TxDOT contract A00183298 bid tabulation
Bicycle And Pedestrian Improvements, SH 36 (BU 83D to FM 1750). Let by Texas DOT on July 1, 2025, Taylor, Abilene District. 5 bids received; low bid $4,169,101 by J. H. Strain & Sons, Inc., +1.8% against the engineer's estimate of $4,094,862.
- Owner
- Texas DOT
- Letting
- 01 JUL 2025
- Pay items
- 78
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | J. H. Strain & Sons, Inc. | $4,169,101 | Low | +2.0% |
| 2 | STX Civil | $4,239,250 | +2.0% | +4.0% |
| 3 | Bontke Brothers Construction Company | $4,686,027 | +12% | +14% |
| 4 | Talbert Companies LLC | $4,711,656 | +13% | +15% |
| 5 | Grey Sky Construction LLC | $5,360,358 | +29% | +31% |
Engineer's estimate: $4,094,862.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. J. H. Strain & Sons, Inc. | 2. STX Civil | 3. Bontke Brothers Construction Company | 4. Talbert Companies LLC | 5. Grey Sky Construction LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 583 | $35.00 | $22.00 | $15.00 | $40.00 | $52.46 | $100.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 1,498 | $20.00 | $25.00 | $18.00 | $40.00 | $55.00 | $20.00 |
| 3 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 369 | $30.00 | $25.00 | $20.00 | $45.00 | $40.13 | $20.00 |
| 4 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 5,271 | $15.00 | $15.00 | $6.00 | $5.00 | $18.87 | $20.00 |
| 5 | Removing concrete (retaining walls) (104-7025) | SY | 10 | $100.00 | $5.00 | $500.00 | $84.91 | $100.00 | |
| 6 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052) | SY | 9,119 | $10.00 | $11.00 | $10.00 | $5.00 | $21.69 | $20.00 |
| 7 | Embankment (final)(OC)(type A) (132-7001) | CY | 252 | $75.00 | $30.00 | $30.00 | $98.45 | $100.00 | |
| 8 | Furn & place topsoil (4") (160-7002) | SY | 4,410 | $5.00 | $7.00 | $2.50 | $9.00 | $6.11 | $10.00 |
| 9 | Block sodding (162-7002) | SY | 4,410 | $10.00 | $9.00 | $6.00 | $9.00 | $25.20 | $10.00 |
| 10 | Vegetative watering (168-7001) | TGL | 37.10 | $50.00 | $200.00 | $50.00 | $500.00 | $49.26 | $30.00 |
| 11 | Flexible pavement structure repair(8") (351-7007) | SY | 630 | $85.00 | $133.00 | $100.00 | $75.00 | $88.46 | $95.00 |
| 12 | Class C concrete (miscellaneous) (420-7067) | CY | 21.80 | $1,000.00 | $1,000.00 | $900.00 | $1,865.59 | $2,500.00 | |
| 13 | Retaining wall (concrete block) (423-7013) | SF | 83 | $60.00 | $70.00 | $500.00 | $275.00 | $250.00 | |
| 14 | Riprap (concrete)(5 in) (432-7002) | CY | 76.40 | $1,000.00 | $775.00 | $750.00 | $900.00 | $746.16 | $650.00 |
| 15 | Rail (handrail)(type B) (450-7059) | LF | 260 | $200.00 | $130.00 | $180.00 | $500.00 | $86.69 | $200.00 |
| 16 | Rail (handrail)(type F) (450-7063) | LF | 82 | $225.00 | $180.00 | $500.00 | $147.46 | $200.00 | |
| 17 | Grate & frame (471-7003) | EACH | 113 | $2,200.00 | $2,500.00 | $950.00 | $1,046.40 | $9,000.00 | |
| 18 | Adjusting manholes (479-7001) | EACH | 1 | $1,100.00 | $2,000.00 | $1,500.00 | $2,080.52 | $2,500.00 | |
| 19 | Adjusting manholes (utility box) (479-7004) | EACH | 20 | $1,000.00 | $850.00 | $500.00 | $500.00 | $1,124.52 | $1,500.00 |
| 20 | Remove STR (bollard) (496-7028) | EACH | 28 | $65.00 | $50.00 | $350.00 | $387.20 | $500.00 | |
| 21 | Mobilization (500-7001) | LS | 1 | $372,260 | $150,000 | $330,500 | $450,000 | $268.55 | $500,000 |
| 22 | Barricades, signs and traffic handling (502-7001) | MO | 18 | $5,000.00 | $4,000.00 | $5,000.00 | $3,000.00 | $93.50 | $8,500.00 |
| 23 | Portable changeable message sign (503-7002) | EACH | 2 | $16,500 | $8,000.00 | $800.00 | $13,200 | $20,000 | |
| 24 | TMA (stationary) (505-7001) | DAY | 295 | $200.00 | $225.00 | $40.00 | $300.00 | $330.00 | $250.00 |
| 25 | TMA (mobile operation) (505-7003) | DAY | 10 | $250.00 | $350.00 | $200.00 | $500.00 | $557.77 | $550.00 |
| 26 | Sandbags for erosion control (506-7035) | EACH | 1,201 | $9.00 | $12.00 | $4.00 | $6.00 | $19.25 | $10.00 |
| 27 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 4,771 | $7.00 | $8.00 | $6.00 | $8.00 | $7.70 | $12.00 |
| 28 | Biodegradable erosion control logs (remove) (506-7046) | LF | 4,771 | $2.00 | $2.00 | $3.00 | $4.00 | $1.65 | $5.00 |
| 29 | Colored textured concrete (4") (527-7001) | SY | 1,010 | $180.00 | $120.00 | $200.00 | $139.01 | $150.00 | |
| 30 | Concrete curb (type I) (529-7001) | LF | 191 | $31.00 | $50.00 | $25.00 | $39.64 | $50.00 | |
| 31 | Concrete curb (type II) (529-7002) | LF | 3,011 | $30.00 | $35.00 | $55.00 | $25.00 | $15.40 | $45.00 |
| 32 | Concrete curb & gutter (type I) (529-7008) | LF | 418 | $30.00 | $42.00 | $60.00 | $30.00 | $61.38 | $60.00 |
| 33 | Concrete curb & gutter (type II) (529-7009) | LF | 8,729 | $40.00 | $48.00 | $60.00 | $30.00 | $33.00 | $55.00 |
| 34 | Concrete curb (slotted) (529-7013) | LF | 127 | $50.00 | $60.00 | $45.00 | $52.40 | $150.00 | |
| 35 | Concrete curb & gutter (armor curb) (529-7018) | LF | 140 | $265.00 | $300.00 | $50.00 | $237.25 | $300.00 | |
| 36 | Driveways (concrete) (530-7006) | SY | 7,138 | $100.00 | $125.00 | $115.00 | $150.00 | $231.00 | $85.00 |
| 37 | Driveways (ACP) (530-7010) | SY | 2,102 | $90.00 | $45.00 | $80.00 | $100.00 | $100.10 | $55.00 |
| 38 | Concrete sidewalks (4") (531-7001) | SY | 7,046 | $90.00 | $95.00 | $85.00 | $135.00 | $68.02 | $65.00 |
| 39 | Curb ramps (type 1) (531-7015) | SY | 161 | $165.00 | $160.00 | $120.00 | $145.00 | $230.25 | $350.00 |
| 40 | Curb ramps (type 2) (531-7016) | SY | 27 | $165.00 | $160.00 | $120.00 | $145.00 | $173.95 | $350.00 |
| 41 | Curb ramps (type 3) (531-7017) | SY | 184 | $165.00 | $158.00 | $110.00 | $145.00 | $307.70 | $350.00 |
| 42 | Curb ramps (type 6) (531-7019) | SY | 112 | $165.00 | $162.00 | $120.00 | $145.00 | $226.88 | $350.00 |
| 43 | Curb ramps (type 7) (531-7020) | SY | 167 | $165.00 | $168.00 | $120.00 | $145.00 | $185.09 | $350.00 |
| 44 | Curb ramps (type 10) (531-7021) | SY | 225 | $165.00 | $160.00 | $110.00 | $145.00 | $317.78 | $350.00 |
| 45 | Curb ramps (type 21) (531-7023) | SY | 6 | $165.00 | $360.00 | $200.00 | $145.00 | $1,029.19 | $350.00 |
| 46 | Curb ramps (type 22) (531-7024) | SY | 45 | $165.00 | $170.00 | $200.00 | $145.00 | $146.85 | $350.00 |
| 47 | Concrete sidewalks (special) (531-7025) | SY | 747 | $225.00 | $200.00 | $145.00 | $160.00 | $249.38 | $100.00 |
| 48 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 1 | $1,200.00 | $930.00 | $400.00 | $1,500.00 | $819.50 | $1,150.00 |
| 49 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 4 | $800.00 | $430.00 | $500.00 | $950.00 | $379.50 | $1,150.00 |
| 50 | Mailbox install-D (TWG-post) type 2 (560-7003) | EACH | 1 | $1,000.00 | $480.00 | $500.00 | $1,000.00 | $423.50 | $150.00 |
| 51 | Ground box type A (122311) (624-7001) | EACH | 20 | $1,000.00 | $1,725.00 | $3,054.08 | $350.00 | $2,200.00 | $1,150.00 |
| 52 | Ground box type A (122311)W/apron (624-7002) | EACH | 9 | $3,450.00 | $3,970.30 | $600.00 | $2,860.00 | $1,250.00 | |
| 53 | Remove ground box (624-7013) | EACH | 29 | $250.00 | $515.00 | $1,725.55 | $250.00 | $1,243.00 | $50.00 |
| 54 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 6 | $800.00 | $945.00 | $750.00 | $850.00 | $835.80 | $1,500.00 |
| 55 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 32 | $600.00 | $845.00 | $400.00 | $600.00 | $742.50 | $1,150.00 |
| 56 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $150.00 | $175.00 | $350.00 | $250.00 | $159.05 | $500.00 |
| 57 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 1,213 | $1.00 | $1.20 | $4.09 | $6.00 | $1.01 | $3.00 |
| 58 | Reflectorized pavement marking type II (Y) 4" (solid) (666-7210) | LF | 301 | $1.20 | $4.09 | $6.00 | $1.01 | $3.00 | |
| 59 | Pavement sler 4" (666-7346) | LF | 301 | $1.20 | $2.73 | $6.00 | $1.01 | $3.00 | |
| 60 | Pavement sler 6" (666-7347) | LF | 1,213 | $1.00 | $1.20 | $2.73 | $6.00 | $1.01 | $3.00 |
| 61 | Pavement sler 24" (666-7352) | LF | 1,261 | $5.00 | $3.60 | $8.18 | $20.00 | $3.30 | $20.00 |
| 62 | Pavement sler (yld tri) (666-7365) | EACH | 19 | $5.00 | $66.00 | $24.54 | $800.00 | $60.50 | $50.00 |
| 63 | Prefabricated PM type B (W)(24")(solid) (668-7021) | LF | 1,261 | $25.00 | $42.00 | $47.72 | $10.00 | $38.50 | $20.00 |
| 64 | Prefabricated PM type B (W)(36")(yld tri) (668-7038) | EACH | 19 | $75.00 | $235.00 | $136.34 | $1,000.00 | $214.50 | $150.00 |
| 65 | Eliminating existing PM & markers (4") (677-7001) | LF | 834 | $1.00 | $1.20 | $2.73 | $8.50 | $1.01 | $3.00 |
| 66 | Eliminating existing PM & markers (24") (677-7008) | LF | 587 | $5.00 | $3.60 | $6.82 | $6.00 | $3.03 | $20.00 |
| 67 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 1 | $200.00 | $136.35 | $500.00 | $132.00 | $250.00 | |
| 68 | Eliminating existing PM & markers (word) (677-7015) | EACH | 1 | $250.00 | $170.42 | $500.00 | $165.00 | $250.00 | |
| 69 | Eliminating existing PM & markers (36")(yld tri) (677-7024) | EACH | 7 | $125.00 | $23.86 | $350.00 | $104.05 | $150.00 | |
| 70 | Pavement surface preparation for marking (4") (678-7001) | LF | 301 | $1.20 | $2.45 | $3.00 | $1.01 | $3.00 | |
| 71 | Pavement surface preparation for marking (6") (678-7002) | LF | 1,213 | $1.00 | $1.20 | $2.73 | $3.00 | $1.01 | $3.00 |
| 72 | Pavement surface preparation for marking (24") (678-7008) | LF | 1,261 | $3.00 | $2.50 | $6.82 | $3.00 | $2.02 | $20.00 |
| 73 | Pavement surface preparation for marking (36")(yld tri) (678-7023) | EACH | 19 | $15.00 | $65.00 | $34.09 | $250.00 | $55.00 | $150.00 |
| 74 | Relocate pedestrian pole assembly (687-7003) | EACH | 2 | $5,175.00 | $13,614 | $1,200.00 | $9,806.05 | $5,500.00 | |
| 75 | Pedestrian detect push button (standard) (688-7002) | EACH | 8 | $1,100.00 | $1,610.00 | $1,832.45 | $1,500.00 | $1,320.00 | $1,500.00 |
| 76 | Removal of pedestrian push buttons (690-7030) | EACH | 8 | $150.00 | $115.00 | $267.23 | $1,200.00 | $192.05 | $500.00 |
| 77 | Removal of concrete foundations (690-7063) | EACH | 2 | $1,000.00 | $2,000.00 | $2,000.00 | $6,000.00 | $2,914.43 | $1,500.00 |
| 78 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 3 | $1,500.00 | $750.00 | $100.00 | $1,200.00 | $182.05 | $2,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.