TxDOT contract A00197661 bid tabulation

Install Traffic Signal, Various (VARIOUS LOCATIONS DISTRICTWIDE to .). Let by Texas DOT on January 7, 2026, Travis, Austin District. 5 bids received; low bid $986,475 by Austin Traffic Signal Construction Co., Inc., +20% against the engineer's estimate of $825,443.

Owner
Texas DOT
Letting
07 JAN 2026
Pay items
118
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Austin Traffic Signal Construction Co., Inc.$986,475Low+20%
2Elecnor Belco Electric, Inc.$1,109,896+13%+34%
3The Levy Company, Inc.$1,140,868+16%+38%
4Sice, Inc.$1,379,999+40%+67%
5Lumin8 Transportation Technologies, LLC$1,565,357+59%+90%
TxDOT contract A00197661: bids by rank

Engineer's estimate: $825,443.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Austin Traffic Signal Construction Co., Inc.2. Elecnor Belco Electric, Inc.3. The Levy Company, Inc.4. Sice, Inc.5. Lumin8 Transportation Technologies, LLC
1Removing concrete (miscellaneous) (104-7046)SY10$150.00$250.00$47.00$350.00$345.00$104.00
2Embankment (vehicle)(OC)(type B) (132-7015)CY5$75.00$500.00$938.00$1,200.00$1,159.00$369.00
3Furn & place topsoil (4") (160-7002)SY500$7.00$10.00$12.00$10.00$14.00$79.00
4Block sodding (162-7002)SY50$25.00$50.00$37.00$6.50$9.00$53.00
5Broadcast seed (permanent_urban_clay) (164-7004)SY300$9.50$10.00$3.60$1.50$3.00$5.00
6Vegetative watering (168-7001)TGL6$150.00$200.00$840.00$900.00$302.00$583.00
7Soil retention blankets (CL 1) (type B) (169-7043)SY300$12.00$10.00$4.20$1.10$5.00$5.85
8Flowable backfill (401-7001)CY10$300.00$500.00$237.00$370.00$346.00$526.00
9Drilled shaft (24 in) (416-7004)LF75$305.00$200.00$446.00$290.00$250.00$300.00
10Drilled shaft (36 in) (416-7006)LF75$385.00$325.00$710.00$570.00$861.00$672.00
11Drilled shaft (42 in) (416-7007)LF75$460.00$470.00$762.00$670.00$928.00$805.00
12Drilled shaft (48 in) (416-7008)LF75$550.00$530.00$879.00$700.00$1,012.00$1,110.00
13Riprap (concrete)(CL B) (432-7005)CY10$750.00$1,000.00$580.00$1,100.00$1,584.00$937.00
14Riprap (mow strip)(5 in) (432-7014)CY10$625.00$1,000.00$580.00$1,200.00$1,210.00$1,317.00
15Mobilization (callout 1) (500-7003)EACH25$1,500.00$1,500.00$2,900.00$3,700.00$2,769.69$5,156.00
16Mobilization (callout 2) (500-7004)EACH15$1,500.00$2,500.00$2,900.00$9,800.00$2,769.69$7,946.00
17Mobilization (emergency) (500-7033)EACH15$2,500.00$2,000.00$4,250.00$1,500.00$3,662.11$6,245.00
18TMA (stationary) (505-7001)DAY20$225.00$500.00$381.00$64.00$674.00$1,063.00
19Rock filter dams (install) (type 2) (506-7002)LF50$65.00$100.00$62.00$40.00$153.00$87.00
20Rock filter dams (remove) (506-7011)LF50$18.00$50.00$33.00$10.00$64.00$47.00
21Biodegradable erosion control logs (install) (12") (506-7044)LF100$10.00$10.00$11.00$5.00$13.00$15.00
22Biodegradable erosion control logs (remove) (506-7046)LF100$5.00$5.00$3.60$2.00$4.00$5.00
23Right of way markers (538-7001)EACH3$925.00$500.00$1,680.00$60.00$615.00$441.00
24Metal W-beam guard fence (timber post) (540-7001)LF100$60.00$50.00$38.00$32.00$42.00$54.00
25Metal W-beam guard fence (steel post) (540-7002)LF100$60.00$75.00$54.00$37.00$45.00$76.00
26Metal beam guard fence trans (thrie-beam) (540-7005)EACH2$4,500.00$3,500.00$3,350.00$2,725.00$2,882.00$4,759.00
27Downstream anchor terminal section (540-7015)EACH2$3,500.00$2,500.00$2,264.00$1,600.00$1,762.00$3,217.00
28Remove metal beam guard fence (542-7001)LF100$18.00$10.00$10.30$3.60$3.30$14.00
29Remove terminal anchor section (542-7002)EACH2$1,500.00$1,000.00$343.00$340.00$320.30$486.00
30Guardrail end treatment (install) (544-7001)EACH2$6,250.00$3,000.00$4,541.00$4,000.00$5,603.70$6,452.00
31Guardrail end treatment (move & reset) (544-7002)EACH2$2,500.00$5,000.00$5,138.00$640.00$800.60$7,299.00
32Conduit (PVC) (schedule 40) (2") (618-7030)LF500$27.50$25.00$14.00$16.00$40.20$30.00
33Conduit (PVC) (schedule 40) (2") (bore) (618-7031)LF150$75.00$60.00$19.00$55.00$53.70$43.00
34Conduit (PVC) (schedule 40) (3") (618-7036)LF100$42.00$50.00$45.00$26.00$42.00$31.00
35Conduit (PVC) (schedule 40) (3") (bore) (618-7037)LF100$100.00$75.00$48.00$39.00$53.80$44.00
36Conduit (RM) (3/4") (618-7070)LF100$35.50$45.00$30.00$27.00$24.20$43.00
37Conduit (RM) (2") (618-7078)LF100$55.00$50.00$45.00$49.00$50.50$73.00
38ITS multi-duct CND (PVC-40) (619-7001)LF100$20.00$45.00$48.00$26.00$68.30$51.00
39ITS multi-duct CND (PVC-40)(concrete encse) (619-7003)LF250$22.00$55.00$27.00$40.00$79.70$129.00
40Electrical conductor (no.14) insulated (620-7002)LF5,000$1.25$2.00$1.60$1.05$1.00$1.66
41Electrical conductor (no.8) insulated (620-7008)LF1,000$1.75$2.00$2.70$1.95$2.50$3.27
42Electrical conductor (no.6) bare (620-7009)LF4,000$1.85$2.00$2.25$2.00$2.90$3.42
43Electrical conductor (no.6) insulated (620-7010)LF5,000$2.10$3.00$2.80$2.30$3.30$3.61
44Electrical conductor (no.4) bare (620-7011)LF1,000$2.75$3.00$3.20$2.85$3.80$5.28
45Electrical conductor (no.4) insulated (620-7012)LF500$3.50$4.00$3.50$3.10$4.40$5.78
46Electrical conductor (no.2) bare (620-7015)LF250$4.70$4.00$4.80$4.50$5.70$6.72
47Electrical conductor (no.2) insulated (620-7016)LF500$4.50$5.00$5.52$4.90$6.50$7.64
48Electrical conductor (1/0) bare (620-7019)LF250$5.70$5.00$7.26$6.25$7.90$9.28
49Electrical conductor (1/0) insulated (620-7020)LF250$5.75$6.00$8.50$6.50$8.50$10.36
50ITS GND box type 2 (366048)W/apron (623-7034)EACH3$5,000.00$9,000.00$12,068$12,100$8,478.50$12,321
51Remove ITS ground box (623-7041)EACH3$880.00$1,500.00$2,078.00$2,700.00$390.00$765.00
52Ground box type A (122311)W/apron (624-7002)EACH10$1,650.00$1,200.00$1,465.00$1,600.00$2,126.00$1,510.00
53Ground box type D (162922)W/apron (624-7008)EACH7$1,800.00$2,000.00$1,547.00$2,100.00$2,622.00$2,265.00
54Remove ground box (624-7013)EACH3$425.00$500.00$413.00$140.00$513.00$510.00
55Zinc-coat steel wire strand (1/4") (625-7002)LF250$4.00$3.00$3.38$3.00$8.00$2.00
56Zinc-coat steel wire strand (3/8") (625-7004)LF250$5.00$3.00$4.60$3.00$7.00$3.00
57Timber pole (CL 2) 50 FT (627-7004)EACH2$3,500.00$2,000.00$6,496.00$2,500.00$3,269.00$3,498.00
