TxDOT contract A00184682 bid tabulation
Hazard Elimination & Safety, FM 624 (1500 FT W OF CR 308 to 1500 FT E OF CR 308). Let by Texas DOT on February 6, 2025, Jim Wells, Corpus Christi District. 6 bids received; low bid $1,711,943 by Hunter Industries, LTD., -23% against the engineer's estimate of $2,235,251.
- Owner
- Texas DOT
- Letting
- 06 FEB 2025
- Pay items
- 75
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hunter Industries, LTD. | $1,711,943 | Low | -23% |
| 2 | Anderson Columbia Co., Inc. | $1,984,982 | +16% | -11% |
| 3 | J E Construction Services, LLC | $2,148,590 | +26% | -4.0% |
| 4 | LCR Total Transport LLC | $2,229,295 | +30% | 0.0% |
| 5 | CK Newberry, LLC | $2,237,605 | +31% | 0.0% |
| 6 | RBM Contractors LLC | $2,895,219 | +69% | +30% |
Engineer's estimate: $2,235,251.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hunter Industries, LTD. | 2. Anderson Columbia Co., Inc. | 3. J E Construction Services, LLC | 4. LCR Total Transport LLC | 5. CK Newberry, LLC | 6. RBM Contractors LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7007) | CY | 38 | $55.00 | $13.20 | $167.00 | $81.00 | $330.00 | $50.00 | $270.74 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 339 | $30.00 | $19.80 | $27.00 | $11.00 | $29.00 | $25.00 | $32.49 |
| 3 | Remove (6"-10") TRT/untrt base & asphalt pavement (105-7006) | SY | 1,934 | $7.00 | $5.50 | $14.00 | $14.00 | $4.00 | $8.00 | $9.60 |
| 4 | Excavation (roadway) (110-7001) | CY | 1,820 | $30.00 | $18.70 | $14.00 | $11.00 | $22.50 | $25.00 | $49.00 |
| 5 | Embankment (final)(DC)(type C) (132-7006) | CY | 2,389 | $55.00 | $19.80 | $15.00 | $14.00 | $22.50 | $25.00 | $39.14 |
| 6 | Backfill (type A or B) (134-7004) | STA | 49 | $104.50 | $487.00 | $230.00 | $325.00 | $250.00 | $2,100.00 | |
| 7 | Compost manuf topsoil (4") (161-7002) | SY | 9,845 | $3.00 | $4.00 | $5.85 | $5.00 | $4.25 | $2.00 | $5.58 |
| 8 | Drill seed (permanent_rural_sand) (164-7009) | SY | 9,845 | $1.20 | $1.50 | $0.50 | $2.00 | $1.60 | $0.45 | $2.57 |
| 9 | Vegetative watering (168-7001) | TGL | 180 | $60.00 | $26.40 | $49.00 | $49.00 | $65.00 | $20.00 | $19.75 |
| 10 | FL BS (cip)(type A GR 1-2 or 5) final pos (247-7348) | CY | 1,237 | $175.00 | $104.32 | $114.00 | $135.00 | $147.00 | $142.00 | $51.00 |
| 11 | Cement (275-7001) | TON | 104 | $200.00 | $209.00 | $221.00 | $220.00 | $210.00 | $225.00 | $362.38 |
| 12 | Cement TRT (existing material)(8") (275-7003) | SY | 7,734 | $3.00 | $2.86 | $2.60 | $4.00 | $1.85 | $3.00 | $5.07 |
| 13 | Prime coat (MC-30) (310-7004) | GAL | 1,419 | $10.00 | $7.70 | $6.40 | $6.00 | $5.00 | $7.00 | $7.50 |
| 14 | Asphalt (CRS-2) (316-7011) | GAL | 2,640 | $7.00 | $4.18 | $3.50 | $5.00 | $2.00 | $4.50 | $7.50 |
| 15 | Asphalt(AC-15P, HFRS-2P or CRS-2P) (316-7070) | GAL | 11,889 | $11.00 | $4.29 | $3.40 | $5.00 | $4.50 | $4.25 | $33.00 |
| 16 | Aggregate (type-PB, GR-3 or 3S)(sac-B) (316-7209) | CY | 81 | $170.00 | $228.15 | $316.00 | $287.00 | $160.50 | $300.00 | $305.00 |
| 17 | Aggregate (type-PB, GR-4S or 4)(sac-B) (316-7212) | CY | 345 | $125.00 | $185.69 | $222.00 | $205.00 | $161.00 | $150.00 | $405.00 |
| 18 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 4,091 | $110.00 | $111.10 | $128.00 | $152.00 | $155.50 | $165.00 | $145.00 |
| 19 | D-GR HMA type D PG70-22 (level-UP) (341-7051) | TON | 29 | $180.00 | $255.20 | $750.00 | $420.00 | $157.00 | $200.00 | $145.00 |
| 20 | Plane & text asphalt concrete pavement(0" to 1") (354-7001) | SY | 530 | $9.00 | $4.62 | $27.00 | $15.00 | $2.20 | $5.00 | $12.03 |
