TxDOT contract A00209567 bid tabulation

Preventive Maintenance, IH 69C (Business 281 to FM 2812). Let by Texas DOT on May 1, 2025, Hidalgo, Pharr District. 4 bids received; low bid $6,414,834 by Foremost Paving, Inc., -18% against the engineer's estimate of $7,870,655.

Owner
Texas DOT
Letting
01 MAY 2025
Pay items
58
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Foremost Paving, Inc.$6,414,834Low-18%
2Ioc Company LLC$6,452,440+1.0%-18%
3Pulice Construction, Inc.$7,458,225+16%-5.0%
4Earthworks Enterprise$8,662,912+35%+10%
TxDOT contract A00209567: bids by rank

Engineer's estimate: $7,870,655.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Foremost Paving, Inc.2. Ioc Company LLC3. Pulice Construction, Inc.4. Earthworks Enterprise
1Removing concrete (mowstrip) (104-7005)LF100$15.00$36.78$62.48$17.43$21.50
2SP mixes SP-D sac-A PG76-22 (344-7064)TON12,956$114.75$108.05$105.09$132.00
3Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009)TON27,873$140.00$129.05$123.85$135.65$169.00
4Flexible pavement structure repair(12") (351-7011)SY6,933$23.96$30.00$41.20$31.00
5Planing asphalt concrete pavement(2") (354-7051)SY358,137$2.50$1.33$1.50$1.61$2.50
6Riprap (mow strip)(4 in) (432-7013)CY104$500.00$377.78$973.57$401.16$393.25
7Mobilization (500-7001)LS1$350,000$100,000$240,000$743,927$250,000
8Barricades, signs and traffic handling (502-7001)MO6$5,000.00$6,750.00$2,000.00$11,439$2,882.00
9TMA (stationary) (505-7001)DAY120$100.00$116.38$1.00$327.78$394.00
10TMA (mobile operation) (505-7003)DAY120$150.00$0.01$0.10$144.68$281.00
11Biodegradable erosion control logs (install) (12") (506-7044)LF1,130$7.00$5.53$4.79$11.18$6.00
12Biodegradable erosion control logs (remove) (506-7046)LF1,130$1.00$1.51$1.36$2.54$1.00
13Metal W-beam guard fence (timber post) (540-7001)LF925$30.00$26.44$27.18$28.66$44.00
14Metal beam guard fence trans (thrie-beam) (540-7005)EACH7$2,250.00$2,175.83$2,120.00$2,359.59$3,258.00
15Downstream anchor terminal section (540-7015)EACH2$1,500.00$1,226.10$1,635.00$1,329.65$3,258.00
16Connector plate for thrie beam (540-7030)EACH3$1,300.00$1,125.60$1,103.00$1,220.67$3,258.00
17Remove metal beam guard fence (542-7001)LF886$3.00$3.02$3.75$3.27$10.25
18Remove terminal anchor section (542-7002)EACH3$250.00$221.10$325.00$239.78$1,012.00
19Remove downstream anchor terminal (542-7003)EACH1$250.00$231.15$325.00$250.68$1,012.00
20RM metal beam guard fence trans (thrie-beam) (542-7004)EACH4$350.00$261.30$325.00$283.37$1,012.00
21Guardrail end treatment (install) (544-7001)EACH8$3,400.00$2,989.88$3,454.00$3,242.39$5,505.00
22Guardrail end treatment (remove) (544-7003)EACH6$250.00$331.65$325.00$359.66$1,012.00
23Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH28$35.00$28.65$100.17$31.06$57.00
24Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH6,456$1.00$1.11$1.25$2.26$0.75
25Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH3,733$1.11$1.33$2.28$0.75
26Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF38$1.11$1.10$1.12$4.50
27Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF11,090$1.25$0.89$0.88$0.89$1.50
28Reflectorized pavement marking type I (W)12"(lane drop)(100MIL) (666-7027)LF1,420$4.00$1.11$1.10$1.12$5.25
29Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF2,227$4.00$1.11$1.10$1.12$5.25
30Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF8,248$3.52$3.50$3.56$4.50
31Reflectorized pavement marking type II (W) 6" (broken) (666-7172)LF8,525$0.35$0.39$0.38$0.39$0.75
32Reflectorized pavement marking type II (W) 8" (solid) (666-7179)LF2,526$0.60$0.49$0.48$0.49$1.00
33Reflectorized pavement marking type II (W) 12" (lane drop) (666-7181)LF355$2.00$1.11$1.10$1.12$2.75
34Reflectorized pavement marking type II (Y) 6" (broken) (666-7211)LF2,483$0.39$0.38$0.39$0.75
35Reflectorized pavement marking type II (Y) 6" (solid) (666-7213)LF9,341$0.39$0.38$0.39$0.75
36Reflectorized pavement marking type III (W)(6")(solid) (666-7236)LF627$2.50$6.54$6.50$6.61$4.50
37Reflectorized pavement marking type III (W)(6")(broken) (666-7237)LF157$3.00$6.54$6.50$6.61$4.75
38Reflectorized pavement marking type III (Y)(6")(solid) (666-7248)LF627$2.50$6.54$6.50$6.61$4.25
39Reflectorized pavement marking type III (Y)(6")(broken) (666-7249)LF40$6.54$6.50$6.61$4.75
40Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF19,081$0.65$0.75$0.74$0.75$1.00
41Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF75,126$0.65$0.63$0.62$0.63$1.00
42Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF5,517$0.79$0.78$0.79$1.00
43Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF72,363$0.65$0.63$0.62$0.63$1.00
44Prefabricated PM type B (W)(6")(broken)contrast (668-7012)LF157$8.81$20.10$20.00$20.33$11.00
45Prefabricated PM type C (W)(arrow) (668-7091)EACH57$135.68$135.00$137.26$264.00
46Prefabricated PM type C (W)(double arrow) (668-7093)EACH4$326.63$325.00$330.44$517.00
47Prefabricated PM type C (W)(number) (668-7102)EACH4$250.00$95.48$95.00$96.59$236.00
48Prefabricated PM type C (W)(word) (668-7103)EACH47$226.13$225.00$228.76$264.00
49Prefabricated PM type C (W)(RR crossing) (668-7108)EACH2$653.25$650.00$660.88$764.00
50Prefabricated PM type C (W)(bike arrow) (668-7113)EACH30$90.45$90.00$91.51$147.00
51Prefabricated PM type C (W)(bike symbol) (668-7115)EACH30$180.90$180.00$183.01$209.00
52Reflectorized pavement marker type I-C (672-7002)EACH599$7.54$7.50$7.63$5.00
53Reflectorized pavement marker type II-A-A (672-7004)EACH1,395$7.54$7.50$7.63$4.50
54Reflectorized pavement marker type II-C-R (672-7006)EACH1,263$3.00$7.54$7.50$7.63$4.50
55Eliminating existing PM & markers (4") (677-7001)LF1,451$0.65$0.26$0.25$0.25$1.25
56Eliminating existing PM & markers (24") (677-7008)LF3,589$2.01$2.00$2.03$2.50
57Vehicle LP detect (sawcut) (688-7004)LF6,139$13.07$13.00$13.22$18.00
58Bonding course (3007-7001)GAL25,071$4.50$3.05$3.00$3.91$5.00
TxDOT contract A00209567: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of May 1, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way