TxDOT contract A00139936 bid tabulation

Install/Upgrade Drainage Structure(S), SH 27 (At Irene Creek to .). Let by Texas DOT on April 3, 2025, Kerr, San Antonio District. 7 bids received; low bid $1,403,742 by Acee Construction LLC., -44% against the engineer's estimate of $2,512,371.

Owner
Texas DOT
Letting
03 APR 2025
Pay items
101
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Acee Construction LLC.$1,403,742Low-44%
2MPB, Inc.$1,730,872+23%-31%
3Dan Williams Company$1,877,364+34%-25%
4Acme Bridge Company, Inc.$2,185,879+56%-13%
5Hunter Industries, LTD.$2,304,308+64%-8.0%
6STX Civil$2,421,453+72%-4.0%
7Icos Management, LLC$2,672,864+90%+6.0%
TxDOT contract A00139936: bids by rank

Engineer's estimate: $2,512,371.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Acee Construction LLC.2. MPB, Inc.3. Dan Williams Company4. Acme Bridge Company, Inc.5. Hunter Industries, LTD.6. STX Civil
1Preparing row (100-7001)ACRE0.49$10,000$5,500.00$6,500.00$200,000$20,618$21,100$20,000
2Removing concrete (riprap) (104-7006)SY320$12.00$12.50$10.00$20.00$36.90$42.00$30.00
3Removing stab base and asphalt pavement(0"-16") (105-7129)SY79$10.00$20.00$55.00$50.00$106.00$38.50$25.00
4Excavation (roadway) (110-7001)CY27$13.74$50.00$85.00$50.00$134.00$77.00$40.00
5Excavation (channel) (110-7002)CY783$12.00$25.00$18.00$40.00$46.90$77.00$40.00
6Embankment (final)(OC)(type C) (132-7005)CY28$30.00$55.00$165.00$55.00$238.00$77.00$50.00
7Blading (150-7002)HR10$65.85$180.00$65.00$43.40$144.00$100.00
8Straw/hay mulch seed(permanent_rural_clay) (164-7026)SY3,096$1.50$1.00$5.00$1.40$1.36$6.00
9Vegetative watering (168-7001)TGL49$35.70$300.00$15.00$143.00$31.50$50.00
10Soil ret BLKT(chan_temporary_4 PSF) (169-7030)SY526$4.75$5.25$8.00$4.80$4.64$10.00
11Asphalt (AC-15P or CRS-2P) (316-7078)GAL1,070$7.50$6.30$22.00$9.40$9.20$25.00
12Aggregate (type-PB, GR-4)(sac-B) (316-7211)CY31$241.00$735.00$450.00$652.00$553.55$900.00
13D-GR HMA type-B PG64-22 (exempt) (341-7003)TON195$133.00$205.00$315.00$210.00$338.00$220.00$200.00
14D-GR HMA type-C sac-B PG70-22 (exempt) (341-7037)TON112$190.79$205.00$331.00$235.00$355.00$225.50$400.00
15Planing asphalt concrete pavement(0" to 2") (354-7032)SY973$2.60$4.50$10.50$14.00$11.30$9.04$25.00
16Cut & restore asphalt paving (400-7008)SY150$107.50$140.00$185.00$128.00$239.66$350.00
17Cem stabil BKFL (400-7010)CY154$161.76$142.50$95.00$250.00$390.00$324.00$250.00
18Flowable backfill (401-7001)CY40$250.00$145.00$150.00$265.00$225.00$324.00$300.00
19Trench excavation protection (402-7001)LF220$5.00$8.50$17.00$1.00$156.00$34.56$20.00
20Temporary special shoring (403-7001)SF1,430$25.00$20.00$106.00$25.00$56.40$70.20$75.00
21Class C concrete (cap) (420-7022)CY1$1,075.00$850.00$650.00$1,200.00$4,270.00$1,943.99$5,000.00
22Riprap (concrete)(4 in) (432-7001)CY21$350.00$495.00$645.00$625.00$1,060.00$674.99$900.00
23Riprap (concrete)(5 in) (432-7002)CY105.10$479.00$505.00$460.00$600.00$932.00$669.59$1,000.00
24Rail (type C1W) (450-7030)LF91.72$227.24$532.00$550.00$400.00$741.00$430.92$600.00
25Gabion mattresses (galvanized)(9 in) (459-7006)SY100$120.00$168.00$200.00$121.00$136.00$100.00
26Gabion (1.5' X 3')(galvanized) (459-7014)CY18$120.00$265.00$300.00$480.00$650.00$200.00
27Concrete box culvert (6 FT X 5 FT) (462-7013)LF73$654.59$785.00$1,650.00$1,000.00$1,160.00$944.45$1,100.00
28Concrete box culvert (7 FT X 3 FT) (462-7015)LF210$615.00$450.00$900.00$1,170.00$1,037.49$1,300.00
29Concrete box culvert (12 FT X 5 FT) (462-7048)LF73$1,586.98$3,250.00$2,700.00$2,000.00$2,660.00$3,197.86$2,500.00
