TxDOT contract A00132253 bid tabulation
Ferry Operation Projects, SH 361 (AT FERRY LANDINGS ON HARBOR ISLAND to .). Let by Texas DOT on May 7, 2026, Nueces, Corpus Christi District. 4 bids received; low bid $41,937,000 by Russell Marine, LLC, -4.3% against the engineer's estimate of $43,826,715.
- Owner
- Texas DOT
- Letting
- 07 MAY 2026
- Pay items
- 78
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Russell Marine, LLC | $41,937,000 | Low | -4.0% |
| 2 | Ragle Construction, Inc. | $45,629,054 | +9.0% | +4.0% |
| 3 | Callan Marine LTD | $45,701,905 | +9.0% | +4.0% |
| 4 | Orion Construction, LLC | $47,230,000 | +13% | +8.0% |
Engineer's estimate: $43,826,715.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Russell Marine, LLC | 2. Ragle Construction, Inc. | 3. Callan Marine LTD | 4. Orion Construction, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7001) | ACRE | 3.50 | $500,000 | $1,000.00 | $580,000 | $5,939.00 | $435,000 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 1,553 | $50.00 | $45.00 | $15.00 | $46.00 | $55.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 24 | $50.00 | $70.00 | $75.00 | $199.00 | $280.00 |
| 4 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 206 | $22.00 | $65.00 | $30.00 | $27.00 | $37.00 |
| 5 | Removing concrete (curb) (104-7016) | LF | 63 | $10.00 | $20.00 | $50.00 | $7.00 | $56.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 100 | $20.00 | $40.00 | $350.00 | $39.00 | $35.00 |
| 7 | Embankment (final)(DC)(type C) (132-7006) | CY | 6,169 | $40.00 | $30.00 | $25.00 | $49.00 | $36.00 |
| 8 | FL BS (compacted in place)(type A GR 1-2) (12") (247-7113) | SY | 678 | $40.00 | $80.00 | $55.00 | $154.00 | $160.00 |
| 9 | FL BS (compacted in place)(type A GR 1-2) (9") (247-7350) | SY | 1,870 | $25.00 | $69.00 | $40.00 | $80.00 | $125.00 |
| 10 | Cement (275-7001) | TON | 57 | $300.00 | $300.00 | $240.00 | $440.00 | $525.00 |
| 11 | Cement TRT (subgrade)(6") (275-7022) | SY | 1,870 | $20.00 | $30.00 | $11.00 | $42.00 | $17.00 |
| 12 | Prime coat (MC-30) (310-7004) | GAL | 468 | $50.00 | $10.00 | $10.00 | $36.00 | $14.00 |
| 13 | Asphalt(AC-15P, HFRS-2P or CRS-2P) (316-7070) | GAL | 599 | $5.00 | $5.00 | $10.00 | $28.00 | $7.00 |
| 14 | Aggregate (type-PB, GR-4S or 4)(sac-B) (316-7212) | CY | 20 | $500.00 | $900.00 | $350.00 | $195.00 | $1,250.00 |
| 15 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 412 | $350.00 | $360.00 | $200.00 | $312.00 | $510.00 |
| 16 | Struct excavation (400-7001) | CY | 4,200 | $35.00 | $20.00 | $17.00 | $52.00 | $29.00 |
| 17 | Cem stabil BKFL (400-7010) | CY | 84.50 | $300.00 | $500.00 | $190.00 | $189.00 | $495.00 |
| 18 | Flowable backfill (401-7001) | CY | 1,080 | $500.00 | $300.00 | $285.00 | $327.00 | $362.00 |
| 19 | Temporary special shoring (403-7001) | SF | 2,100 | $50.00 | $1.00 | $90.00 | $74.00 | $200.00 |
| 20 | Sheet piling (NZ 42) (407-7010) | SF | 23,913 | $125.00 | $90.00 | $66.00 | $99.00 | $120.00 |
| 21 | Steel H - piling (HP 14 X 73) (407-7012) | LF | 4,849 | $200.00 | $225.00 | $140.00 | $262.00 | $267.00 |
| 22 | Steel pipe piling (36 X 1 1/4) (407-7014) | LF | 822 | $1,500.00 | $2,000.00 | $1,255.00 | $1,608.00 | $1,675.00 |
