TxDOT contract A00188712 bid tabulation
Surfacing/Roadway Restoration, FM 2004 (SH 288 to SH 332). Let by Texas DOT on April 3, 2025, Brazoria, Houston District. 6 bids received; low bid $2,192,873 by Elite Kings Construction, LLC, -6.1% against the engineer's estimate of $2,336,183.
- Owner
- Texas DOT
- Letting
- 03 APR 2025
- Pay items
- 127
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Elite Kings Construction, LLC | $2,192,873 | Low | -6.0% |
| 2 | Forde Construction Company, Inc. | $2,287,604 | +4.0% | -2.0% |
| 3 | Cornerstone Paving and Construction, L.L.C. | $2,335,631 | +7.0% | 0.0% |
| 4 | Vulcan Materials Asphalt and Construction, LLC | $2,362,253 | +8.0% | +1.0% |
| 5 | Durwood Greene Construction Co. | $2,394,034 | +9.0% | +2.0% |
| 6 | Texas Materials Group, Inc. | $2,782,837 | +27% | +19% |
Engineer's estimate: $2,336,183.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Elite Kings Construction, LLC | 2. Forde Construction Company, Inc. | 3. Cornerstone Paving and Construction, L.L.C. | 4. Vulcan Materials Asphalt and Construction, LLC | 5. Durwood Greene Construction Co. | 6. Texas Materials Group, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (medians) (104-7008) | SY | 2 | $30.00 | $30.53 | $212.00 | $150.00 | $350.00 | $125.00 | $350.00 |
| 2 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 20 | $5.10 | $20.00 | $53.00 | $150.00 | $160.00 | $50.00 | $120.00 |
| 3 | Removing concrete (curb ramp) (104-7015) | SY | 14 | $40.00 | $20.00 | $76.00 | $125.00 | $190.00 | $50.00 | $120.00 |
| 4 | Embankment (final)(DC)(type C) (132-7006) | CY | 6 | $38.00 | $20.00 | $225.00 | $500.00 | $1,000.00 | $75.00 | $900.00 |
| 5 | Backfill (type A or B) (134-7004) | STA | 41 | $315.00 | $159.00 | $472.00 | $470.00 | $190.00 | $275.00 | $270.00 |
| 6 | Block sodding (162-7002) | SY | 128 | $5.15 | $7.44 | $10.00 | $5.25 | $5.25 | $15.00 | $12.00 |
| 7 | Fertilizer (166-7001) | ACRE | 0.03 | $1,295.00 | $1,800.00 | $1,600.00 | $850.00 | $850.00 | $1,000.00 | $11,500 |
| 8 | Vegetative watering (168-7001) | TGL | 0.36 | $43.00 | $20.00 | $150.00 | $2,000.00 | $30.00 | $250.00 | $7,500.00 |
| 9 | Aggregate (type-PB, GR-4)(sac-B) (316-7211) | CY | 221 | $355.00 | $150.00 | $327.00 | $224.00 | $248.00 | $185.00 | $265.00 |
| 10 | Asphalt (multi option) (316-7263) | GAL | 9,204 | $2.30 | $3.38 | $3.30 | $8.40 | $3.50 | $9.35 | $4.65 |
| 11 | D-GR HMA type D sac-A PG70-22 (341-7049) | TON | 3,259 | $148.10 | $140.00 | $142.00 | $150.30 | $155.00 | $160.00 | $209.00 |
| 12 | Planing asphalt concrete pavement(2") (354-7051) | SY | 28,761 | $5.56 | $3.00 | $2.60 | $2.67 | $2.10 | $3.00 | $5.50 |
| 13 | Full-depth repair CRCP (var depth) (361-7044) | CY | 60 | $857.00 | $1,000.00 | $2,400.00 | $2,094.00 | $2,094.80 | $1,000.00 | $2,475.00 |
| 14 | Cem stabil BKFL (400-7010) | CY | 2 | $68.00 | $267.48 | $350.00 | $2,500.00 | $168.00 | $300.00 | $110.00 |
| 15 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 184 | $285.00 | $539.69 | $275.17 | $260.00 | $259.69 | $350.00 | $300.00 |