30RC pipe (CL III)(36 in) (464-7009)LF82$188.74$151.50$165.00$165.00$232.00$118.80$300.00
31Wingwall (PW - 1) (HW=9 FT) (466-7179)EACH2$45,872$38,500$40,000$50,000$54,300$38,121$60,000
32Set (type I)(S= 7 FT)(HW= 4 FT)(4:1)(C) (467-7154)EACH10$9,750.00$5,425.00$7,500.00$8,340.00$11,312$20,000
33Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368)EACH2$4,963.33$4,499.95$5,200.00$6,000.00$9,130.00$6,543.67$10,000
34Removing structure (manhole) (496-7003)EACH1$1,360.43$500.00$500.00$1,800.00$1,050.00$782.19$1,000.00
35Removing structure (set) (496-7004)EACH2$607.89$350.00$250.00$650.00$409.00$669.59$250.00
36Removing structure (wingwall) (496-7005)EACH2$1,838.72$330.75$500.00$1,850.00$843.00$1,564.39$2,500.00
37Removing structure (pipe) (496-7007)LF643$26.00$21.80$9.25$25.00$17.90$59.40$20.00
38Remove STR (rail) (496-7017)LF60$15.00$15.20$5.75$12.00$22.30$12.50$50.00
39Mobilization (500-7001)LS1$1,256,475$137,500$150,000$180,000$195,000$230,367$220,000
40Barricades, signs and traffic handling (502-7001)MO8$5,000.00$5,500.00$5,000.00$20,000$6,470.00$20,270$10,000
41Portable changeable message sign (503-7001)DAY70$89.01$80.00$75.00$150.00$358.00$169.17$60.00
42Rock filter dams (install) (type 2) (506-7002)LF228$35.00$47.90$47.25$45.00$55.60$53.79$70.00
43Rock filter dams (remove) (506-7011)LF228$14.83$5.30$5.25$5.00$12.40$12.00$10.00
44Construction exits (install) (type 1) (506-7020)SY314$25.00$29.80$29.50$28.00$31.30$30.30$60.00
45Construction exits (remove) (506-7024)SY314$7.97$2.65$2.65$2.50$10.00$9.70$22.00
46Temporary sediment control fence (install) (506-7039)LF920$4.75$4.75$4.45$5.10$4.90$7.00
47Temporary sediment control fence (remove) (506-7041)LF920$0.95$1.00$1.00$1.70$1.65$2.50
48Constructing detours (508-7001)SY392$56.60$205.00$100.00$166.00$253.00$200.00
49One-way traffic control (port traffic signal) (510-7003)MO3$5,000.00$4,850.00$3,500.00$5,200.00$11,588$7,500.00
50Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF210$26.50$140.00$45.00$152.00$115.00$160.00
51Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF360$200.00$26.80$110.00$30.00$40.30$75.00$100.00
52Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF80$140.00$25.05$105.00$30.00$53.40$85.00$100.00
53Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF210$10.00$40.00$15.00$17.80$70.00$30.00
54Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF220$10.00$10.00$28.00$15.00$13.80$80.00$30.00
55Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF40$20.00$10.00$40.00$15.00$28.10$125.00$30.00
56Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF210$12.50$62.00$35.00$48.80$95.00$105.00
57Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF360$30.00$12.50$31.00$25.00$30.50$55.00$30.00
58Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF80$23.92$12.50$20.00$25.00$51.30$65.00$30.00
59Concrete curb (type I) (529-7001)LF179$20.00$12.15$41.00$30.00$45.70$34.56$100.00
60Driveways (concrete) (530-7006)SY67$101.21$99.65$157.00$110.00$205.00$128.52$150.00
61Driveways (ACP) (530-7010)SY12$50.43$325.80$350.00$165.00$372.00$101.20$110.00
62Concrete sidewalks (4") (531-7001)SY101$70.14$62.50$130.00$85.00$143.00$97.20$100.00
63Crash cushion attenuator (move & reset) (545-7002)EACH2$750.00$1,500.00$2,000.00$2,900.00$875.00$1,500.00
64Crash cushion attenuator (remove) (545-7004)EACH2$650.00$650.00$2,000.00$1,010.00$800.00$1,000.00
65Crash cushion attenuator (install)(R)(N)(TL2) (545-7009)EACH1$20,233$20,000$30,000$30,000$30,900$25,750$20,000
66Crash cushion attenuator (install)(S)(N)(TL2) (545-7013)EACH2$6,750.00$8,750.00$8,500.00$11,100$7,700.00$9,000.00
67Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH2$182.90$100.00$200.00$84.60$97.58$100.00
68Work zone pavement marking removing (W)4"(DOT) (662-7062)LF144$1.66$3.70$3.68$3.50$2.55$2.40$4.50
69Work zone pavement marking removing (W)4"(solid) (662-7064)LF4,424$0.50$2.05$2.05$1.95$2.55$2.40$2.50
70Work zone pavement marking removing (W)24"(solid) (662-7077)LF24$15.75$15.75$15.00$11.30$10.65$18.00
71Work zone pavement marking removing (Y)4"(solid) (662-7097)LF7,860$0.46$2.05$2.05$1.95$2.55$2.40$2.50
72Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH24$1.64$3.55$5.00$2.26$2.20$1.69$2.50
73Work zone pavement marking SHT terminal (tab)type Y (662-7113)EACH40$1.38$2.75$5.00$2.26$2.20$1.69$2.50
74Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH28$3.25$5.00$2.26$2.20$1.69$3.00
75Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF237$1.00$2.15$2.10$2.00$2.80$2.66$2.50
76Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF205$8.90$13.15$13.13$12.50$11.30$10.65$15.00
77Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH2$186.09$262.50$262.50$250.00$225.00$213.03$303.00
78Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH2$232.22$288.75$288.75$275.00$254.00$239.66$333.00
79Pavement sler 6" (666-7347)LF9,134$0.32$1.00$1.00$1.00$0.56$0.53$1.50
80Pavement sler 8" (666-7348)LF237$0.43$1.60$1.58$1.50$0.85$0.80$2.00
81Pavement sler 24" (666-7352)LF205$1.82$5.80$5.78$5.50$3.40$3.20$7.00
82Pavement sler (arrow) (666-7353)EACH2$51.68$105.00$105.00$100.00$113.00$106.52$121.00
83Pavement sler (word) (666-7354)EACH2$45.71$105.00$105.00$100.00$113.00$106.52$121.00
84Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF970$0.60$1.60$1.58$1.50$1.40$1.33$2.00
85Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF2,200$1.30$1.32$1.25$1.40$1.33$1.50
86Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF1,049$0.48$1.60$1.16$1.50$1.40$1.33$2.00
87Reflectorized pavement marking type I (Y)6"(solid)(060MIL) (666-7421)LF3,815$0.36$1.15$1.16$1.10$1.30$1.22$1.50
88Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF1,100$1.30$1.32$1.25$1.40$1.33$1.50
89Reflectorized pavement marker type II-A-A (672-7004)EACH28$10.50$10.50$10.00$5.60$5.33$12.00
90Eliminating existing PM & markers (4") (677-7001)LF5,074$0.75$1.60$1.58$1.50$1.15$1.07$2.00
91Underseal course (3006-7001)GAL195$4.38$4.50$14.70$25.00$15.80$5.75$15.00
92Hydrostatic pressure test (7044-7001)EACH1$2,500.00$1,500.00$1,000.00$6,000.00$5,000.00$3,500.00$8,000.00
93Remove 8" water line (7044-7002)LF100$12.00$15.00$25.00$25.00$33.80$25.00$35.00
94Tie in (complete)(8") (7044-7003)EACH2$2,200.00$2,500.00$500.00$4,000.00$5,000.00$3,500.00$5,000.00
95Pipe WTR main (PVC/C-900) (8IN.) (7044-7004)LF56$95.00$80.00$100.00$325.00$500.00$125.00$120.00
96Ductile iron fittings (7044-7005)TON1.80$6,500.00$2,500.00$1,000.00$7,500.00$15,000$8,500.00$9,000.00
97Carrier pipe 8" (open cut trench) (8") (7044-7006)LF44$115.00$85.00$250.00$185.00$300.00$100.00$130.00
98Temporary blow-off complete (2") (7044-7007)EACH2$1,800.00$2,850.00$1,000.00$5,000.00$1,000.00$3,750.00$5,250.00
99Gate valve & box (complete) (8") (7044-7008)EACH2$6,500.00$2,950.00$2,250.00$6,500.00$5,000.00$27,500$6,200.00
10024" steel casing (7044-7009)LF44$155.00$200.00$100.00$325.00$500.00$450.00$400.00
101Trench excavation protection (7044-7010)LF100$5.00$8.50$60.00$1.00$30.00$15.00$20.00
TxDOT contract A00139936: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of April 3, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy