TxDOT contract A00155357 bid tabulation
BRIDGE PREVENTATIVE MAINTENANCE, FM1535 (FM 1535 AT UNNAMED DRAW to AND SH 16 AT COMANCHE CREEK). Let by Texas DOT on January 16, 2025, Bexar, San Antonio District. 8 bids received; low bid $218,588 by Diamond R Contracting, LLC, -13% against the engineer's estimate of $251,787.
- Owner
- Texas DOT
- Letting
- 16 JAN 2025
- Pay items
- 32
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Diamond R Contracting, LLC | $218,588 | Low | -13% |
| 2 | BK Field Operations LLC | $229,938 | +5.0% | -9.0% |
| 3 | Rhino Equity, LLC | $283,142 | +30% | +12% |
| 4 | Garret Shields Infrastructure | $297,060 | +36% | +18% |
| 5 | Lakey, Inc. | $317,751 | +45% | +26% |
| 6 | Myers Concrete Construction, LP | $382,348 | +75% | +52% |
| 7 | Dan Williams Company | $425,510 | +95% | +69% |
| 8 | Salinas Construction Technologies, LTD. | $498,144 | +128% | +98% |
Engineer's estimate: $251,787.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Diamond R Contracting, LLC | 2. BK Field Operations LLC | 3. Rhino Equity, LLC | 4. Garret Shields Infrastructure | 5. Lakey, Inc. | 6. Myers Concrete Construction, LP |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7007) | CY | 35 | $527.51 | $300.00 | $200.00 | $100.00 | $100.00 | $110.00 | $144.00 |
| 2 | Removing concrete (miscellaneous) (104-7047) | CY | 7 | $150.00 | $1,000.00 | $200.00 | $100.00 | $100.00 | $150.00 | $164.00 |
| 3 | Embankment (final)(OC)(type B) (132-7003) | CY | 283 | $14.00 | $50.00 | $40.00 | $45.00 | $40.00 | $30.00 | $61.00 |
| 4 | Compost manuf topsoil (4") (161-7002) | SY | 500 | $9.00 | $1.00 | $4.00 | $6.00 | $5.00 | $6.00 | $14.00 |
| 5 | Broadcast seed (permanent_urban_clay) (164-7004) | SY | 500 | $0.62 | $1.00 | $1.00 | $2.00 | $1.00 | $1.00 | $2.00 |
| 6 | Soil ret BLKT(SL_mod_clay_short) (169-7001) | SY | 500 | $4.39 | $1.00 | $5.00 | $4.00 | $1.00 | $2.00 | $9.00 |
| 7 | Flowable backfill (401-7001) | CY | 49 | $270.00 | $200.00 | $400.00 | $400.00 | $500.00 | $385.00 | $340.00 |
| 8 | Temporary special shoring (403-7001) | SF | 400 | $25.00 | $30.00 | $4.00 | $12.00 | $60.00 | $40.00 | $24.00 |
| 9 | Class C concrete (miscellaneous) (420-7067) | CY | 2 | $1,777.32 | $1,000.00 | $3,000.00 | $1,000.00 | $1,000.00 | $1,500.00 | $3,594.00 |
| 10 | Riprap (concrete)(5 in) (432-7002) | CY | 42 | $500.00 | $1,000.00 | $550.00 | $800.00 | $500.00 | $450.00 | $872.00 |
| 11 | Gabion mattresses (galvanized)(12 in) (459-7007) | SY | 199 | $114.95 | $60.00 | $140.00 | $85.00 | $125.00 | $156.00 | $136.00 |
| 12 | Gabions (3' X 3')(galvanized) (459-7010) | CY | 50 | $450.00 | $150.00 | $220.00 | $290.00 | $300.00 | $450.00 | $615.00 |
| 13 | Gabions (5'X 3')(galvanized) (459-7012) | CY | 82 | $222.00 | $150.00 | $250.00 | $290.00 | $280.00 | $450.00 | $389.00 |
| 14 | Gabion (1.5' X 3')(galvanized) (459-7014) | CY | 97 | $210.00 | $150.00 | $230.00 | $290.00 | $280.00 | $450.00 | $342.00 |
| 15 | Clean existing culverts (480-7001) | EACH | 1 | $2,000.00 | $5,000.00 | $3,000.00 | $4,000.00 | $5,000.00 | $2,000.00 | $4,869.00 |
| 16 | Mobilization (500-7001) | LS | 1 | $18,000 | $25,000 | $19,000 | $40,000 | $20,000 | $49,000 | $32,406 |
| 17 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $3,500.00 | $2,000.00 | $2,000.00 | $5,000.00 | $5,000.00 | $2,500.00 | $3,873.00 |
| 18 | TMA (stationary) (505-7001) | DAY | 50 | $261.58 | $1.00 | $1.00 | $150.00 | $300.00 | $144.00 | $484.00 |
| 19 | Construction exits (install) (type 1) (506-7020) | SY | 224 | $18.00 | $1.00 | $1.00 | $12.00 | $20.00 | $35.00 | $22.00 |
| 20 | Construction exits (remove) (506-7024) | SY | 224 | $8.78 | $1.00 | $1.00 | $6.00 | $10.00 | $12.78 | $12.00 |
| 21 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 100 | $6.10 | $1.00 | $3.00 | $6.00 | $8.00 | $6.60 | $16.00 |
| 22 | Biodegradable erosion control logs (remove) (506-7046) | LF | 100 | $1.59 | $1.00 | $1.00 | $1.00 | $1.00 | $3.15 | $2.00 |
| 23 | Chain link fence (repair) (6') (550-7002) | LF | 80 | $5.00 | $50.00 | $60.00 | $40.00 | $40.00 | $12.50 | $44.00 |
| 24 | Chain link fence (remove) (550-7007) | LF | 85 | $5.00 | $40.00 | $15.00 | $20.00 | $5.00 | $13.00 | $18.00 |
| 25 | Chain link fence(install)(6 )(barb top) (550-7008) | LF | 85 | $55.85 | $50.00 | $100.00 | $30.00 | $100.00 | $120.00 | $53.00 |
| 26 | Driftwood removal (735-7061) | LS | 2 | $8,333.33 | $2,500.00 | $10,000 | $10,000 | $5,000.00 | $3,750.00 | $5,479.00 |
| 27 | Tree trimming / brush removal(channels) (752-7003) | ACRE | 0.20 | $15,000 | $25,000 | $2,500.00 | $5,000.00 | $10,000 | $10,000 | $15,458 |
| 28 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 11 | $394.69 | $500.00 | $100.00 | $300.00 | $500.00 | $185.00 | $838.00 |
| 29 | Tree removal (12" - 18" diameter) (752-7006) | EACH | 3 | $233.36 | $500.00 | $200.00 | $500.00 | $600.00 | $175.00 | $2,047.00 |
| 30 | Tree removal (18" - 24" diameter) (752-7007) | EACH | 5 | $328.57 | $500.00 | $325.00 | $500.00 | $1,000.00 | $275.00 | $1,757.00 |
| 31 | Tree removal (24" - 30" diameter) (752-7008) | EACH | 3 | $434.51 | $500.00 | $450.00 | $700.00 | $1,500.00 | $395.00 | $2,341.00 |
| 32 | Tree removal (30" - 36" diameter) (752-7009) | EACH | 4 | $625.00 | $500.00 | $650.00 | $700.00 | $2,000.00 | $550.00 | $3,071.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 16, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.