TxDOT contract A00199633 bid tabulation
Bridge Maintenance, US 183 (US 183 at Clear Fork Brazos River to .). Let by Texas DOT on December 3, 2025, Stephens, Brownwood District. 7 bids received; low bid $1,341,645 by Built Right Construction of Oklahoma, LLC, +3.8% against the engineer's estimate of $1,293,068.
- Owner
- Texas DOT
- Letting
- 03 DEC 2025
- Pay items
- 54
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Built Right Construction of Oklahoma, LLC | $1,341,645 | Low | +4.0% |
| 2 | Premier Contractors LLC | $1,346,434 | 0.0% | +4.0% |
| 3 | Structural Integrity Group LLC | $1,346,607 | 0.0% | +4.0% |
| 4 | Scott Tucker Construction Company, LLC | $1,422,061 | +6.0% | +10% |
| 5 | SCR Civil Construction, LLC | $1,507,857 | +12% | +17% |
| 6 | Icos Management, LLC | $1,508,473 | +12% | +17% |
| 7 | THK Construction LLC | $2,054,795 | +53% | +59% |
Engineer's estimate: $1,293,068.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Built Right Construction of Oklahoma, LLC | 2. Premier Contractors LLC | 3. Structural Integrity Group LLC | 4. Scott Tucker Construction Company, LLC | 5. SCR Civil Construction, LLC | 6. Icos Management, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Excavation (channel) (110-7002) | CY | 5 | $100.00 | $500.00 | $150.00 | $226.00 | $573.00 | $220.00 | |
| 2 | Embankment (final)(OC)(type C) (132-7005) | CY | 80 | $125.00 | $190.00 | $94.00 | $132.00 | $88.00 | $88.00 | |
| 3 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 100 | $3.00 | $2.50 | $0.30 | $7.00 | $0.35 | $1.00 | |
| 4 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 1,300 | $2.00 | $0.40 | $2.50 | $0.25 | $2.00 | $0.30 | $1.00 |
| 5 | Broadcast seed (temporary_warm) (164-7005) | SY | 425 | $4.50 | $0.40 | $2.50 | $0.25 | $5.00 | $0.20 | $1.00 |
| 6 | Broadcast seed (temporary_cool) (164-7006) | SY | 425 | $4.50 | $0.40 | $2.50 | $2.50 | $5.00 | $0.20 | $1.00 |
| 7 | Vegetative watering (168-7001) | TGL | 23 | $100.00 | $250.00 | $100.00 | $75.00 | $223.00 | $70.00 | $1.00 |
| 8 | Soil ret BLKT(SL_steep_clay_long) (169-7006) | SY | 850 | $3.75 | $4.00 | $35.00 | $1.20 | $5.00 | $3.00 | $6.00 |
| 9 | Flowable backfill (401-7001) | CY | 63 | $550.00 | $500.00 | $350.00 | $650.00 | $597.00 | $894.00 | $385.00 |
| 10 | Temporary special shoring (403-7001) | SF | 234 | $125.00 | $35.00 | $20.00 | $80.00 | $51.50 | $6.00 | |
| 11 | Drilled shaft (18 in) (416-7002) | LF | 48 | $400.00 | $300.00 | $250.00 | $172.00 | $375.00 | $660.00 | |
| 12 | Class C concrete (column encasement) (420-7064) | CY | 8 | $1,500.00 | $1,500.00 | $4,750.00 | $6,150.00 | $3,644.00 | $1,320.00 | |
| 13 | Class C concrete (miscellaneous) (420-7067) | CY | 8 | $1,500.00 | $2,000.00 | $3,600.00 | $3,201.00 | $1,500.00 | $1,320.00 | |
| 14 | Class C concrete (culvert) (420-7152) | CY | 13 | $4,000.00 | $1,500.00 | $5,200.00 | $5,820.00 | $1,800.00 | $1,320.00 | |
| 15 | Penetrating concrete surface treatment (428-7001) | SY | 242 | $35.00 | $28.00 | $40.00 | $15.00 | $61.00 | $24.00 | $22.00 |
| 16 | Concrete structure repair(clean & coat WTH epoxy) (429-7001) | SF | 111 | $200.00 | $325.00 | $250.00 | $90.00 | $73.00 | $112.00 | $198.00 |
| 17 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 226 | $230.00 | $325.00 | $500.00 | $300.00 | $178.00 | $200.00 | $165.00 |
| 18 | Concrete structure repair (standard) (429-7009) | SF | 92 | $325.00 | $150.00 | $160.00 | $693.00 | $665.40 | $198.00 | |
| 19 | Concrete structure repair (pan girder hole repair) (429-7010) | EACH | 50 | $150.00 | $300.00 | $450.00 | $75.00 | $125.00 | $360.00 | $660.00 |
| 20 | Riprap (concrete)(5 in) (432-7002) | CY | 22.20 | $850.00 | $1,500.00 | $675.00 | $652.00 | $1,760.00 | $770.00 | |
| 21 | Riprap (mow strip)(4 in) (432-7013) | CY | 36 | $663.00 | $850.00 | $1,000.00 | $650.00 | $907.00 | $1,760.00 | $660.00 |
| 22 | Riprap (stone protection)(18 in) (432-7043) | CY | 65 | $350.00 | $250.00 | $260.00 | $322.00 | $313.00 | $220.00 | |
| 23 | Riprap (stone protection)(24 in) (432-7045) | CY | 55 | $325.00 | $350.00 | $250.00 | $260.00 | $328.00 | $313.00 | $242.00 |
