TxDOT contract A00197666 bid tabulation
Install Illumination, IH 14 (Jasper Dr to Rosewood Dr). Let by Texas DOT on June 3, 2026, Bell, Waco District. 11 bids received; low bid $2,981,026 by Highway Intelligent Traffic Solutions, Inc., -21% against the engineer's estimate of $3,792,763.
- Owner
- Texas DOT
- Letting
- 03 JUN 2026
- Pay items
- 45
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Highway Intelligent Traffic Solutions, Inc. | $2,981,026 | Low | -21% |
| 2 | Albatross Construction LLC | $3,000,000 | +1.0% | -21% |
| 3 | E-Z Bel Construction, LLC | $3,169,821 | +6.0% | -16% |
| 4 | Vaca Underground Utilities Inc | $3,259,344 | +9.0% | -14% |
| 5 | Sice, Inc. | $3,381,523 | +13% | -11% |
| 6 | Elecnor Belco Electric, Inc. | $3,597,582 | +21% | -5.0% |
| 7 | Florida Traffic Control Devices, Inc. | $3,672,672 | +23% | -3.0% |
| 8 | Cross Plus Construction, LLC | $3,677,400 | +23% | -3.0% |
| 9 | The Levy Company, Inc. | $3,823,417 | +28% | +1.0% |
| 10 | Austin Traffic Signal Construction Co., Inc. | $3,994,135 | +34% | +5.0% |
| 11 | Digg Commercial, LLC | $4,313,617 | +45% | +14% |
Engineer's estimate: $3,792,763.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Highway Intelligent Traffic Solutions, Inc. | 2. Albatross Construction LLC | 3. E-Z Bel Construction, LLC | 4. Vaca Underground Utilities Inc | 5. Sice, Inc. | 6. Elecnor Belco Electric, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 169 | $60.00 | $30.68 | $30.70 | $4.75 | $45.00 | $5.63 | $5.70 |
| 2 | Removing concrete (rail) (104-7036) | LF | 19.50 | $80.00 | $152.22 | $94.25 | $100.00 | $45.00 | $82.97 | $32.00 |
| 3 | Drill seed (permanent_urban_clay) (164-7012) | SY | 2,200 | $0.80 | $0.47 | $4.17 | $0.23 | $0.35 | $0.27 | $0.60 |
| 4 | Drill seed (temporary_warm_cool) (164-7015) | SY | 2,200 | $0.80 | $0.47 | $4.17 | $0.17 | $0.35 | $0.20 | $0.60 |
| 5 | Vegetative watering (168-7001) | TGL | 36 | $100.00 | $118.00 | $357.00 | $250.00 | $10.00 | $134.14 | $591.00 |
| 6 | Drilled shaft (high mast pole) (54 in) (416-7036) | LF | 668 | $750.00 | $549.94 | $664.65 | $570.00 | $600.00 | $832.09 | $651.00 |
| 7 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 20 | $500.00 | $258.68 | $297.43 | $400.00 | $400.00 | $146.48 | $432.00 |
| 8 | Class C concrete (wingwalls) (420-7146) | CY | 0.77 | $8,000.00 | $4,720.00 | $4,069.80 | $5,500.00 | $2,300.00 | $3,122.27 | $8,037.00 |
| 9 | Riprap (concrete)(4 in) (432-7001) | CY | 61 | $1,300.00 | $531.00 | $1,035.30 | $900.00 | $550.00 | $806.02 | $591.00 |
| 10 | Riprap (mow strip)(4 in) (432-7013) | CY | 63 | $700.00 | $767.00 | $963.90 | $585.00 | $550.00 | $669.71 | $692.00 |
| 11 | Mobilization (500-7001) | LS | 1 | $271,612 | $243,559 | $196,026 | $250,000 | $125,000 | $260,911 | $318,000 |
| 12 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $14,000 | $2,655.00 | $10,776 | $10,000 | $3,000.00 | $6,002.78 | $13,896 |
| 13 | Portable changeable message sign (503-7002) | EACH | 2 | $12,500 | $8,850.00 | $10,710 | $7,500.00 | $7,500.00 | $9,845.15 | $4,864.00 |
| 14 | TMA (stationary) (505-7001) | DAY | 181 | $300.00 | $189.89 | $269.05 | $375.00 | $80.00 | $343.48 | $139.00 |
| 15 | TMA (mobile operation) (505-7002) | HR | 500 | $80.00 | $83.98 | $41.65 | $33.00 | $80.00 | $95.94 | $67.00 |
| 16 | Temporary sediment control fence (install) (506-7039) | LF | 2,800 | $4.50 | $3.54 | $5.95 | $1.00 | $1.00 | $3.50 | $3.50 |
| 17 | Temporary SDMT cont fence (inlet protection) (506-7040) | LF | 200 | $6.00 | $11.80 | $35.70 | $1.00 | $1.00 | $4.74 | $4.80 |
| 18 | Temporary sediment control fence (remove) (506-7041) | LF | 3,000 | $1.80 | $1.77 | $2.98 | $1.00 | $1.00 | $1.13 | $1.20 |
