TxDOT contract A00193225 bid tabulation
Hazard Elimination & Safety, US 287 (FM 294 to 3.6 MI EAST OF FM 294). Let by Texas DOT on June 2, 2026, Armstrong, Amarillo District. 6 bids received; low bid $6,922,966 by HJC Farms, Inc., -16% against the engineer's estimate of $8,256,774.
- Owner
- Texas DOT
- Letting
- 02 JUN 2026
- Pay items
- 68
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | HJC Farms, Inc. | $6,922,966 | Low | -16% |
| 2 | Gilvin-Terrill, LTD. | $7,485,977 | +8.0% | -9.0% |
| 3 | Highway Intelligent Traffic Solutions, Inc. | $7,883,063 | +14% | -5.0% |
| 4 | Gratiot Construction, LTD. | $8,234,416 | +19% | 0.0% |
| 5 | Ti-Zack Concrete, LLC | $9,301,859 | +34% | +13% |
| 6 | Roadway Specialties, Inc. | $9,923,822 | +43% | +20% |
Engineer's estimate: $8,256,774.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. HJC Farms, Inc. | 2. Gilvin-Terrill, LTD. | 3. Highway Intelligent Traffic Solutions, Inc. | 4. Gratiot Construction, LTD. | 5. Ti-Zack Concrete, LLC | 6. Roadway Specialties, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 1 | $850.00 | $1,000.00 | $2,861.50 | $600.00 | $679.20 | $2,640.10 | |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 5 | $1,275.00 | $1,000.00 | $3,433.80 | $1,500.00 | $679.20 | $2,913.18 | |
| 3 | Removing concrete (flume) (104-7041) | SY | 2,223 | $16.00 | $27.00 | $13.74 | $25.00 | $8.40 | $61.51 | |
| 4 | Remove (18") TRT/untrt base & asphalt pavement (105-7038) | SY | 4,692 | $13.75 | $20.00 | $17.35 | $20.00 | $30.00 | $32.95 | |
| 5 | Remove (22") TRT/untrt base & asphalt pavement (105-7042) | SY | 353 | $6.50 | $20.00 | $17.35 | $33.00 | $25.20 | $46.21 | |
| 6 | Excavation (roadway) (110-7001) | CY | 2,402 | $17.00 | $35.00 | $13.74 | $22.00 | $49.28 | $61.81 | |
| 7 | Embankment (final)(DC)(type B) (132-7004) | CY | 18,510 | $19.75 | $35.00 | $19.46 | $33.00 | $27.25 | $72.33 | |
| 8 | Blading (150-7002) | HR | 300 | $75.00 | $145.00 | $97.29 | $25.00 | $102.00 | $657.50 | |
| 9 | Drill seed (temporary_warm_cool) (164-7047) | ACRE | 46 | $730.00 | $700.00 | $560.50 | $700.00 | $828.00 | $1,088.40 | |
| 10 | Straw/hay mulch seed(permanent_rural_clay) (164-7058) | ACRE | 46 | $1,450.00 | $1,500.00 | $3,009.00 | $1,400.00 | $1,632.00 | $6,149.56 | |
| 11 | FL BS (compacted in place)(type A or B GR 4)(12") (247-7133) | SY | 8,906 | $48.00 | $40.00 | $56.64 | $45.00 | $54.00 | $59.18 | |
| 12 | Prime coat (MC-30) (310-7004) | GAL | 2,228 | $5.75 | $6.00 | $7.66 | $18.50 | $6.54 | $7.17 | |
| 13 | Emuls asphalt (erosion control)(CSS-1H) (314-7011) | GAL | 55,660 | $5.15 | $4.10 | $3.68 | $6.50 | $5.94 | $6.51 | |
| 14 | SP mixes SP-D sac-A PG70-28 (344-7057) | TON | 3,066 | $200.00 | $175.00 | $206.31 | $215.00 | $228.00 | $249.85 | |
| 15 | Tack coat (344-7077) | GAL | 3,597 | $7.00 | $5.00 | $6.35 | $6.00 | $7.86 | $8.61 | |
| 16 | Planing asphalt concrete pavement(2") (354-7051) | SY | 3,190 | $8.50 | $5.00 | $42.75 | $10.00 | $9.66 | $10.61 | |
| 17 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 360 | $300.00 | $365.00 | $250.00 | $238.57 | $400.00 | $420.00 | $460.25 |
| 18 | Riprap (concrete)(5 in) (432-7002) | CY | 5.90 | $745.00 | $750.00 | $1,228.34 | $1,100.00 | $1,440.00 | $2,226.11 | |
| 19 | Riprap (mow strip)(4 in) (432-7013) | CY | 4,546 | $457.00 | $475.00 | $545.90 | $530.00 | $727.20 | $487.05 | |
| 20 | Concrete box culvert (6 FT X 3 FT)(extend) (462-7066) | LF | 10 | $1,390.00 | $2,000.00 | $1,716.90 | $1,000.00 | $1,476.00 | $2,339.48 | |
| 21 | RC pipe (CL III)(30 in) (464-7007) | LF | 16 | $175.00 | $400.00 | $314.77 | $290.00 | $660.00 | $297.14 | |
| 22 | Set (type I)(S= 6 FT)(HW= 4 FT)(6:1)(C) (467-7130) | EACH | 1 | $32,875 | $25,000 | $4,807.32 | $27,000 | $9,000.00 | $22,201 | |
| 23 | Set (type II) (30 in) (RCP) (6: 1) (C) (467-7347) | EACH | 1 | $5,300.00 | $10,000 | $5,494.08 | $4,250.00 | $9,000.00 | $5,280.17 | |
| 24 | Adjusting inlets (479-7002) | EACH | 6 | $4,350.00 | $2,500.00 | $629.53 | $3,000.00 | $5,400.00 | $2,978.93 | |
| 25 | Removing structure (set) (496-7004) | EACH | 2 | $215.00 | $500.00 | $1,373.52 | $880.00 | $2,760.00 | $488.43 | |
| 26 | Removing structure (pipe) (496-7007) | LF | 8 | $55.00 | $500.00 | $171.69 | $60.00 | $420.00 | $244.21 | |
| 27 | Removing structure (box culvert) (496-7008) | LF | 4 | $105.00 | $500.00 | $400.61 | $470.00 | $1,440.00 | $244.22 | |
| 28 | Mobilization (500-7001) | LS | 1 | $630,000 | $400,000 | $700,000 | $757,774 | $814,000 | $468,000 | $1,039,508 |
| 29 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $16,000 | $3,300.00 | $20,000 | $33,125 | $19,000 | $7,800.00 | $4,535.51 |
| 30 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $7,500.00 | $18,500 | $11,800 | $6,400.00 | $18,000 | $5,443.44 |
| 31 | TMA (stationary) (505-7001) | DAY | 293 | $210.00 | $150.00 | $375.00 | $227.95 | $25.00 | $264.00 | $405.89 |
| 32 | TMA (mobile operation) (505-7002) | HR | 20 | $100.00 | $300.00 | $95.00 | $83.98 | $65.00 | $276.00 | $97.76 |
| 33 | Sandbags for erosion control (8") (506-7037) | LF | 1,000 | $20.00 | $5.00 | $11.80 | $10.00 | $6.00 | $32.90 | |
| 34 | Temporary sediment control fence (install) (506-7039) | LF | 1,725 | $5.00 | $4.00 | $5.31 | $4.50 | $7.20 | $13.15 | |
| 35 | Temporary sediment control fence (remove) (506-7041) | LF | 1,725 | $1.00 | $1.00 | $2.73 | $1.10 | $2.40 | $3.13 | |
| 36 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 2,450 | $5.00 | $5.00 | $12.17 | $3.00 | $8.40 | $15.61 | |
| 37 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,450 | $1.00 | $1.00 | $2.73 | $1.10 | $6.00 | $3.13 | |
| 38 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 2,272 | $100.00 | $110.00 | $78.93 | $125.00 | $198.00 | $91.48 | |
| 39 | Permanent CTB (single slope) (type 4) (42 ) (514-7003) | LF | 100 | $243.00 | $350.00 | $188.10 | $350.00 | $414.00 | $453.56 | |
| 40 | Cable barrier system (install)(TL-4) (543-7002) | LF | 57,253 | $12.50 | $10.50 | $12.15 | $11.00 | $15.60 | $9.81 | |
| 41 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 38 | $4,200.00 | $2,500.00 | $2,666.80 | $3,750.00 | $3,360.00 | $2,826.07 | |
| 42 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 2 | $35,000 | $35,000 | $29,242 | $32,000 | $5,400.00 | $40,870 | |
| 43 | In RD IL (type SA) 50B-12-12(400W EQ)LED (610-7185) | EACH | 10 | $8,250.00 | $7,235.00 | $7,500.00 | $6,576.36 | $8,000.00 | $8,190.00 | $8,974.88 |
| 44 | In RD IL (type ST) 50T-12-12(400W EQ)LED (610-7233) | EACH | 36 | $7,800.00 | $7,550.00 | $7,500.00 | $6,789.94 | $8,300.00 | $8,550.00 | $9,369.38 |