| 23 | Steel pipe piling (60 X 1 1/4) (407-7015) | LF | 474 | $2,500.00 | $3,000.00 | $2,940.00 | $4,120.00 | $4,300.00 |
| 24 | Steel pipe piling (60 X 1 3/8) (407-7016) | LF | 119 | $2,600.00 | $3,100.00 | $2,175.00 | $2,814.00 | $3,100.00 |
| 25 | Steel pipe piling (66 X 1 1/2) (407-7017) | LF | 438 | $2,700.00 | $3,500.00 | $3,452.00 | $4,943.00 | $5,000.00 |
| 26 | Sheet piling (NZ-20) (407-7018) | SF | 3,074 | $90.00 | $140.00 | $50.50 | $78.00 | $76.50 |
| 27 | Sheet piling (NZ-26) (407-7019) | SF | 3,427 | $95.00 | $150.00 | $57.00 | $78.00 | $79.50 |
| 28 | Sheet piling (NZ-38) (407-7020) | SF | 19,210 | $100.00 | $85.00 | $63.00 | $100.00 | $100.00 |
| 29 | Prestressed concrete pil (18 in SQ) (409-7002) | LF | 3,600 | $200.00 | $180.00 | $140.00 | $178.00 | $143.00 |
| 30 | Drilled shaft (24 in) (416-7004) | LF | 1,452 | $260.00 | $250.00 | $225.00 | $304.00 | $430.00 |
| 31 | Drilled shaft (36 in) (416-7006) | LF | 570 | $400.00 | $490.00 | $335.00 | $495.00 | $725.00 |
| 32 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 120 | $350.00 | $450.00 | $375.00 | $591.00 | $725.00 |
| 33 | Class A concrete (miscellaneous) (420-7002) | CY | 33.60 | $1,100.00 | $1,100.00 | $1,200.00 | $835.00 | $1,950.00 |
| 34 | Class B concrete (miscellaneous) (420-7011) | CY | 8.80 | $1,100.00 | $1,000.00 | $1,100.00 | $445.00 | $1,700.00 |
| 35 | CL F concrete (cap)(HPC) (420-7072) | CY | 545.80 | $2,500.00 | $1,900.00 | $1,170.00 | $1,035.00 | $3,275.00 |
| 36 | CL F concrete (column)(HPC) (420-7104) | CY | 85.50 | $3,000.00 | $2,200.00 | $1,670.00 | $10,520 | $3,700.00 |
| 37 | CL F concrete (abutment)(HPC) (420-7161) | CY | 80.80 | $2,500.00 | $1,700.00 | $960.00 | $2,245.00 | $2,200.00 |
| 38 | CL F concrete (miscellaneous)(HPC) (420-7162) | CY | 11.50 | $3,000.00 | $2,700.00 | $2,850.00 | $642.00 | $5,900.00 |
| 39 | Approach slab (HPC) (422-7014) | CY | 101.20 | $1,300.00 | $1,400.00 | $680.00 | $1,350.00 | $1,500.00 |
| 40 | Riprap (concrete)(5 in) (432-7002) | CY | 127.80 | $265.00 | $1,000.00 | $950.00 | $1,175.00 | $850.00 |
| 41 | Riprap (stone protection)(15 in) (432-7042) | CY | 1,850 | $350.00 | $350.00 | $225.00 | $356.00 | $465.00 |
| 42 | Riprap (stone protection)(18 in) (432-7043) | CY | 430 | $375.00 | $400.00 | $235.00 | $593.00 | $475.00 |
| 43 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 410,000 | $8.00 | $10.00 | $13.50 | $9.00 | $9.90 |
| 44 | STR steel (miscellaneous non-bridge) (truss) (442-7019) | LB | 80,820 | $8.00 | $20.00 | $13.50 | $18.00 | $9.50 |
| 45 | RC pipe (CL III)(30 in) (464-7007) | LF | 38 | $300.00 | $350.00 | $120.00 | $390.00 | $245.00 |
| 46 | Headwall (CH - PW - 0) (diameter= 30 in) (466-7103) | EACH | 1 | $10,000 | $15,000 | $12,000 | $18,729 | $12,250 |
| 47 | Removing structure (set) (496-7004) | EACH | 1 | $2,500.00 | $500.00 | $600.00 | $1,127.00 | $1,500.00 |
| 48 | Removing structure (pipe) (496-7007) | LF | 4 | $500.00 | $150.00 | $100.00 | $46.00 | $380.00 |
| 49 | Removing structure (ret wall) (496-7019) | LF | 780 | $200.00 | $175.00 | $75.00 | $321.00 | $90.00 |
| 50 | Remove STR (piling) (496-7023) | LF | 1,440 | $100.00 | $150.00 | $110.00 | $53.00 | $215.00 |