| 16 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 66 | $380.00 | $710.11 | $295.21 | $280.00 | $278.61 | $400.00 | $330.00 |
| 17 | Riprap (concrete)(4 in) (432-7001) | CY | 5 | $740.00 | $946.43 | $915.00 | $1,000.00 | $2,500.00 | $1,250.00 | $1,100.00 |
| 18 | Cleaning existing joints (438-7008) | LF | 754 | $40.00 | $34.62 | $18.00 | $16.50 | $16.50 | $12.00 | $20.00 |
| 19 | RC pipe (CL III)(18 in) (464-7003) | LF | 20 | $144.00 | $110.36 | $150.00 | $80.00 | $465.00 | $290.00 | $350.00 |
| 20 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 2 | $1,380.00 | $1,803.09 | $2,700.00 | $1,200.00 | $4,388.00 | $2,500.00 | $3,700.00 |
| 21 | Removing structure (set) (496-7004) | EACH | 2 | $844.00 | $575.00 | $500.00 | $850.00 | $2,035.00 | $800.00 | $2,000.00 |
| 22 | Mobilization (500-7001) | LS | 1 | $203,178 | $100,000 | $147,000 | $90,000 | $187,000 | $140,000 | $200,000 |
| 23 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $10,000 | $1,500.00 | $6,300.00 | $6,000.00 | $8,600.00 | $7,000.00 | $10,500 |
| 24 | Portable changeable message sign (503-7001) | DAY | 120 | $130.00 | $250.00 | $90.00 | $65.00 | $56.00 | $300.00 | $95.00 |
| 25 | TMA (stationary) (505-7001) | DAY | 50 | $450.00 | $200.00 | $175.00 | $210.00 | $336.00 | $350.00 | $285.00 |
| 26 | TMA (mobile operation) (505-7003) | DAY | 5 | $355.00 | $360.00 | $175.00 | $210.00 | $336.00 | $350.00 | $675.00 |
| 27 | Temporary sediment control fence (install) (506-7039) | LF | 350 | $4.00 | $5.22 | $5.00 | $5.00 | $8.60 | $5.00 | $4.75 |
| 28 | Temporary sediment control fence (remove) (506-7041) | LF | 350 | $1.38 | $2.50 | $1.00 | $2.00 | $7.25 | $2.50 | $4.75 |
| 29 | Concrete sidewalks (4") (531-7001) | SY | 260 | $100.00 | $50.00 | $125.00 | $200.00 | $102.00 | $110.00 | $105.00 |
| 30 | Concrete sidewalks (5") (531-7002) | SY | 168 | $95.00 | $202.50 | $125.00 | $250.00 | $150.00 | $114.00 | $110.00 |
| 31 | Curb ramps (type 7) (531-7010) | EACH | 2 | $2,850.00 | $3,040.19 | $4,000.00 | $4,500.00 | $5,186.00 | $3,400.00 | $3,000.00 |
| 32 | Curb ramps (type 22) (531-7024) | SY | 262 | $150.00 | $100.00 | $182.00 | $385.00 | $134.00 | $120.00 | $118.50 |
| 33 | Metal W-beam guard fence (timber post) (540-7001) | LF | 60 | $25.00 | $44.00 | $27.50 | $60.00 | $30.00 | $75.00 | $70.00 |
| 34 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $2,140.00 | $2,298.96 | $2,250.00 | $2,800.00 | $6,233.55 | $3,150.00 | $2,675.00 |
| 35 | Remove metal beam guard fence (542-7001) | LF | 160 | $5.50 | $5.25 | $3.15 | $5.00 | $5.00 | $5.00 | $6.00 |
| 36 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $2,950.00 | $2.99 | $3,100.00 | $3,671.00 | $3,950.00 | $4,250.00 | $4,400.00 |
| 37 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 290 | $14.13 | $15.00 | $16.75 | $16.00 | $15.81 | $20.00 | $19.00 |
| 38 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 3,220 | $9.52 | $15.00 | $10.00 | $10.00 | $9.33 | $12.00 | $11.00 |