| 19 | Metal W-beam guard fence (steel post) (540-7002) | LF | 850 | $35.00 | $36.58 | $36.89 | $33.50 | $32.00 | $39.71 | $40.00 |
| 20 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 1 | $2,500.00 | $2,596.00 | $2,618.00 | $2,675.00 | $30,000 | $3,170.75 | $3,162.16 |
| 21 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,600.00 | $1,416.00 | $1,428.00 | $1,425.00 | $2,000.00 | $1,689.09 | $1,685.00 |
| 22 | Remove metal beam guard fence (542-7001) | LF | 100 | $4.75 | $3.54 | $3.57 | $2.00 | $4.00 | $2.37 | $2.40 |
| 23 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $300.00 | $177.00 | $178.50 | $150.00 | $175.00 | $177.80 | $178.00 |
| 24 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $4,000.00 | $3,540.00 | $3,570.00 | $3,500.00 | $3,500.00 | $4,148.64 | $4,137.00 |
| 25 | Guardrail end treatment (remove) (544-7003) | EACH | 3 | $400.00 | $295.00 | $297.50 | $150.00 | $350.00 | $177.80 | $178.00 |
| 26 | Remove RD IL asm (bridge mount) (610-7006) | EACH | 1 | $550.00 | $406.72 | $225.78 | $800.00 | $550.00 | $344.53 | $464.00 |
| 27 | Remove RD IL asm (trans-base) (610-7009) | EACH | 37 | $750.00 | $730.64 | $225.78 | $700.00 | $550.00 | $359.47 | $618.00 |
| 28 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 5 | $5,600.00 | $4,991.13 | $4,636.95 | $5,000.00 | $6,000.00 | $4,222.77 | $5,225.00 |
| 29 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 19,529 | $15.00 | $11.16 | $10.18 | $8.00 | $15.00 | $12.34 | $15.00 |
| 30 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 2,381 | $28.00 | $20.07 | $24.88 | $30.00 | $20.00 | $30.46 | $30.00 |
| 31 | Conduit (prepare) (618-7090) | LF | 6,822 | $3.00 | $1.01 | $1.27 | $0.50 | $1.00 | $1.06 | $5.00 |
| 32 | Remove ground box (624-7013) | EACH | 22 | $350.00 | $531.80 | $244.46 | $175.00 | $400.00 | $296.33 | $410.00 |
| 33 | Install ground box (W/secure lid) (624-7014) | EACH | 83 | $2,200.00 | $2,533.31 | $1,877.32 | $1,750.00 | $2,250.00 | $1,665.52 | $1,728.00 |
| 34 | Retro ground box (W/secure lid) (624-7015) | EACH | 35 | $1,500.00 | $1,911.61 | $971.10 | $845.00 | $1,650.00 | $1,028.57 | $1,847.00 |
| 35 | Remove electrical services (628-7002) | EACH | 6 | $800.00 | $1,153.28 | $719.49 | $550.00 | $650.00 | $723.57 | $1,236.00 |
| 36 | Elc SRV type A 240/480 060(NS)SS(E)SP(U) (628-7049) | EACH | 10 | $8,500.00 | $9,124.57 | $7,947.86 | $7,000.00 | $7,500.00 | $7,723.18 | $9,165.00 |
| 37 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 17 | $60.00 | $53.10 | $53.55 | $34.00 | $85.00 | $40.30 | $40.00 |
| 38 | Remove above-ground conduit (690-7144) | LF | 261 | $15.00 | $29.84 | $14.03 | $10.00 | $7.00 | $7.11 | $5.00 |
| 39 | Remove conductor (690-7150) | LF | 59,901 | $1.00 | $0.40 | $0.43 | $0.20 | $1.00 | $0.25 | $0.80 |
| 40 | Replace fuse (690-7218) | EACH | 20 | $65.00 | $45.54 | $129.14 | $25.00 | $60.00 | $47.37 | $126.00 |
| 41 | Replace breakaway fuse holder (690-7220) | EACH | 10 | $180.00 | $155.81 | $276.70 | $220.00 | $210.00 | $47.37 | $226.00 |
| 42 | Ground box (prepare) (6013-7006) | EACH | 3 | $400.00 | $340.64 | $432.01 | $600.00 | $625.00 | $237.07 | $309.00 |
| 43 | Aluminum electrical cond (#6 XHHW) (6071-7003) | LF | 95,463 | $1.60 | $1.03 | $0.93 | $0.75 | $1.75 | $1.09 | $1.75 |
| 44 | LED HM(100 FT)(100MPH)(6FIXT)(type B) (6083-7007) | EACH | 22 | $62,000 | $48,945 | $48,396 | $62,000 | $60,000 | $58,468 | $59,530 |
| 45 | LED HM(100 FT)(100MPH)(6FIXT)(type B)SHLD (6083-7008) | EACH | 3 | $63,000 | $51,727 | $49,363 | $62,750 | $60,000 | $58,776 | $54,158 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 3, 2026. Compiled by Mirage Metrics.