| 24 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 61 | $65.00 | $65.00 | $49.00 | $351.00 | $55.00 | $55.00 | |
| 25 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 130 | $65.00 | $65.00 | $64.00 | $31.00 | $60.00 | $77.00 | |
| 26 | Rail (type C221) (450-7032) | LF | 138 | $135.00 | $225.00 | $490.00 | $354.00 | $411.00 | $880.00 | |
| 27 | Retrofit rail (type T131RC) (451-7049) | LF | 1,545 | $215.00 | $200.00 | $260.00 | $246.00 | $222.00 | $233.50 | $385.00 |
| 28 | Waterproofing (type 10) (458-7007) | SY | 20 | $67.50 | $115.00 | $35.00 | $99.00 | $419.00 | $550.00 | |
| 29 | Pipe (galvanized) (4 in X 6 in) (481-7048) | LF | 200 | $240.00 | $100.00 | $120.00 | $250.00 | $124.00 | $240.00 | $88.00 |
| 30 | Remove STR (rail) (496-7017) | LF | 76 | $65.00 | $50.00 | $26.00 | $16.00 | $47.40 | $44.00 | |
| 31 | Mobilization (500-7001) | LS | 1 | $118,000 | $135,000 | $100,000 | $135,000 | $142,209 | $142,000 | $25,000 |
| 32 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $6,000.00 | $4,500.00 | $1.00 | $6,600.00 | $6,217.00 | $9,000.00 | $1.00 |
| 33 | Portable changeable message sign (503-7001) | DAY | 93 | $95.00 | $135.00 | $1.00 | $1.00 | $112.00 | $116.00 | $165.00 |
| 34 | TMA (stationary) (505-7001) | DAY | 124 | $230.00 | $300.00 | $1.00 | $1.00 | $403.00 | $350.00 | $220.00 |
| 35 | Temporary sediment control fence (install) (506-7039) | LF | 3,050 | $4.00 | $5.00 | $15.00 | $3.50 | $4.00 | $4.00 | $2.00 |
| 36 | Temporary sediment control fence (remove) (506-7041) | LF | 3,050 | $1.00 | $2.00 | $1.00 | $1.25 | $1.00 | $1.40 | $1.00 |
| 37 | One-way traffic control (port traffic signal) (510-7003) | MO | 1 | $7,000.00 | $9,000.00 | $1.00 | $12,500 | $10,437 | $10,000 | $22,000 |
| 38 | Metal W-beam guard fence (steel post) (540-7002) | LF | 1,690 | $33.00 | $33.00 | $44.00 | $28.00 | $37.00 | $32.10 | $39.00 |
| 39 | Metal thrie-beam guard fence (steel post) (540-7020) | EACH | 8 | $2,500.00 | $2,700.00 | $1,000.00 | $2,715.00 | $3,508.00 | $2,900.00 | $4,400.00 |
| 40 | Remove metal beam guard fence (542-7001) | LF | 1,950 | $3.00 | $4.00 | $14.00 | $8.00 | $3.00 | $2.30 | $5.00 |
| 41 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,300.00 | $4,000.00 | $2,500.00 | $2,950.00 | $3,621.00 | $3,784.00 | $4,400.00 |
| 42 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 48 | $32.00 | $35.00 | $30.00 | $45.00 | $34.00 | $36.00 | $55.00 |
| 43 | Remove delin & object marker assms (658-7078) | EACH | 8 | $26.00 | $45.00 | $40.00 | $25.00 | $18.00 | $100.00 | $55.00 |
| 44 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 40 | $10.00 | $65.00 | $10.00 | $50.00 | $55.00 | $30.00 | $11.00 |
| 45 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 7,749 | $1.00 | $1.00 | $2.00 | $0.50 | $1.00 | $1.03 | $2.00 |
| 46 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 5,166 | $1.10 | $1.00 | $2.00 | $0.50 | $1.00 | $1.03 | $2.00 |
| 47 | Eliminating existing PM & markers (6") (677-7002) | LF | 5,766 | $1.15 | $1.50 | $3.00 | $1.00 | $2.00 | $1.15 | $2.00 |
| 48 | Driftwood removal (735-7060) | CY | 9 | $500.00 | $200.00 | $260.00 | $187.00 | $265.00 | $550.00 | |
| 49 | Concrete rail repair (in-kind) (778-7001) | LF | 15 | $500.00 | $390.00 | $400.00 | $361.00 | $220.00 | $1,100.00 | |
| 50 | CNC crack repair (discrete)(surface seal) (780-7004) | LF | 40 | $55.00 | $50.00 | $35.00 | $65.00 | $36.00 | $60.00 | $132.00 |
| 51 | Concrete beam repair (CFRP) (788-7002) | EACH | 1 | $11,000 | $5,000.00 | $15,000 | $22,818 | $20,400 | $22,000 | |
| 52 | Steel bridge zone painting ref STR #1 (4010-7002) | EACH | 1 | $48,000 | $60,000 | $40,000 | $45,000 | $21,831 | $48,000 | $55,000 |
| 53 | Steel bridge zone painting ref STR #2 (4010-7003) | EACH | 1 | $60,000 | $50,000 | $45,000 | $21,831 | $48,000 | $55,000 | |
| 54 | Preformed in-lane (trans) rumble strip (6024-7001) | LF | 320 | $20.00 | $20.00 | $30.00 | $16.00 | $22.00 | $50.00 | $22.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.