| 39 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 605 | $30.38 | $15.00 | $22.00 | $21.00 | $20.61 | $25.00 | $24.50 |
| 40 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 290 | $37.16 | $15.00 | $22.00 | $20.00 | $19.63 | $30.00 | $23.50 |
| 41 | Electrical conductor (no.14) insulated (620-7002) | LF | 605 | $3.00 | $2.00 | $1.05 | $1.00 | $1.00 | $2.00 | $1.20 |
| 42 | Electrical conductor (no.8) bare (620-7007) | LF | 3,800 | $1.58 | $2.00 | $1.55 | $1.50 | $1.48 | $2.25 | $1.80 |
| 43 | Electrical conductor (no.8) insulated (620-7008) | LF | 170 | $5.00 | $2.00 | $2.30 | $2.20 | $2.19 | $3.00 | $2.70 |
| 44 | Electrical conductor (no.2) insulated (620-7016) | LF | 1,860 | $5.35 | $2.00 | $1.55 | $1.41 | $1.41 | $2.50 | $1.70 |
| 45 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 12,100 | $2.59 | $2.00 | $3.00 | $2.90 | $2.86 | $3.50 | $3.40 |
| 46 | ITS GND box(pcast) type 1 (243636)W/aprn (623-7002) | EACH | 1 | $2,000.00 | $5,000.00 | $7,300.00 | $6,910.00 | $6,906.55 | $7,700.00 | $8,250.00 |
| 47 | Ground box type D (162922)W/apron (624-7008) | EACH | 30 | $1,454.00 | $3,079.52 | $1,270.00 | $1,210.00 | $1,201.30 | $1,400.00 | $1,400.00 |
| 48 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 2 | $4,828.50 | $10,000 | $7,600.00 | $7,200.00 | $7,193.84 | $7,800.00 | $8,500.00 |
| 49 | Elc SRV type D 120/240 060(NS)SS(E)SP(U) (628-7149) | EACH | 1 | $7,070.00 | $3,874.79 | $5,800.00 | $5,600.00 | $5,505.85 | $6,200.00 | $6,500.00 |
| 50 | Elc SRV type T 120/240 000(NS)GS(N)SP(O) (628-7326) | EACH | 1 | $7,885.00 | $3,874.90 | $5,500.00 | $5,300.00 | $5,281.50 | $6,000.00 | $6,250.00 |
| 51 | Aluminum signs (type O) (636-7003) | SF | 108 | $48.83 | $75.66 | $95.00 | $90.00 | $89.95 | $100.00 | $107.00 |
| 52 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 15 | $825.34 | $1,025.00 | $680.00 | $435.00 | $875.00 | $500.00 | $515.00 |
| 53 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 152 | $6.36 | $2.00 | $6.40 | $6.00 | $6.00 | $4.00 | $7.00 |
| 54 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 596 | $5.11 | $2.00 | $6.35 | $6.00 | $6.00 | $4.00 | $7.00 |
| 55 | Work zone pavement marking removing (W)6"(DOT) (662-7066) | LF | 398 | $1.72 | $2.00 | $0.65 | $0.62 | $2.50 | $1.00 | $0.75 |
| 56 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 18,270 | $1.30 | $2.00 | $0.65 | $0.62 | $1.40 | $0.70 | $0.75 |
| 57 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 3,824 | $1.72 | $2.00 | $0.85 | $0.82 | $2.00 | $1.35 | $1.00 |
| 58 | Work zone pavement marking removing (W)12"(solid) (662-7075) | LF | 1,112 | $5.94 | $2.00 | $0.50 | $0.45 | $4.00 | $2.50 | $0.50 |
| 59 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 950 | $12.78 | $2.00 | $4.70 | $4.50 | $8.00 | $4.55 | $5.50 |
| 60 | Work zone pavement marking removing (W)(arrow) (662-7082) | EACH | 50 | $435.62 | $100.00 | $127.00 | $120.00 | $300.00 | $130.00 | $140.00 |
| 61 | Work zone pavement marking removing (W)(word) (662-7092) | EACH | 44 | $266.25 | $150.00 | $137.00 | $130.00 | $350.00 | $145.00 | $150.00 |
