TxDOT contract A00187771 bid tabulation
Resurface Roadway, SS 557 (US 80 to IH 20). Let by Texas DOT on November 5, 2025, Kaufman, Dallas District. 8 bids received; low bid $8,281,477 by O. Trevino Construction, LLC, -32% against the engineer's estimate of $12,242,999.
- Owner
- Texas DOT
- Letting
- 05 NOV 2025
- Pay items
- 55
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | O. Trevino Construction, LLC | $8,281,477 | Low | -32% |
| 2 | Texas Materials Group, Inc. | $8,577,278 | +4.0% | -30% |
| 3 | Foutsco Paving Company, LLC | $9,324,427 | +13% | -24% |
| 4 | Austin Bridge & Road Services, LP | $9,498,139 | +15% | -22% |
| 5 | Peachtree Construction, LTD. | $9,790,731 | +18% | -20% |
| 6 | Silver Creek Construction, Inc. | $10,062,413 | +22% | -18% |
| 7 | Overland Corporation | $10,174,947 | +23% | -17% |
| 8 | Grey Sky Construction LLC | $11,981,427 | +45% | -2.0% |
Engineer's estimate: $12,242,999.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. O. Trevino Construction, LLC | 2. Texas Materials Group, Inc. | 3. Foutsco Paving Company, LLC | 4. Austin Bridge & Road Services, LP | 5. Peachtree Construction, LTD. | 6. Silver Creek Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 231.37 | $3,500.00 | $100.00 | $275.00 | $50.00 | $4,105.17 | $250.00 | $750.00 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 2,041 | $6.50 | $16.00 | $16.00 | $20.00 | $3.68 | $19.50 | $10.00 |
| 3 | Backfill (type A or B) (134-7004) | STA | 227.71 | $420.00 | $275.00 | $249.00 | $100.00 | $143.94 | $550.00 | $275.00 |
| 4 | Block sodding (162-7002) | SY | 100 | $7.00 | $12.50 | $10.60 | $10.00 | $12.00 | $12.50 | $15.00 |
| 5 | Vegetative watering (168-7001) | TGL | 15 | $2.00 | $260.00 | $90.00 | $1.00 | $250.00 | $325.00 | $300.00 |
| 6 | Stone-MTRX-asphalt SMA-C sac-B PG76-22 (346-7004) | TON | 21,535 | $170.00 | $150.00 | $143.00 | $209.00 | $146.61 | $182.75 | $150.00 |
| 7 | Tack coat (346-7028) | GAL | 12,862 | $4.50 | $4.50 | $4.42 | $10.00 | $4.00 | $1.50 | $5.00 |
| 8 | Plane & text asphalt concrete pavement(0" to 3") (354-7003) | SY | 40,810 | $3.70 | $3.00 | $2.32 | $1.50 | $3.00 | $3.25 | $8.00 |
| 9 | Plane & text asphalt concrete pavement(0" to 8") (354-7006) | SY | 10,103 | $9.00 | $11.25 | $1.00 | $2.00 | $0.20 | $14.00 | $3.74 |
| 10 | Full - depth repair CRCP (12") (361-7007) | CY | 3,378 | $1,200.00 | $713.00 | $865.00 | $400.00 | $803.00 | $815.00 | $1,009.50 |
| 11 | Full - depth repair CPCD (12") (361-7023) | CY | 375 | $900.00 | $725.00 | $875.00 | $800.00 | $812.00 | $830.00 | $1,000.00 |
| 12 | Riprap (mow strip)(4 in) (432-7013) | CY | 535 | $850.00 | $750.00 | $575.00 | $550.00 | $591.27 | $660.00 | $575.00 |
| 13 | Mobilization (500-7001) | LS | 1 | $1,268,311 | $795,000 | $820,479 | $900,000 | $1,044,795 | $875,000 | $1,000,000 |
| 14 | Barricades, signs and traffic handling (502-7001) | MO | 11 | $30,000 | $3,200.00 | $9,000.00 | $100,000 | $14,552 | $35,000 | $25,000 |
| 15 | Portable changeable message sign (503-7002) | EACH | 2 | $8,000.00 | $25,000 | $11,000 | $20,000 | $195.00 | $14,000 | $20,000 |
| 16 | TMA (stationary) (505-7001) | DAY | 179 | $200.00 | $152.00 | $320.00 | $1.00 | $608.18 | $175.00 | $250.00 |
| 17 | TMA (mobile operation) (505-7003) | DAY | 35 | $250.00 | $250.00 | $1.00 | $1.00 | $5.00 | $450.00 | $600.00 |
| 18 | Rock filter dams (install) (type 2) (506-7002) | LF | 50 | $30.00 | $55.00 | $78.00 | $20.00 | $35.50 | $38.00 | $40.00 |
| 19 | Rock filter dams (remove) (506-7011) | LF | 50 | $12.00 | $25.94 | $26.00 | $10.00 | $12.00 | $12.50 | $12.00 |
| 20 | Temporary sediment control fence (install) (506-7039) | LF | 2,048 | $3.00 | $3.89 | $4.00 | $4.00 | $3.60 | $3.75 | $5.00 |
| 21 | Temporary sediment control fence (remove) (506-7041) | LF | 2,048 | $0.80 | $1.19 | $1.25 | $1.00 | $1.10 | $1.20 | $1.00 |
| 22 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 483 | $5.00 | $6.32 | $6.50 | $4.00 | $5.85 | $6.25 | $8.00 |
| 23 | Biodegradable erosion control logs (remove) (506-7046) | LF | 483 | $1.00 | $1.35 | $1.55 | $1.00 | $1.25 | $1.35 | $1.00 |
| 24 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 66,316 | $0.25 | $0.17 | $0.20 | $0.20 | $0.12 | $0.15 | $0.35 |