| 51 | Removing structure (dolphin and fender sys) (496-7031) | EACH | 19 | $40,000 | $19,000 | $23,000 | $11,322 | $22,000 |
| 52 | Removing rock riprap (496-7040) | LF | 864 | $250.00 | $150.00 | $50.00 | $350.00 | $500.00 |
| 53 | Mobilization (500-7001) | LS | 1 | $4,200,000 | $4,076,800 | $4,500,000 | $809,647 | $4,700,000 |
| 54 | Barricades, signs and traffic handling (502-7001) | MO | 39 | $1,000.00 | $500.00 | $39,650 | $1,996.00 | $2,500.00 |
| 55 | Portable changeable message sign (503-7002) | EACH | 1 | $38,000 | $20,000 | $150,000 | $2,649.00 | $28,414 |
| 56 | Temporary sediment control fence (install) (506-7039) | LF | 1,000 | $6.00 | $1.00 | $4.00 | $8.00 | $9.00 |
| 57 | Temporary sediment control fence (remove) (506-7041) | LF | 1,000 | $2.00 | $1.00 | $1.00 | $4.00 | $1.50 |
| 58 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 300 | $150.00 | $200.00 | $350.00 | $119.00 | $200.00 |
| 59 | Driveways (ACP) (530-7010) | SY | 101 | $60.00 | $112.00 | $105.00 | $283.00 | $190.00 |
| 60 | Concrete sidewalks (5") (531-7002) | SY | 234 | $150.00 | $220.00 | $70.00 | $144.00 | $125.00 |
| 61 | Curb ramps (type 10) (531-7011) | EACH | 3 | $3,000.00 | $2,200.00 | $3,200.00 | $6,540.00 | $5,100.00 |
| 62 | Chain link fence (install) (6') (550-7001) | LF | 186 | $45.00 | $120.00 | $55.00 | $107.00 | $120.00 |
| 63 | Gate (special) (552-7009) | EACH | 4 | $45,000 | $106,000 | $75,000 | $40,573 | $135,000 |
| 64 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 2 | $2,000.00 | $765.00 | $1,250.00 | $1,576.00 | $1,850.00 |
| 65 | Reflectorized pavement marking type I (W)12"(solid)(090MIL) (666-7029) | LF | 662 | $12.00 | $12.00 | $12.00 | $13.00 | $11.00 |
| 66 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 492 | $15.00 | $15.00 | $15.00 | $18.00 | $21.00 |
| 67 | Pavement sler 12" (666-7350) | LF | 662 | $1.50 | $1.00 | $1.50 | $5.00 | $1.75 |
| 68 | Pavement sler 24" (666-7352) | LF | 492 | $2.00 | $1.00 | $3.50 | $6.00 | $2.25 |
| 69 | Rep steel sheave assembly (784-7026) | EACH | 8 | $40,000 | $30,000 | $25,000 | $14,830 | $3,250.00 |
| 70 | 8" laminated fender wrap (4061-7001) | SF | 2,805 | $350.00 | $235.00 | $180.00 | $223.00 | $215.00 |
| 71 | Ornamental fence (4062-7001) | LF | 436 | $100.00 | $205.00 | $145.00 | $205.00 | $260.00 |
| 72 | Ornamental fence (gate) (4062-7002) | EACH | 3 | $2,000.00 | $13,000 | $10,800 | $41,053 | $16,500 |
| 73 | 72IN donut fender (4063-7001) | EACH | 8 | $125,000 | $106,000 | $200,000 | $161,321 | $155,000 |
| 74 | 108" donut fender (4063-7002) | EACH | 2 | $150,000 | $148,000 | $275,000 | $221,827 | $208,000 |
| 75 | Transfer ramps (4065-7001) | EACH | 4 | $1,000,000 | $975,000 | $1,000,000 | $1,356,880 | $1,250,000 |
| 76 | Hydraulic PWR sys (7088-7001) | LS | 1 | $2,500,000 | $2,850,000 | $2,750,000 | $4,226,321 | $1,150,000 |
| 77 | Ferry electrical sys rehab (7089-7001) | LS | 1 | $7,000,000 | $5,880,000 | $8,000,000 | $7,377,712 | $5,543,000 |
| 78 | Mobile fuel cell transfer system (7090-7001) | LS | 1 | $10,000 | $12,000 | $100,000 | $889,752 | $25,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 7, 2026. Compiled by Mirage Metrics.