| 62 | Work zone pavement marking removing (W)36"(yld tri) (662-7094) | EACH | 16 | $65.67 | $179.00 | $26.00 | $25.00 | $35.00 | $65.00 | $30.00 |
| 63 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 28,814 | $1.15 | $2.00 | $0.65 | $0.62 | $1.40 | $0.70 | $0.75 |
| 64 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 595 | $1.70 | $2.00 | $1.85 | $1.75 | $2.45 | $2.00 | $2.00 |
| 65 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,439 | $1.99 | $2.00 | $1.85 | $1.75 | $0.95 | $1.40 | $2.00 |
| 66 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 615 | $11.28 | $2.00 | $9.50 | $9.00 | $6.27 | $10.00 | $10.50 |
| 67 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 20 | $204.02 | $20.00 | $290.00 | $275.00 | $150.00 | $200.00 | $325.00 |
| 68 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 16 | $245.53 | $20.00 | $312.00 | $295.00 | $250.00 | $225.00 | $350.00 |
| 69 | Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090) | EACH | 16 | $40.50 | $56.90 | $60.00 | $57.50 | $50.00 | $75.00 | $70.00 |
| 70 | Reflectorized pavement marking type I (W)(bike arrow)(100MIL) (666-7093) | EACH | 5 | $170.25 | $169.95 | $280.00 | $265.00 | $100.00 | $170.00 | $315.00 |
| 71 | Reflectorized pavement marking type I(W)(bike syml)(100MIL) (666-7099) | EACH | 5 | $210.25 | $180.00 | $300.00 | $285.00 | $100.00 | $275.00 | $350.00 |
| 72 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 49 | $5.39 | $6.00 | $4.25 | $4.00 | $5.78 | $5.00 | $5.00 |
| 73 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 6,681 | $1.16 | $1.03 | $1.25 | $1.17 | $0.95 | $1.50 | $1.40 |
| 74 | Reflectorized pavement marking type III (W)(6")(broken) (666-7237) | LF | 3,725 | $1.33 | $1.06 | $1.25 | $1.17 | $0.95 | $1.50 | $1.40 |
| 75 | Reflectorized pavement marking type III (W)(8")(solid) (666-7239) | LF | 121 | $1.79 | $1.87 | $3.35 | $3.19 | $1.50 | $4.50 | $3.75 |
| 76 | Reflectorized pavement marking type III (W)(24")(solid) (666-7244) | LF | 167 | $10.69 | $14.05 | $10.50 | $10.19 | $8.00 | $20.00 | $12.00 |
| 77 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 7,530 | $1.14 | $1.04 | $1.25 | $1.17 | $0.95 | $1.50 | $1.40 |
| 78 | Reflectorized pavement marking type III (Y)(12")(solid) (666-7252) | LF | 722 | $4.22 | $5.38 | $5.40 | $5.10 | $4.00 | $12.00 | $6.00 |
| 79 | Reflectorized pavement marking type III (W)(arrow) (666-7254) | EACH | 4 | $189.00 | $5.00 | $334.00 | $315.00 | $450.00 | $500.00 | $375.00 |
| 80 | Reflectorized pavement marking type III (W)(word) (666-7257) | EACH | 4 | $210.00 | $1.30 | $355.00 | $355.00 | $450.00 | $500.00 | $400.00 |
| 81 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 10,060 | $1.15 | $1.33 | $0.95 | $0.88 | $0.70 | $1.00 | $1.00 |
| 82 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 13,698 | $1.25 | $1.33 | $0.95 | $0.88 | $0.70 | $1.00 | $1.00 |
| 83 | Reflectorized pavement marker type I-C (672-7002) | EACH | 76 | $6.84 | $6.21 | $6.35 | $6.00 | $6.00 | $7.00 | $7.00 |