| 25 | Metal W-beam guard fence (timber post) (540-7001) | LF | 12,437 | $22.00 | $25.59 | $24.90 | $20.00 | $18.00 | $19.25 | $25.00 |
| 26 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $2,500.00 | $2,503.40 | $2,785.00 | $1,500.00 | $1,535.00 | $1,650.00 | $2,500.00 |
| 27 | Downstream anchor terminal section (540-7015) | EACH | 15 | $1,300.00 | $1,418.59 | $1,379.00 | $950.00 | $1,200.00 | $1,250.00 | $1,400.00 |
| 28 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 200 | $110.00 | $83.45 | $81.00 | $75.00 | $81.00 | $87.50 | $90.00 |
| 29 | Remove metal beam guard fence (542-7001) | LF | 12,737 | $4.00 | $1.11 | $1.08 | $2.00 | $2.00 | $2.15 | $1.00 |
| 30 | Remove terminal anchor section (542-7002) | EACH | 15 | $320.00 | $111.26 | $108.00 | $950.00 | $200.00 | $215.00 | $120.00 |
| 31 | Guardrail end treatment (install) (544-7001) | EACH | 16 | $3,200.00 | $3,115.34 | $3,000.00 | $2,450.00 | $2,850.00 | $3,075.00 | $3,250.00 |
| 32 | Guardrail end treatment (remove) (544-7003) | EACH | 16 | $275.00 | $111.26 | $108.00 | $250.00 | $200.00 | $215.00 | $100.00 |
| 33 | Aluminum signs (type A) (636-7001) | SF | 56 | $50.00 | $108.07 | $108.00 | $100.00 | $100.00 | $105.00 | $100.00 |
| 34 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 20 | $25.00 | $32.42 | $32.00 | $20.00 | $25.00 | $27.00 | $35.00 |
| 35 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 121 | $35.00 | $36.20 | $36.00 | $22.00 | $31.00 | $33.50 | $35.00 |
| 36 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 65 | $25.00 | $32.42 | $32.00 | $20.00 | $25.00 | $27.00 | $35.00 |
| 37 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 83 | $35.00 | $36.20 | $36.00 | $21.00 | $31.00 | $33.50 | $35.00 |
| 38 | Install delineator assembly (D-SW)SZ 1(WFLX)GNDHH (658-7106) | EACH | 52 | $100.00 | $210.00 | $215.00 | $150.00 | $205.00 | $35.00 | $200.00 |
| 39 | Install delineator assembly (D-DW)SZ 1(WFLX)GNDHH (658-7139) | EACH | 37 | $110.00 | $210.00 | $215.00 | $150.00 | $205.00 | $170.00 | $200.00 |
| 40 | Install object marker assembly (OM-2Z)(WFLX)SRFHH (658-7257) | EACH | 19 | $200.00 | $225.00 | $230.00 | $165.00 | $219.50 | $58.50 | $200.00 |
| 41 | Install object marker assembly (OM-2Z)(yflx)SRFHH (658-7259) | EACH | 24 | $200.00 | $225.00 | $230.00 | $165.00 | $219.50 | $58.50 | $200.00 |
| 42 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 3,256 | $0.80 | $6.40 | $1.23 | $1.00 | $0.50 | $3.50 | $5.00 |
| 43 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 6,638 | $2.00 | $0.60 | $0.86 | $0.80 | $0.77 | $0.83 | $0.85 |
| 44 | Reflectorized pavement marking type I (W)12"(lane drop)(100MIL) (666-7027) | LF | 289 | $3.00 | $1.60 | $3.24 | $3.00 | $2.00 | $2.15 | $2.20 |
| 45 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 1,872 | $8.00 | $1.60 | $2.90 | $2.50 | $3.25 | $3.50 | $3.60 |
| 46 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 2,366 | $1.50 | $2.50 | $6.45 | $6.00 | $6.00 | $6.50 | $7.00 |
| 47 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 9,764 | $0.60 | $0.22 | $0.19 | $0.18 | $0.25 | $0.27 | $0.30 |
| 48 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 50,056 | $0.60 | $0.22 | $0.18 | $0.17 | $0.17 | $0.18 | $0.25 |
| 49 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 46,525 | $0.60 | $0.22 | $0.18 | $0.17 | $0.17 | $0.18 | $0.25 |
| 50 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 9,764 | $0.80 | $0.50 | $0.57 | $0.53 | $0.52 | $0.55 | $0.60 |
| 51 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 50,056 | $0.80 | $0.50 | $0.54 | $0.50 | $0.48 | $0.50 | $0.55 |
| 52 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 46,525 | $4.00 | $0.50 | $0.54 | $0.50 | $0.48 | $0.50 | $0.55 |
| 53 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 873 | $6.00 | $4.25 | $3.88 | $3.60 | $3.75 | $4.05 | $4.00 |
| 54 | Eliminating existing PM & markers (4") (677-7001) | LF | 19,075 | $1.00 | $0.25 | $0.51 | $0.48 | $0.45 | $0.50 | $0.50 |
| 55 | Full - width mowing (730-7019) | CYC | 2 | $5,000.00 | $7,000.00 | $3,670.00 | $8,000.00 | $4,500.00 | $20,000 | $7,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 5, 2025. Compiled by Mirage Metrics.