| 21 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 3,202 | $4.62 | $8.90 | $6.00 | $1.40 | $3.00 | $5.99 | |
| 22 | Flowable backfill (401-7001) | CY | 4 | $325.00 | $836.30 | $377.00 | $185.00 | $350.00 | $700.00 | $2,655.73 |
| 23 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 80 | $220.00 | $245.00 | $273.00 | $310.00 | $425.50 | $400.00 | $665.26 |
| 24 | Riprap (concrete)(CL B) (432-7005) | CY | 4 | $750.00 | $1,028.31 | $1,120.00 | $710.00 | $890.00 | $1,200.00 | $770.00 |
| 25 | RC pipe (CL III)(36 in) (464-7009) | LF | 24 | $200.00 | $349.41 | $631.00 | $274.00 | $132.00 | $400.00 | $233.16 |
| 26 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 3 | $4,500.00 | $5,207.84 | $5,550.00 | $3,160.00 | $3,000.00 | $9,500.00 | $5,060.31 |
| 27 | Set (type II) (36 in) (RCP) (6: 1) (C) (467-7367) | EACH | 3 | $4,600.00 | $5,727.34 | $6,110.00 | $4,420.00 | $3,900.00 | $4,250.00 | $7,508.96 |
| 28 | Clean existing culverts (480-7001) | EACH | 3 | $880.00 | $2,133.68 | $471.00 | $1,430.00 | $1,650.00 | $500.00 | $3,317.53 |
| 29 | Removing structure (headwall) (496-7006) | EACH | 2 | $1,800.00 | $2,864.92 | $3,140.00 | $3,620.00 | $3,725.00 | $1,056.40 | $2,715.90 |
| 30 | Mobilization (500-7001) | LS | 1 | $91,311 | $152,999 | $142,000 | $84,210 | $186,000 | $225,000 | $46,180 |
| 31 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $5,000.00 | $5,350.58 | $11,700 | $17,060 | $5,025.00 | $18,000 | $5,975.00 |
| 32 | Portable changeable message sign (503-7001) | DAY | 214 | $50.00 | $32.48 | $66.00 | $160.00 | $100.00 | $75.00 | $102.28 |
| 33 | TMA (stationary) (505-7001) | DAY | 61 | $250.00 | $216.50 | $400.00 | $390.00 | $210.00 | $350.00 | $475.29 |
| 34 | TMA (mobile operation) (505-7003) | DAY | 20 | $175.00 | $324.75 | $100.00 | $540.00 | $375.00 | $150.00 | $1,700.00 |
| 35 | Temporary sediment control fence (install) (506-7039) | LF | 660 | $10.00 | $6.00 | $6.95 | $5.00 | $6.50 | $6.25 | $9.05 |
| 36 | Temporary sediment control fence (remove) (506-7041) | LF | 660 | $2.00 | $2.00 | $3.90 | $3.00 | $2.25 | $3.50 | $4.24 |
| 37 | Intersections (ACP) (530-7002) | SY | 2,694 | $15.40 | $20.00 | $39.00 | $38.50 | $25.00 | $51.05 | |
| 38 | Driveways (concrete) (530-7006) | SY | 348 | $115.00 | $124.23 | $104.00 | $79.00 | $147.00 | $100.00 | $140.30 |
| 39 | Driveways (ACP) (530-7010) | SY | 499 | $100.00 | $15.40 | $48.00 | $54.00 | $42.00 | $55.00 | $51.05 |
| 40 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 14,913 | $1.00 | $0.39 | $0.80 | $1.00 | $0.50 | $0.40 | $1.38 |
| 41 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 8,254 | $1.50 | $0.53 | $0.75 | $1.00 | $0.50 | $0.40 | $1.38 |
| 42 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 3 | $350.00 | $385.00 | $428.00 | $450.00 | $410.00 | $500.00 | $2,500.00 |
| 43 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 10 | $5,000.00 | $4,500.00 | $5,010.00 | $5,300.00 | $5,525.00 | $5,200.00 | $6,250.98 |
| 44 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 1,820 | $30.00 | $10.00 | $11.00 | $11.00 | $26.50 | $25.00 | $30.08 |
| 45 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 175 | $40.00 | $32.00 | $36.00 | $37.00 | $53.00 | $50.00 | $60.16 |
| 46 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 10 | $50.00 | $40.00 | $45.00 | $47.00 | $117.00 | $110.00 | $132.36 |
| 47 | Electrical conductor (no.6) bare (620-7009) | LF | 2,050 | $2.10 | $2.10 | $2.35 | $2.00 | $3.25 | $3.00 | $3.61 |
| 48 | Electrical conductor (no.6) insulated (620-7010) | LF | 4,100 | $3.00 | $2.20 | $2.45 | $3.00 | $3.35 | $3.15 | $3.75 |
| 49 | Ground box type A (122311)W/apron (624-7002) | EACH | 1 | $2,500.00 | $1,150.00 | $1,280.00 | $1,360.00 | $1,960.00 | $1,840.00 | $2,214.01 |
| 50 | Elc SRV type A 240/480 060(SS)SS(E)GC(U) (628-7055) | EACH | 1 | $10,000 | $7,400.00 | $8,230.00 | $8,740.00 | $10,425 | $9,800.00 | $11,792 |
| 51 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 18 | $600.00 | $750.00 | $834.00 | $880.00 | $800.00 | $635.00 | $764.08 |
| 52 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $175.00 | $195.00 | $420.00 | $186.00 | $135.00 | $162.44 | |
| 53 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 2 | $200.00 | $150.00 | $167.00 | $173.00 | $160.00 | $105.00 | $126.34 |
| 54 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 908 | $1.10 | $1.20 | $1.00 | $1.25 | $1.40 | $2.53 | |
| 55 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 132 | $16.00 | $18.00 | $20.00 | $17.00 | $6.00 | $14.56 | |
| 56 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 8 | $150.00 | $167.00 | $180.00 | $160.00 | $140.00 | $270.86 | |
| 57 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 24 | $250.00 | $278.00 | $290.00 | $266.00 | $140.00 | $300.94 | |
| 58 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 13,050 | $0.78 | $0.85 | $1.00 | $0.85 | $1.00 | $1.62 | |
| 59 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 620 | $5.00 | $5.00 | $5.55 | $5.00 | $5.30 | $5.00 | $7.94 |
| 60 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 20,000 | $0.50 | $0.72 | $0.80 | $1.00 | $0.75 | $1.25 | $1.62 |
| 61 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 24,700 | $0.55 | $0.72 | $0.80 | $1.00 | $0.75 | $1.25 | $1.62 |
| 62 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 91 | $1.63 | $3.70 | $3.00 | $2.65 | $2.00 | $1.85 | |
| 63 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 924 | $2.50 | $1.63 | $3.70 | $3.00 | $2.65 | $2.00 | $1.85 |
| 64 | Reflectorized pavement marking type I (W)8"(DOT)(090MIL) (666-7017) | LF | 368 | $1.00 | $2.00 | $2.20 | $3.00 | $2.15 | $4.00 | $2.53 |
| 65 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 1,268 | $1.50 | $1.50 | $1.65 | $2.00 | $1.60 | $2.25 | $2.53 |
| 66 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 14,913 | $1.10 | $1.40 | $1.55 | $2.00 | $1.50 | $0.75 | $1.26 |
| 67 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 8,198 | $1.10 | $2.00 | $2.20 | $2.00 | $2.15 | $0.75 | $1.26 |
| 68 | PRFB rumble strip (BLK)(4')(transverse) (668-7001) | LF | 320 | $7.50 | $8.35 | $9.00 | $8.00 | $28.00 | $12.15 | |
| 69 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 168 | $25.00 | $16.00 | $18.00 | $19.00 | $17.00 | $14.25 | $14.56 |
| 70 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 12 | $400.00 | $150.00 | $167.00 | $170.00 | $160.00 | $275.00 | $300.94 |
| 71 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 28 | $400.00 | $250.00 | $278.00 | $290.00 | $266.00 | $280.00 | $355.08 |
| 72 | Reflectorized pavement marker type I-C (672-7002) | EACH | 64 | $7.00 | $7.50 | $8.35 | $8.00 | $8.00 | $6.00 | $6.74 |
| 73 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,417 | $8.00 | $7.50 | $8.35 | $9.00 | $8.00 | $5.00 | $6.74 |
| 74 | Install RDSD FLSH BCN assembly (solar PWRD) (685-7004) | EACH | 16 | $7,150.00 | $7,950.00 | $8,470.00 | $12,025 | $7,500.00 | $13,597 | |
| 75 | Removing RDSD FLSH BCN AM (solar PWRD) (685-7006) | EACH | 4 | $850.00 | $946.00 | $1,010.00 | $3,175.00 | $1,100.00 | $3,585.74 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.