TxDOT contract A00198611 bid tabulation
Rehabilitate Bridge, Various (Various Locations in Harris County to .). Let by Texas DOT on June 5, 2025, Harris, Houston District. 9 bids received; low bid $1,851,563 by Isi Contracting, Inc., -18% against the engineer's estimate of $2,249,519.
- Owner
- Texas DOT
- Letting
- 05 JUN 2025
- Pay items
- 24
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Isi Contracting, Inc. | $1,851,563 | Low | -18% |
| 2 | MBN Enterprises LLC | $1,860,650 | 0.0% | -17% |
| 3 | Garret Shields Infrastructure | $1,864,271 | +1.0% | -17% |
| 4 | Forde Construction Company, Inc. | $1,879,584 | +2.0% | -16% |
| 5 | Structural Integrity Group LLC | $1,965,931 | +6.0% | -13% |
| 6 | SCR Civil Construction, LLC | $2,107,285 | +14% | -6.0% |
| 7 | MC2 Civil, LLC | $2,167,571 | +17% | -4.0% |
| 8 | Pathfield Investments LLC | $2,224,239 | +20% | -1.0% |
| 9 | Built Right Construction of Oklahoma, LLC | $3,094,090 | +67% | +38% |
Engineer's estimate: $2,249,519.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Isi Contracting, Inc. | 2. MBN Enterprises LLC | 3. Garret Shields Infrastructure | 4. Forde Construction Company, Inc. | 5. Structural Integrity Group LLC | 6. SCR Civil Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 15 | $2,950.00 | $7,250.00 | $3,000.00 | $1,500.00 | $6,000.00 | $500.00 | $2,600.00 |
| 2 | Cem stabil BKFL (400-7010) | CY | 733 | $275.00 | $575.00 | $100.00 | $200.00 | $165.00 | $180.00 | $320.00 |
| 3 | Flowable backfill (401-7001) | CY | 17 | $450.00 | $850.00 | $700.00 | $600.00 | $595.00 | $625.00 | $900.00 |
| 4 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 74 | $260.00 | $225.00 | $200.00 | $150.00 | $139.00 | $205.00 | $275.00 |
| 5 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 750 | $327.00 | $75.00 | $210.00 | $200.00 | $185.00 | $175.00 | $195.00 |
| 6 | Riprap (concrete)(5 in) (432-7002) | CY | 539 | $840.00 | $351.00 | $700.00 | $450.00 | $702.00 | $644.00 | $675.00 |
| 7 | Riprap (concrete)(flume) (432-7012) | CY | 136 | $826.00 | $797.00 | $750.00 | $400.00 | $930.00 | $980.00 | $1,540.00 |
| 8 | Riprap (stone type R)(dry)(18 in) (432-7024) | CY | 2,285 | $150.00 | $260.00 | $210.00 | $250.00 | $214.00 | $270.00 | $215.00 |
| 9 | Cleaning and sealing existing joints (438-7001) | LF | 2,289 | $55.00 | $25.00 | $10.00 | $40.00 | $45.00 | $63.00 | $78.50 |
| 10 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 245 | $65.00 | $32.00 | $20.00 | $50.00 | $45.00 | $42.00 | $52.50 |
| 11 | Retrofit rail (type T631) (451-7020) | LF | 180 | $110.00 | $270.00 | $200.00 | $150.00 | $156.00 | $130.00 | $0.01 |
| 12 | Mobilization (500-7001) | LS | 1 | $22,272 | $50,000 | $185,000 | $180,000 | $178,000 | $88,500 | $176,000 |
| 13 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $9,727.25 | $3,500.00 | $5,000.00 | $5,000.00 | $1,700.00 | $16,500 | $6,000.00 |
| 14 | Portable changeable message sign (503-7001) | DAY | 30 | $117.00 | $200.00 | $200.00 | $100.00 | $200.00 | $1.00 | $135.00 |
| 15 | TMA (mobile operation) (505-7003) | DAY | 30 | $294.00 | $200.00 | $400.00 | $1,000.00 | $180.00 | $1.00 | $900.00 |
| 16 | Temporary sediment control fence (install) (506-7039) | LF | 1,500 | $5.00 | $5.00 | $6.00 | $5.00 | $4.25 | $1.00 | $6.00 |
| 17 | Temporary sediment control fence (remove) (506-7041) | LF | 1,500 | $2.00 | $5.00 | $1.00 | $1.00 | $1.60 | $1.00 | $3.00 |
| 18 | Metal W-beam guard fence (steel post) (540-7002) | LF | 230 | $40.00 | $50.00 | $45.00 | $40.00 | $38.00 | $35.00 | $0.01 |
| 19 | Short radius (28") (540-7013) | LF | 50 | $45.00 | $75.00 | $65.00 | $40.00 | $54.00 | $100.00 | $0.01 |
| 20 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,519.00 | $1,000.00 | $2,000.00 | $2,500.00 | $1,425.00 | $1,500.00 | $0.01 |
| 21 | Remove metal beam guard fence (542-7001) | LF | 161 | $4.25 | $7.00 | $10.00 | $1.00 | $10.00 | $3.00 | $0.01 |
| 22 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,080.00 | $4,200.00 | $5,000.00 | $4,000.00 | $3,300.00 | $4,500.00 | $0.01 |
| 23 | Bridge joint replacement (armor) (785-7010) | LF | 61 | $670.00 | $425.00 | $200.00 | $500.00 | $755.00 | $810.00 | $300.00 |
| 24 | Carbon fiber reinforced polymer protection (786-7001) | SF | 2,220 | $225.00 | $37.00 | $115.00 | $100.00 | $45.00 | $60.00 | $54.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.