TxDOT contract A00139041 bid tabulation
Bridge Replacement, SISTER GROVE RD (Sister Grove Road to At West Prong Sister Grove Creek). Let by Texas DOT on January 8, 2025, Grayson, Paris District. 6 bids received; low bid $1,816,247 by THK Construction LLC, +5.4% against the engineer's estimate of $1,723,647.
- Owner
- Texas DOT
- Letting
- 08 JAN 2025
- Pay items
- 40
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | THK Construction LLC | $1,816,247 | Low | +5.0% |
| 2 | Skyline Bridge LLC | $1,972,279 | +9.0% | +14% |
| 3 | Hodges and Son Construction Company, Inc. | $2,080,627 | +15% | +21% |
| 4 | East Texas Bridge, Inc. | $2,110,555 | +16% | +22% |
| 5 | STX Civil | $2,372,880 | +31% | +38% |
| 6 | Talbert Companies LLC | $2,426,584 | +34% | +41% |
Engineer's estimate: $1,723,647.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. THK Construction LLC | 2. Skyline Bridge LLC | 3. Hodges and Son Construction Company, Inc. | 4. East Texas Bridge, Inc. | 5. STX Civil | 6. Talbert Companies LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 13.80 | $3,294.00 | $12,185 | $3,300.00 | $4,500.00 | $6,000.00 | $5,200.00 | $7,560.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 941 | $20.25 | $18.00 | $15.00 | $20.00 | $25.00 | $28.50 | $34.50 |
| 3 | Excavation (channel) (110-7002) | CY | 2,134 | $17.00 | $15.00 | $12.00 | $20.00 | $25.00 | $18.00 | $60.37 |
| 4 | Embankment (final)(OC)(type B) (132-7003) | CY | 726 | $33.00 | $20.00 | $40.00 | $25.00 | $35.00 | $33.00 | $101.02 |
| 5 | Broadcast seed (temporary_warm) (164-7005) | SY | 3,661 | $0.40 | $0.54 | $1.50 | $1.20 | $0.55 | $0.10 | $0.32 |
| 6 | Broadcast seed (temporary_cool) (164-7006) | SY | 3,661 | $0.30 | $0.54 | $1.50 | $1.20 | $0.55 | $0.15 | $0.32 |
| 7 | Hydro mulch seed (permanent_rural_clay) (164-7018) | SY | 7,322 | $0.55 | $0.65 | $1.50 | $1.50 | $0.75 | $0.75 | $0.59 |
| 8 | Vegetative watering (168-7001) | TGL | 89 | $57.10 | $20.00 | $1.00 | $1.00 | $20.00 | $60.00 | $86.40 |
| 9 | FL BS (compacted in place)(type A GR 4) (6") (247-7046) | SY | 1,823 | $40.00 | $40.00 | $50.00 | $30.00 | $20.00 | $51.84 | |
| 10 | Rework BS metal (type B)(6")(ord comp) (251-7025) | SY | 1,002 | $3.15 | $40.00 | $20.00 | $15.00 | $25.00 | $3.50 | $10.80 |
| 11 | D-GR HMA type-C PG64-22 (341-7015) | TON | 221 | $250.00 | $248.46 | $275.00 | $250.00 | $300.00 | $270.00 | $238.68 |
| 12 | Cem stabil BKFL (400-7010) | CY | 155 | $93.25 | $297.00 | $300.00 | $275.00 | $300.00 | $270.00 | $194.40 |
| 13 | Drilled shaft (24 in) (416-7004) | LF | 525 | $199.29 | $325.00 | $160.00 | $235.00 | $668.66 | $189.00 | |
| 14 | Drilled shaft (30 in) (416-7005) | LF | 285 | $303.40 | $240.35 | $400.00 | $245.00 | $265.00 | $1,077.31 | $221.40 |
| 15 | Class C concrete (abutment) (420-7012) | CY | 75.20 | $1,363.75 | $1,100.00 | $1,250.00 | $2,000.00 | $1,600.00 | $1,200.00 | $1,425.81 |
| 16 | Reinforced concrete slab (box beam) (422-7005) | SF | 2,355 | $20.70 | $24.00 | $28.00 | $30.00 | $27.00 | $22.00 | $25.44 |
| 17 | Reinforced concrete slab (slab beam) (422-7007) | SF | 2,470 | $22.00 | $28.00 | $40.00 | $26.00 | $26.33 | $26.61 | |
| 18 | Shear key (422-7020) | CY | 24.10 | $358.40 | $800.00 | $900.00 | $800.00 | $850.00 | $580.00 | $618.49 |
| 19 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 469.91 | $309.00 | $350.00 | $425.00 | $365.00 | $250.00 | $220.64 | |
| 20 | Prestressed concrete box beam (4B34) (425-7030) | LF | 358 | $250.00 | $377.00 | $450.00 | $435.00 | $400.00 | $485.00 | $313.90 |
| 21 | Prestressed concrete box beam (5B34) (425-7031) | LF | 179 | $250.00 | $377.00 | $550.00 | $435.00 | $400.00 | $495.00 | $313.90 |
| 22 | Riprap (stone protection)(18 in) (432-7043) | CY | 1,596 | $195.40 | $168.00 | $185.00 | $220.00 | $200.00 | $200.00 | $199.80 |
| 23 | Rail (type T631LS) (450-7021) | LF | 462 | $67.50 | $67.50 | $95.00 | $70.00 | $70.00 | $83.69 | $72.90 |
| 24 | RC pipe (CL III)(24 in) (464-7005) | LF | 40 | $100.00 | $130.00 | $120.00 | $125.00 | $140.00 | $102.06 | |
| 25 | RC pipe (CL III)(36 in) (464-7009) | LF | 40 | $160.00 | $200.00 | $180.00 | $250.00 | $245.00 | $204.12 | |
| 26 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $1,800.00 | $2,500.00 | $4,000.00 | $3,000.00 | $2,600.00 | $3,199.50 | |
| 27 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 2 | $4,000.00 | $5,000.00 | $6,000.00 | $6,500.00 | $8,400.00 | $6,423.30 | |
| 28 | Removing structure (pipe) (496-7007) | LF | 74 | $20.00 | $15.00 | $20.00 | $35.00 | $65.84 | $48.45 | |
| 29 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 3 | $26,020 | $5,000.00 | $15,000 | $30,000 | $35,000 | $25,000 | $21,600 |
| 30 | Mobilization (500-7001) | LS | 1 | $156,695 | $180,000 | $150,000 | $175,000 | $210,000 | $180,526 | $460,000 |
| 31 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $6,435.00 | $899.81 | $2,800.00 | $4,300.00 | $5,000.00 | $2,547.50 | $14,854 |
| 32 | Rock filter dams (install) (type 2) (506-7002) | LF | 156 | $125.00 | $64.80 | $45.00 | $1.00 | $65.00 | $72.20 | $57.24 |
| 33 | Rock filter dams (remove) (506-7011) | LF | 156 | $35.00 | $15.12 | $8.00 | $1.00 | $15.00 | $16.85 | $25.92 |
| 34 | Construction exits (install) (type 1) (506-7020) | SY | 468 | $34.50 | $43.20 | $10.00 | $1.00 | $45.00 | $48.13 | $37.80 |
| 35 | Construction exits (remove) (506-7024) | SY | 468 | $9.30 | $10.80 | $1.00 | $1.00 | $10.00 | $12.03 | $10.00 |
| 36 | Temporary sediment control fence (install) (506-7039) | LF | 2,232 | $4.05 | $4.59 | $4.00 | $1.00 | $4.70 | $5.11 | $3.78 |
| 37 | Temporary sediment control fence (remove) (506-7041) | LF | 2,232 | $1.20 | $0.60 | $1.50 | $1.00 | $0.75 | $0.66 | $1.08 |
| 38 | Metal W-beam guard fence (steel post) (540-7002) | LF | 300 | $32.00 | $27.54 | $30.00 | $26.00 | $30.00 | $32.11 | $31.86 |
| 39 | Guardrail end treatment (install) (544-7001) | EACH | 12 | $3,210.00 | $3,168.00 | $3,250.00 | $3,000.00 | $3,200.00 | $3,740.00 | $3,137.40 |
| 40 | Install delineator assembly (D-SW)SZ 1(WFLX)GF2(BI) (658-7002) | EACH | 54 | $45.45 | $27.00 | $50.00 | $25.00 | $35.00 | $30.08 | $70.20 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.