58Remove electrical services (628-7002)EACH2$610.00$500.00$1,143.00$500.00$2,071.00$803.00
59Elc SRV type D 120/240 060(NS)GS(N)SP(O) (628-7136)EACH1$6,500.00$3,500.00$7,002.00$6,900.00$9,783.00$7,942.00
60Elc SRV type D 120/240 060(NS)GS(N)SP(U) (628-7137)EACH3$8,000.00$3,000.00$8,349.00$7,600.00$9,258.00$6,760.00
61Elc SRV type D 120/240 070(NS)GS(N)SP(U) (628-7179)EACH1$8,500.00$3,000.00$8,923.00$7,600.00$9,283.00$6,785.00
62Elc SRV type D 120/240 100(NS)GS(N)SP(O) (628-7233)EACH2$9,000.00$3,500.00$9,448.00$6,900.00$10,844$8,167.00
63Elc SRV type D 120/240 100(NS)GS(N)SP(U) (628-7234)EACH1$9,500.00$3,000.00$9,973.00$7,700.00$9,374.00$6,375.00
64Relocate existing overhd sign sup (650-7192)EACH1$600.00$9,000.00$22,220$10,400$23,393$18,850
65Remove overhd sign sup (650-7193)EACH1$10,600$6,000.00$9,495.00$3,800.00$4,175.00$9,550.00
66Remove sign walkway (654-7007)EACH1$590.00$2,000.00$3,798.00$1,400.00$3,651.70$9,550.00
67Remove conductor (690-7150)LF100$1.00$10.00$9.50$0.60$0.60$1.84
68Install circuit breaker (690-7234)EACH2$200.00$600.00$597.00$220.00$576.00$330.00
69Lane closure(setup & rem)(typ 7) (790-7007)EACH5$1,500.00$8,000.00$5,272.00$3,100.00$4,890.20$7,493.00
70Lane closure(setup & rem)(typ 11) (790-7011)EACH5$1,500.00$3,000.00$3,222.00$1,500.00$4,379.00$4,578.00
71Lane closure(setup & rem)(typ 14) (790-7014)EACH5$1,500.00$2,000.00$3,222.00$2,750.00$4,379.00$4,578.00
72Lane closure(setup & rem)(typ 18) (790-7018)EACH5$1,700.00$1,500.00$3,222.00$500.00$3,800.00$4,578.00
73Subsurface util locate (non-paved area) (5061-7001)EACH10$1,500.00$1,000.00$807.00$1,600.00$1,343.00$502.00
74Install DMS (pole MTD cabinet) (6004-7001)EACH1$1,500.00$10,000$2,848.00$10,900$7,831.00$3,212.00
75Install DMS (foundation MTD cabinet) (6004-7002)EACH1$3,750.00$15,000$2,622.00$15,600$16,485$3,212.00
76ITS com CBL (ethernet) (6005-7001)LF500$3.00$10.00$4.00$1.45$9.00$2.10
77RVDS (presence and advance detection) (6008-7003)EACH2$8,500.00$7,500.00$9,704.00$2,400.00$11,860$11,061
78ITS pole (60 FT)(90 MPH) (6011-7003)EACH1$24,450$31,000$28,559$30,100$38,610$24,602
79ITS pole (40 FT)(90 MPH) (6011-7020)EACH1$15,000$15,000$14,178$13,900$19,195$43,002
80ITS pole MNTD cab (type 2)(conf 1) (6011-7028)EACH1$6,160.00$12,000$5,820.00$5,700.00$7,162.00$8,266.00
81ITS pole MNT cab (type 1)(conf 1) (6011-7041)EACH1$6,000.00$10,000$5,364.00$4,900.00$9,425.00$8,086.00
82ITS radio(SNGL)(5 GHZ)-I-U (6014-7001)EACH1$4,900.00$3,500.00$4,415.00$6,400.00$7,867.00$5,119.00
83ITS radio (dual) (5 GHZ/5 GHZ)-I-U (6014-7002)EACH1$6,200.00$5,000.00$4,962.00$7,000.00$5,795.00$7,845.00
84Relocate ITS radio (6014-7006)EACH1$1,200.00$1,000.00$1,000.00$2,300.00$1,924.00$3,164.00
85Remove ITS radio (6014-7007)EACH1$1,000.00$500.00$500.00$260.00$962.00$1,624.00
86CCTV field equip (digital) (install only) (6018-7001)EACH2$1,250.00$1,000.00$1,500.00$2,800.00$1,154.00$2,870.00
87Relocate CCTV field equipment (6018-7007)EACH1$1,500.00$1,500.00$1,000.00$3,800.00$1,924.00$5,431.00
88Remove CCTV field equipment (6018-7008)EACH1$1,000.00$500.00$500.00$470.00$825.00$478.00