| 45 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 10,089 | $9.00 | $19.00 | $12.00 | $13.69 | $21.00 | $21.60 | $23.67 |
| 46 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 1,355 | $25.00 | $30.00 | $20.00 | $20.25 | $30.00 | $34.20 | $37.48 |
| 47 | Install ground box (W/secure lid) (624-7014) | EACH | 52 | $1,800.00 | $1,700.00 | $2,500.00 | $1,985.79 | $1,850.00 | $1,920.00 | $2,104.00 |
| 48 | Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048) | EACH | 3 | $9,850.00 | $10,075 | $7,500.00 | $9,715.75 | $11,000 | $11,400 | $12,493 |
| 49 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 5 | $995.00 | $1,000.00 | $860.66 | $1,150.00 | $1,321.20 | $1,010.22 | |
| 50 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 33 | $825.00 | $1,000.00 | $835.44 | $1,150.00 | $1,009.20 | $824.56 | |
| 51 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 2 | $1,000.00 | $1,000.00 | $1,150.02 | $1,150.00 | $1,369.20 | $1,151.69 | |
| 52 | Install small roadside sign support and assembly (inst sign only) (644-7064) | EACH | 6 | $175.00 | $450.00 | $736.37 | $525.00 | $354.00 | $181.22 | |
| 53 | Remove SM RD SN sup&AM (644-7073) | EACH | 11 | $100.00 | $100.00 | $134.92 | $115.00 | $408.00 | $75.42 | |
| 54 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BR) (658-7033) | EACH | 24 | $48.00 | $50.00 | $37.49 | $60.00 | $57.60 | $41.90 | |
| 55 | Remove delin & object marker assms (658-7078) | EACH | 4 | $15.00 | $15.00 | $10.41 | $18.00 | $277.20 | $12.63 | |
| 56 | Install OM SM RD sign (1-OM-con)R (658-7080) | EACH | 11 | $200.00 | $15.00 | $32.93 | $18.00 | $51.60 | $50.39 | |
| 57 | Inst delineator assembly (D-SW)SZ 1(WFLX)GNDLL(BR) (658-7109) | EACH | 57 | $150.00 | $100.00 | $66.46 | $115.00 | $147.60 | $89.80 | |
| 58 | Install object marker assembly (OM-2Z)(yflx)GNDLL(BI) (658-7254) | EACH | 2 | $150.00 | $100.00 | $73.54 | $115.00 | $156.00 | $97.83 | |
| 59 | Install OM SM RD sign (1-OM-PW)Y (658-7317) | EACH | 23 | $25.00 | $15.00 | $14.54 | $17.00 | $16.80 | $19.41 | |
| 60 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 5 | $25.00 | $15.00 | $14.54 | $17.00 | $16.80 | $19.37 | |
| 61 | Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008) | LF | 830 | $1.60 | $1.50 | $1.30 | $1.70 | $1.80 | $1.97 | |
| 62 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 2,402 | $1.70 | $1.60 | $1.30 | $1.80 | $1.92 | $2.10 | |
| 63 | Reflectorized pavement marking type I (W)12"(lane drop)(090MIL) (666-7026) | LF | 365 | $2.60 | $2.50 | $2.36 | $2.90 | $3.00 | $3.29 | |
| 64 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 30 | $21.00 | $20.00 | $11.80 | $25.00 | $24.00 | $26.30 | |
| 65 | Type I high perf PM (W)6"(solid)(090MIL) (666-7292) | LF | 6,225 | $1.50 | $1.50 | $1.18 | $1.75 | $1.80 | $1.97 | |
| 66 | Type I high perf PM (Y)6"(solid)(090MIL) (666-7304) | LF | 1,371 | $1.50 | $1.50 | $1.18 | $1.75 | $1.80 | $1.97 | |
| 67 | Eliminating existing PM & markers (6") (677-7002) | LF | 5,165 | $1.50 | $1.50 | $0.53 | $1.80 | $1.80 | $1.97 | |
| 68 | Aluminum electrical cond (#6 XHHW) (6071-7003) | LF | 34,332 | $2.15 | $2.50 | $2.50 | $1.62 | $2.70 | $2.82 | $3.09 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 2, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.