| 84 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 487 | $16.30 | $7.26 | $6.35 | $6.00 | $6.00 | $7.00 | $7.00 |
| 85 | Eliminating existing PM & markers (6") (677-7002) | LF | 17,570 | $0.53 | $1.06 | $0.50 | $0.49 | $0.47 | $0.45 | $0.60 |
| 86 | Eliminating existing PM & markers (8") (677-7004) | LF | 90 | $2.13 | $1.51 | $1.00 | $0.98 | $0.93 | $0.65 | $1.00 |
| 87 | Eliminating existing PM & markers (12") (677-7006) | LF | 522 | $3.39 | $2.11 | $1.70 | $1.68 | $1.48 | $1.00 | $2.00 |
| 88 | Eliminating existing PM & markers (24") (677-7008) | LF | 160 | $5.60 | $4.67 | $3.50 | $3.30 | $2.67 | $1.40 | $4.00 |
| 89 | Eliminating existing PM & markers (36")(yld tri) (677-7024) | EACH | 16 | $30.25 | $26.88 | $26.50 | $25.00 | $78.00 | $55.00 | $30.00 |
| 90 | Pavement surface preparation for marking (6") (678-7002) | LF | 42,289 | $0.35 | $0.44 | $0.05 | $0.04 | $0.01 | $0.15 | $0.05 |
| 91 | Pavement surface preparation for marking (8") (678-7004) | LF | 1,560 | $1.87 | $0.22 | $0.07 | $0.06 | $0.02 | $0.30 | $0.05 |
| 92 | Pavement surface preparation for marking (12") (678-7006) | LF | 771 | $0.91 | $0.54 | $0.09 | $0.08 | $0.15 | $0.80 | $0.09 |
| 93 | Pavement surface preparation for marking (24") (678-7008) | LF | 782 | $1.42 | $3.96 | $0.20 | $0.16 | $0.25 | $1.25 | $0.19 |
| 94 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 24 | $49.95 | $29.08 | $5.30 | $5.00 | $10.00 | $60.00 | $6.00 |
| 95 | Pavement surface preparation for marking (word) (678-7016) | EACH | 20 | $58.07 | $36.05 | $5.30 | $5.00 | $10.00 | $60.00 | $6.00 |
| 96 | Pavement surface preparation for marking (bike arrow) (678-7026) | EACH | 5 | $5.01 | $36.05 | $5.30 | $5.00 | $10.00 | $60.00 | $6.00 |
| 97 | Pavement surface preparation for marking (bike symbol) (678-7028) | EACH | 5 | $24.72 | $41.20 | $5.30 | $5.00 | $10.00 | $60.00 | $6.00 |
| 98 | Install highway traffic signal (system) (680-7003) | EACH | 3 | $31,140 | $30,000 | $36,000 | $35,000 | $34,239 | $38,000 | $40,000 |
| 99 | Removing traffic signals (680-7004) | EACH | 3 | $7,493.00 | $5,000.00 | $9,800.00 | $9,500.00 | $9,339.84 | $10,450 | $11,000 |
| 100 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 32 | $292.10 | $200.00 | $312.00 | $300.00 | $295.03 | $320.00 | $350.00 |
| 101 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 8 | $300.60 | $200.00 | $312.00 | $300.00 | $295.03 | $320.00 | $350.00 |
| 102 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 32 | $294.10 | $200.00 | $312.00 | $295.00 | $295.03 | $320.00 | $350.00 |
| 103 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 6 | $295.10 | $200.00 | $312.00 | $295.00 | $295.03 | $320.00 | $350.00 |
| 104 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 32 | $292.10 | $200.00 | $312.00 | $296.00 | $295.03 | $320.00 | $350.00 |
| 105 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 12 | $295.10 | $200.00 | $312.00 | $296.00 | $295.03 | $320.00 | $350.00 |
| 106 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 8 | $816.40 | $1,000.00 | $723.00 | $683.00 | $682.46 | $750.00 | $800.00 |
| 107 | Backplate W/reflectorized border(4 sec) (682-7037) | EACH | 8 | $273.48 | $100.00 | $245.00 | $232.00 | $231.28 | $270.00 | $275.00 |
| 108 | Backplate W/reflectorized border(3 sec) (682-7054) | EACH | 30 | $229.73 | $150.00 | $198.00 | $188.00 | $187.46 | $210.00 | $220.00 |
| 109 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 940 | $1.21 | $2.00 | $1.75 | $1.70 | $1.66 | $2.30 | $2.00 |
| 110 | Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009) | LF | 980 | $1.79 | $2.00 | $2.75 | $2.60 | $2.60 | $3.25 | $3.00 |
| 111 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 7,353 | $2.30 | $2.00 | $3.30 | $3.25 | $3.12 | $4.00 | $3.50 |
| 112 | Ins traffic signal PL AM(S)1 arm(32')lum (686-7035) | EACH | 4 | $15,107 | $15,000 | $17,600 | $16,700 | $16,629 | $18,200 | $19,500 |
| 113 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 4 | $14,147 | $15,000 | $18,000 | $17,000 | $16,997 | $18,600 | $20,000 |
| 114 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 2 | $16,025 | $19,000 | $19,300 | $18,500 | $18,247 | $19,950 | $21,500 |
| 115 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 3 | $12,521 | $20,000 | $20,300 | $19,200 | $19,160 | $20,900 | $22,500 |
| 116 | Ins traffic signal PL AM(S)1 arm(50')lum (686-7055) | EACH | 2 | $25,650 | $30,000 | $38,000 | $36,000 | $35,803 | $39,700 | $42,500 |
| 117 | Ins traffic signal PL AM(S)1 arm(55')lum (686-7059) | EACH | 1 | $26,500 | $30,000 | $39,000 | $38,000 | $37,054 | $41,200 | $44,000 |
| 118 | Pedestrian pole assembly (687-7001) | EACH | 8 | $2,050.00 | $3,505.00 | $3,180.00 | $3,010.00 | $3,001.67 | $3,350.00 | $3,500.00 |
| 119 | Pedestrian detect push button (APS) (688-7001) | EACH | 8 | $750.00 | $1,559.00 | $928.00 | $900.00 | $876.24 | $970.00 | $1,100.00 |
| 120 | Pedestrian detector controller unit (688-7003) | EACH | 1 | $3,000.00 | $567.00 | $3,550.00 | $3,400.00 | $3,353.53 | $3,700.00 | $4,000.00 |
| 121 | Bbu system (external battery cabinet) (6007-7001) | EACH | 3 | $8,102.12 | $8,000.00 | $9,100.00 | $8,850.00 | $8,624.47 | $9,720.00 | $10,500 |
| 122 | RVDS (presence det)(install only) (6008-7004) | EACH | 16 | $840.65 | $1,500.00 | $1,200.00 | $1,141.00 | $1,140.25 | $1,270.00 | $1,400.00 |
| 123 | RVDS (advance det)(install only) (6008-7005) | EACH | 6 | $985.76 | $1,000.00 | $1,200.00 | $1,160.00 | $1,152.70 | $1,290.00 | $1,400.00 |
| 124 | Fiber optic CBL (single-mode)(12 fiber) (6027-7001) | LF | 680 | $2.95 | $2.00 | $5.00 | $4.75 | $4.73 | $6.00 | $5.75 |
| 125 | Fiber optic fusion splice (6027-7004) | EACH | 36 | $55.55 | $330.50 | $18.00 | $18.00 | $17.03 | $50.00 | $20.00 |
| 126 | Fiber optic patch panel (12 position) (6027-7005) | EACH | 3 | $850.25 | $4,000.00 | $4,000.00 | $3,800.00 | $3,769.75 | $4,350.00 | $5,000.00 |
| 127 | Bridge deck cleaning (7001-7001) | SY | 3,288 | $10.00 | $4.00 | $7.00 | $13.50 | $10.00 | $1.00 | $2.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.