89Fiber optic CBL (single-mode)(12 fiber) (6027-7001)LF2,500$2.00$4.00$3.20$9.00$6.00$2.24
90Fiber optic fusion splice (6027-7004)EACH100$50.00$40.00$50.00$49.00$81.00$61.00
91Fiber optic patch panel (12 position) (6027-7005)EACH2$2,320.00$3,000.00$1,528.00$1,200.00$3,507.00$1,113.00
92Fiber optic CBL(single-mode)(144 fiber) (6027-7006)LF5,000$4.25$5.00$5.62$5.25$14.00$3.77
93Fiber optic patch panel (144 positions) (6027-7008)EACH2$7,100.00$14,000$7,554.00$8,500.00$25,269$3,875.00
94Fiber optic CBL (single-mode)(6 fiber) (6027-7011)LF500$1.70$3.00$1.30$9.00$6.00$2.36
95Remove fiber optic cable (6027-7018)LF1,000$1.50$2.00$1.00$1.15$4.00$1.23
96Relocate fiber optic cable (6027-7023)LF100$6.00$10.00$15.00$10.00$10.00$4.75
97Fiber optic patch panel (72 position) (6027-7032)EACH2$3,750.00$7,500.00$6,702.00$7,900.00$13,057$3,958.00
98Fiber optic pigtail (12 fiber) (6027-7036)LF250$2.00$10.00$2.00$9.00$6.00$147.00
99Fiber optic splice enclosure (6027-7037)EACH2$1,350.00$2,500.00$1,172.00$1,800.00$3,506.50$1,643.00
100Fiber optic patch panel (48 position) (6027-7038)EACH2$2,250.00$6,000.00$5,576.00$5,100.00$8,537.40$1,787.00
101FO CBL (12 SMF)(aerial) (6027-7039)LF100$3.00$20.00$5.00$13.00$14.80$4.88
102FO CBL (144 SMF)(aerial) (6027-7040)LF100$6.00$30.00$10.00$8.75$29.00$6.54
103FO splice enclosure (type 1)(aerial) (6027-7041)EACH2$1,550.00$2,000.00$1,200.00$1,800.00$3,027.00$1,255.00
104Fiber optic jumpers (6027-7042)EACH2$90.00$100.00$100.00$210.00$81.00$659.00
105Ethernet switch (install only) (6036-7001)EACH2$1,000.00$1,000.00$1,000.00$490.00$1,536.00$534.00
106Spread spectrum radio (6043-7001)EACH2$4,300.00$3,000.00$5,814.00$2,500.00$4,963.00$4,521.00
107ITS GRND MNT cab (type 6)(conf 2) (6050-7009)EACH1$16,000$15,000$15,242$19,800$14,875$24,887
108Remove DMS (6054-7003)EACH1$3,800.00$6,000.00$3,500.00$4,400.00$5,747.00$6,799.00
109Remove existing lane control system (6080-7001)EACH2$1,500.00$5,000.00$2,500.00$5,300.00$1,924.00$6,799.00
110Remove existing fiber hub (6080-7002)EACH1$6,000.00$10,000$500.00$9,300.00$2,211.00$13,598
111Relocate existing fib opt DMS sys(type-2) (6080-7004)EACH1$4,000.00$10,000$5,000.00$19,400$5,224.00$20,823
112Relocate existing fib opt DMS sys(type-3) (6080-7005)EACH1$3,500.00$11,000$5,000.00$13,500$6,545.00$8,964.00
113Relocate existing lane control sys. (6080-7006)EACH1$4,300.00$8,000.00$2,500.00$2,000.00$3,847.00$14,347
114Remove communication cabinet (6080-7007)EACH1$750.00$1,000.00$1,000.00$970.00$1,187.00$6,799.00
115Relocate communication cabinet (6080-7008)EACH1$750.00$3,000.00$3,500.00$910.00$3,561.00$14,680
116Remove existing RVSD (6080-7009)EACH2$1,200.00$500.00$500.00$520.00$962.00$478.00
117Relocate existing RVSD (6080-7010)EACH2$3,300.00$750.00$1,500.00$4,700.00$1,924.00$1,373.00
118Fiber hub (IP) (6125-7001)EACH1$3,000.00$25,000$15,242$11,900$22,679$27,163
TxDOT contract A00197661: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of January 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy