In SRSS & AM (rail)(130 MPH)(P mount) (644-7083) | EACH | 2 | $6,393.56 | $7,243.00 | $3,700.00 | $3,675.00 | $5,000.00 | |
| 56 | In SRSS & AM (rail)(130 MPH)(T mount) (644-7085) | EACH | 1 | $6,692.40 | $7,676.00 | $4,000.00 | $3,975.00 | $5,000.00 | |
| 57 | In SRSS & AM (rail)(130 MPH)(U mount) (644-7086) | EACH | 1 | $6,750.27 | $7,827.00 | $4,050.00 | $4,015.00 | $6,000.00 | |
| 58 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 761 | $3.55 | $5.70 | $5.25 | $6.00 | $7.00 | |
| 59 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 2,207 | $3.55 | $5.70 | $5.25 | $6.00 | $7.00 | |
| 60 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 24,460 | $1.42 | $0.40 | $0.35 | $1.15 | $1.30 | |
| 61 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 21,156 | $0.76 | $0.40 | $0.35 | $1.05 | $1.25 | |
| 62 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 12,762 | $1.42 | $0.70 | $0.60 | $1.85 | $2.20 | |
| 63 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 4,992 | $6.09 | $4.30 | $4.00 | $9.00 | $11.00 | |
| 64 | Work zone pavement marking removing (W)(arrow) (662-7082) | EACH | 114 | $157.34 | $92.00 | $85.00 | $190.00 | $210.00 | |
| 65 | Work zone pavement marking removing (W)(RR crossing) (662-7088) | EACH | 24 | $456.79 | $216.00 | $200.00 | $550.00 | $600.00 | |
| 66 | Work zone pavement marking removing (W)(word) (662-7092) | EACH | 48 | $187.79 | $92.00 | $85.00 | $250.00 | $300.00 | |
| 67 | Work zone pavement marking removing (Y)6"(broken) (662-7098) | LF | 16,440 | $1.42 | $0.40 | $0.35 | $1.15 | $1.30 | |
| 68 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 124,644 | $0.76 | $0.40 | $0.35 | $1.05 | $1.25 | |
| 69 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 3,188 | $1.57 | $1.37 | $1.20 | $1.10 | $1.50 | $1.80 |
| 70 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 425 | $4.00 | $7.97 | $6.50 | $6.00 | $8.50 | $11.00 |
| 71 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 8 | $219.86 | $157.34 | $151.00 | $140.00 | $165.00 | $220.00 |
| 72 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 2 | $255.40 | $167.49 | $184.00 | $170.00 | $220.00 | $260.00 |
| 73 | RE PV marking type I(black)6"(shadow)(100MIL) (666-7138) | LF | 5,520 | $3.95 | $1.27 | $1.00 | $0.90 | $0.98 | $1.20 |
| 74 | Reflectorized pavement marking type I(W)(RR crossing)(100MIL)(callout) (666-7157) | EACH | 12 | $7.00 | $761.31 | $676.00 | $625.00 | $700.00 | $900.00 |
| 75 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 6,753 | $3.75 | $1.22 | $0.90 | $0.80 | $0.98 | $1.20 |
| 76 | Reflectorized pavement marking type III (W)(6")(broken) (666-7237) | LF | 6,710 | $0.76 | $1.37 | $0.90 | $0.80 | $1.02 | $1.20 |
| 77 | Reflectorized pavement marking type III (W)(8")(solid) (666-7239) | LF | 3,193 | $2.49 | $1.37 | $1.30 | $1.20 | $1.60 | $2.00 |
| 78 | Reflectorized pavement marking type III (W)(24")(solid) (666-7244) | LF | 2,071 | $11.37 | $11.17 | $8.70 | $8.00 | $9.00 | $11.00 |
| 79 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 31,574 | $1.57 | $1.22 | $0.90 | $0.80 | $1.00 | $1.20 |
| 80 | Reflectorized pavement marking type III (Y)(6")(broken) (666-7249) | LF | 3,180 | $2.12 | $1.37 | $0.90 | $0.80 | $1.02 | $1.20 |
| 81 | Reflectorized pavement marking type III (W)(arrow) (666-7254) | EACH | 49 | $313.00 | $203.02 | $330.00 | $305.00 | $195.00 | $225.00 |
| 82 | Reflectorized pavement marking type III (W)(word) (666-7257) | EACH | 22 | $319.78 | $203.02 | $463.00 | $430.00 | $230.00 | $265.00 |
| 83 | Reflectorized pavement marking type III (BLK)(6")(shadow) (666-7262) | LF | 6,740 | $1.55 | $1.42 | $0.90 | $0.80 | $0.99 | $1.20 |
| 84 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 5,520 | $1.60 | $1.22 | $0.90 | $0.80 | $1.05 | $1.25 |
| 85 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 3,825 | $1.53 | $1.32 | $0.90 | $0.80 | $1.00 | $1.20 |
| 86 | Type I high perf PM (Y)6"(broken)(100MIL) (666-7302) | LF | 5,040 | $0.98 | $1.22 | $0.90 | $0.80 | $1.05 | $1.25 |
| 87 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 30,748 | $1.47 | $0.42 | $0.87 | $0.80 | $1.02 | $1.20 |
| 88 | Pavement sler 6" (666-7347) | LF | 54,957 | $0.77 | $0.42 | $0.10 | $0.10 | $0.25 | $0.40 |
| 89 | Pavement sler 8" (666-7348) | LF | 3,193 | $1.31 | $0.76 | $0.20 | $0.20 | $0.40 | $0.50 |
| 90 | Pavement sler 24" (666-7352) | LF | 2,071 | $4.10 | $3.05 | $1.10 | $1.00 | $1.20 | $1.50 |
| 91 | Pavement sler (arrow) (666-7353) | EACH | 49 | $49.21 | $25.38 | $13.00 | $12.00 | $50.00 | $70.00 |
| 92 | Pavement sler (word) (666-7354) | EACH | 22 | $55.92 | $25.38 | $13.00 | $12.00 | $60.00 | $80.00 |
| 93 | Reflectorized pavement marker type I-C (672-7002) | EACH | 761 | $6.70 | $5.33 | $6.50 | $6.00 | $6.50 | $9.00 |
| 94 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 2,207 | $3.03 | $5.33 | $6.50 | $6.00 | $6.50 | $9.00 |
| 95 | Eliminating existing PM & markers (6") (677-7002) | LF | 54,957 | $1.57 | $0.56 | $0.40 | $0.40 | $0.40 | $0.50 |
| 96 | Eliminating existing PM & markers (8") (677-7004) | LF | 3,193 | $1.57 | $1.02 | $1.10 | $1.00 | $0.65 | $0.90 |
| 97 | Eliminating existing PM & markers (24") (677-7008) | LF | 2,071 | $5.04 | $3.55 | $2.20 | $2.00 | $2.00 | $3.00 |
| 98 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 49 | $98.31 | $55.83 | $81.00 | $75.00 | $65.00 | $100.00 |
| 99 | Eliminating existing PM & markers (word) (677-7015) | EACH | 22 | $98.46 | $55.83 | $92.00 | $85.00 | $80.00 | $100.00 |
| 100 | Eliminating existing PM & markers (RR crossing) (677-7019) | EACH | 12 | $212.56 | $55.83 | $270.00 | $250.00 | $150.00 | $180.00 |
| 101 | Pavement surface preparation for marking (6") (678-7002) | LF | 54,957 | $0.08 | $0.08 | $0.02 | $0.01 | $0.05 | $0.10 |
| 102 | Pavement surface preparation for marking (8") (678-7004) | LF | 3,193 | $0.52 | $0.16 | $0.06 | $0.05 | $0.10 | $0.20 |
| 103 | Pavement surface preparation for marking (24") (678-7008) | LF | 2,071 | $3.14 | $0.32 | $0.54 | $0.50 | $0.50 | $0.60 |
| 104 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 49 | $13.46 | $7.11 | $10.80 | $10.00 | $15.00 | $25.00 |
| 105 | Pavement surface preparation for marking (word) (678-7016) | EACH | 22 | $15.12 | $7.11 | $10.80 | $10.00 | $23.00 | $30.00 |
| 106 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 2,968 | $4.26 | $0.08 | $0.27 | $0.25 | $0.50 | $0.70 |
| 107 | Bridge joint repair (armor) (785-7004) | LF | 156 | $85.00 | $240.00 | $600.00 | $150.00 | $400.00 | $140.00 |
| 108 | Membrane underseal (3005-7001) | GAL | 18,421 | $10.00 | $5.50 | $5.00 | $4.50 | $4.50 | $13.00 |
| 109 | Continuous grinding-concrete pavement (3017-7001) | SY | 64,669 | $13.00 | $11.00 | $7.00 | $10.25 | $13.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.