TxDOT contract A00133629 bid tabulation
Highway Improvement, SH 6 (FM 2534, South to One Block North of SH 222). Let by Texas DOT on February 6, 2025, Knox, Childress District. 5 bids received; low bid $4,478,136 by Zack Burkett Co., -22% against the engineer's estimate of $5,728,332.
- Owner
- Texas DOT
- Letting
- 06 FEB 2025
- Pay items
- 41
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Zack Burkett Co. | $4,478,136 | Low | -22% |
| 2 | A. L. Helmcamp, Inc. | $4,492,178 | 0.0% | -22% |
| 3 | RK Hall, LLC | $4,508,967 | +1.0% | -21% |
| 4 | Duininck, Inc. | $4,690,932 | +5.0% | -18% |
| 5 | J. Lee Milligan, Inc. | $5,599,490 | +25% | -2.0% |
Engineer's estimate: $5,728,332.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Zack Burkett Co. | 2. A. L. Helmcamp, Inc. | 3. RK Hall, LLC | 4. Duininck, Inc. | 5. J. Lee Milligan, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (driveways) (104-7011) | SY | 40 | $36.90 | $35.00 | $32.10 | $35.00 | $35.00 | |
| 2 | Remove (0"-4") TRT/untrt base & asphalt pavement (105-7060) | CY | 182 | $10.00 | $75.00 | $55.00 | $26.79 | $60.00 | $55.00 |
| 3 | Excavation (channel) (110-7002) | CY | 2,713 | $25.00 | $39.25 | $27.00 | $15.51 | $27.50 | $26.50 |
| 4 | Embankment (final)(OC)(type B) (132-7003) | CY | 32 | $38.50 | $100.00 | $147.00 | $80.70 | $40.00 | $105.00 |
| 5 | Backfill (type A or B) (134-7004) | STA | 257 | $42.00 | $275.00 | $430.00 | $130.99 | $135.00 | $340.00 |
| 6 | Drill seed (permanent_rural_sand) (164-7041) | ACRE | 12.54 | $0.26 | $891.75 | $690.00 | $700.85 | $690.00 | $695.00 |
| 7 | Vegetative watering (168-7001) | TGL | 964.60 | $36.76 | $50.00 | $15.00 | $52.18 | $27.50 | $40.00 |
| 8 | Emuls asphalt (erosion control)(CSS-1H) (314-7011) | GAL | 11,494 | $4.40 | $3.65 | $4.50 | $3.27 | $3.90 | $5.00 |
| 9 | D-GR HMA type D sac-A PG70-28 (341-7053) | TON | 19,534 | $180.00 | $147.80 | $149.25 | $151.12 | $154.10 | $175.00 |
| 10 | D-GR HMA type D PG70-28 (level-UP) (341-7055) | TON | 40 | $111.00 | $165.00 | $395.00 | $172.70 | $210.00 | $275.00 |
| 11 | Tack coat (341-7082) | GAL | 17,744 | $5.00 | $5.05 | $4.00 | $5.26 | $2.55 | $4.95 |
| 12 | Flexible pavement structure repair(3") (351-7002) | SY | 8,667 | $70.00 | $37.50 | $40.00 | $31.39 | $37.00 | $50.00 |
| 13 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 4,986 | $3.00 | $4.00 | $8.00 | $4.03 | $3.50 | $3.40 |
| 14 | Planing asphalt concrete pavement(2") (354-7051) | SY | 48,168 | $3.50 | $2.44 | $2.00 | $2.67 | $3.25 | $3.50 |
| 15 | Riprap (mow strip)(4 in) (432-7013) | CY | 24 | $650.00 | $922.50 | $800.00 | $882.75 | $795.00 | $1,320.00 |
| 16 | Rail (handrail)(type B) (450-7059) | LF | 40 | $130.00 | $273.06 | $320.00 | $237.54 | $315.00 | $315.00 |
| 17 | CMP AR (gal steel des 3) (460-7018) | LF | 480 | $150.00 | $110.70 | $100.00 | $107.00 | $95.00 | $95.00 |
| 18 | Set (type II) (des 3) (CMP) (6: 1) (P) (467-7430) | EACH | 32 | $2,140.00 | $1,845.00 | $1,600.00 | $1,284.00 | $1,600.00 | $1,600.00 |
| 19 | Mobilization (500-7001) | LS | 1 | $535,760 | $282,285 | $288,000 | $421,800 | $430,000 | $559,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $30,000 | $4,838.00 | $15,000 | $11,467 | $25,500 | $35,000 |
| 21 | TMA (stationary) (505-7001) | DAY | 76 | $327.00 | $307.50 | $200.00 | $445.65 | $265.00 | $600.00 |
| 22 | TMA (mobile operation) (505-7002) | HR | 20 | $68.00 | $1.00 | $100.00 | $101.52 | $110.00 | $115.00 |
| 23 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 1,440 | $9.00 | $8.61 | $5.80 | $6.21 | $6.15 | $10.00 |
| 24 | Concrete curb & gutter (type II) (529-7009) | LF | 144 | $79.95 | $75.00 | $80.25 | $68.50 | $70.00 | |
| 25 | Driveways (concrete) (530-7006) | SY | 287 | $75.00 | $147.60 | $140.00 | $133.75 | $125.00 | $130.00 |
| 26 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 45,232 | $1.40 | $0.41 | $0.28 | $0.12 | $0.12 | $0.40 |
| 27 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 22,616 | $1.00 | $0.52 | $0.28 | $0.12 | $0.16 | $0.44 |
| 28 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 124 | $100.00 | $135.30 | $110.00 | $117.70 | $115.00 | $120.00 |
| 29 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,266.00 | $3,997.50 | $3,600.00 | $3,477.50 | $3,400.00 | $3,450.00 |
| 30 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 12 | $37.10 | $43.05 | $45.00 | $37.45 | $37.00 | $37.00 |
| 31 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 310 | $1.20 | $0.50 | $2.52 | $1.55 | $1.65 | |
| 32 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 3,060 | $1.70 | $1.20 | $0.50 | $2.68 | $1.55 | $1.70 |
| 33 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 114 | $9.84 | $3.70 | $3.75 | $3.70 | $3.70 | |
| 34 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 218 | $8.60 | $19.68 | $13.00 | $12.84 | $12.50 | $12.70 |
| 35 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 7 | $246.00 | $290.00 | $294.25 | $290.00 | $290.00 | |
| 36 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 3 | $369.00 | $290.00 | $294.25 | $290.00 | $290.00 | |
| 37 | Reflectorized pavement marking type I (W)4"(solid)(100MIL) (666-7405) | LF | 3,040 | $1.20 | $3.08 | $3.70 | $3.75 | $3.70 | $3.70 |
| 38 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 66,660 | $0.58 | $0.80 | $0.60 | $0.63 | $0.62 | $0.65 |
| 39 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 6,207 | $0.85 | $0.92 | $0.60 | $0.63 | $0.62 | $0.65 |
| 40 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 29,974 | $0.85 | $0.80 | $0.60 | $0.63 | $0.62 | $0.65 |
| 41 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 814 | $6.00 | $6.15 | $4.70 | $4.82 | $4.75 | $4.75 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.