TxDOT contract A00210146 bid tabulation
Bridge Maintenance, Various (DISTRICT WIDE to .). Let by Texas DOT on January 7, 2025, Potter, Amarillo District. 3 bids received; low bid $1,182,257 by Ti-Zack Concrete, LLC, -3.5% against the engineer's estimate of $1,224,932.
- Owner
- Texas DOT
- Letting
- 07 JAN 2025
- Pay items
- 41
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ti-Zack Concrete, LLC | $1,182,257 | Low | -3.0% |
| 2 | Icos Management, LLC | $1,509,844 | +28% | +23% |
| 3 | Built Right Construction of Oklahoma, LLC | $1,644,985 | +39% | +34% |
Engineer's estimate: $1,224,932.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ti-Zack Concrete, LLC | 2. Icos Management, LLC | 3. Built Right Construction of Oklahoma, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 3 | $1,500.00 | $968.00 | $500.00 | $1,000.00 |
| 2 | Removing concrete (wingwall) (104-7028) | CY | 4 | $1,500.00 | $1,210.00 | $1,800.00 | $1,000.00 |
| 3 | Embankment (final)(OC)(type B) (132-7003) | CY | 60 | $90.00 | $66.55 | $150.00 | $100.00 |
| 4 | Flowable backfill (401-7001) | CY | 7 | $400.00 | $665.50 | $800.00 | $500.00 |
| 5 | Class B concrete (flume) (420-7010) | CY | 90 | $900.00 | $423.50 | $800.00 | $1,500.00 |
| 6 | Class C concrete (pile encasement) (420-7060) | CY | 16 | $2,000.00 | $968.00 | $4,000.00 | $3,000.00 |
| 7 | Epoxy waterproof finish (type X) (427-7005) | SF | 2,220 | $17.00 | $18.15 | $30.00 | $50.00 |
| 8 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 999 | $225.00 | $151.25 | $200.00 | $350.00 |
| 9 | Riprap (concrete)(5 in) (432-7002) | CY | 2 | $1,250.00 | $786.50 | $2,000.00 | $1,200.00 |
| 10 | Cleaning existing joints (438-7008) | LF | 48 | $35.00 | $151.25 | $90.00 | $75.00 |
| 11 | Multi-layer polymer overlay (439-7014) | SY | 779 | $68.00 | $90.75 | $110.00 | $100.00 |
| 12 | Header type expansion joint (454-7009) | CF | 2 | $500.00 | $1,210.00 | $2,500.00 | $1,000.00 |
| 13 | Shot blasting (483-7016) | SY | 779 | $10.00 | $18.15 | $24.00 | $12.00 |
| 14 | Remove STR (rail) (496-7017) | LF | 48 | $40.00 | $302.50 | $300.00 | $250.00 |
| 15 | Mobilization (500-7001) | LS | 1 | $100,000 | $102,850 | $150,000 | $150,000 |
| 16 | Barricades, signs and traffic handling (502-7004) | EACH | 5 | $17,000 | $6,050.00 | $6,000.00 | $4,000.00 |
| 17 | Portable changeable message sign (503-7002) | EACH | 2 | $15,000 | $6,050.00 | $6,000.00 | $10,000 |
| 18 | TMA (stationary) (505-7001) | DAY | 88 | $300.00 | $302.50 | $1.00 | $350.00 |
| 19 | TMA (mobile operation) (505-7002) | HR | 40 | $150.00 | $121.00 | $1.00 | $350.00 |
| 20 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 1,527 | $144.00 | $151.25 | $170.00 | $200.00 |
| 21 | Permanent CTB (single slope)(42)(mod) (514-7004) | LF | 60 | $300.00 | $242.00 | $140.00 | $200.00 |
| 22 | Permanent CTB (single slope) (mod) (514-7035) | LF | 220 | $200.00 | $181.50 | $360.00 | $200.00 |
| 23 | Permanent CTB (tran SSCB to parapet) (514-7040) | LF | 98 | $275.00 | $181.50 | $450.00 | $200.00 |
| 24 | Permanent CTB (tran SSCB to T501)(mod) (514-7042) | LF | 36 | $275.00 | $242.00 | $700.00 | $200.00 |
| 25 | Metal W-beam guard fence (steel post) (540-7002) | LF | 340 | $40.00 | $102.85 | $85.00 | $35.00 |
| 26 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 6 | $3,130.00 | $7,260.00 | $3,450.00 | $3,000.00 |
| 27 | Remove metal beam guard fence (542-7001) | LF | 2,046 | $4.00 | $10.89 | $10.00 | $7.00 |
| 28 | Remove terminal anchor section (542-7002) | EACH | 6 | $300.00 | $1,210.00 | $3,500.00 | $500.00 |
| 29 | Remove downstream anchor terminal (542-7003) | EACH | 2 | $430.00 | $1,815.00 | $1,500.00 | $1,000.00 |
| 30 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 5 | $225.00 | $1,815.00 | $750.00 | $1,500.00 |
| 31 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $3,628.00 | $8,470.00 | $6,000.00 | $4,500.00 |
| 32 | Guardrail end treatment (remove) (544-7003) | EACH | 1 | $350.00 | $6,050.00 | $3,500.00 | $2,000.00 |
| 33 | Crash cushion attenuator (remove) (545-7004) | EACH | 1 | $1,650.00 | $4,840.00 | $6,500.00 | $2,000.00 |
| 34 | Crash cushion attenuator (install)(L)(W)(TL3) (545-7008) | EACH | 1 | $36,000 | $12,100 | $42,000 | $75,000 |
| 35 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 18 | $40.00 | $60.50 | $300.00 | $65.00 |
| 36 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 330 | $2.00 | $6.05 | $20.00 | $10.00 |
| 37 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 330 | $2.00 | $6.05 | $20.00 | $10.00 |
| 38 | Crack cleaning and sealing (JCP) (713-7004) | LF | 37 | $20.00 | $268.62 | $50.00 | $65.00 |
| 39 | Carbon fiber reinforced polymer protection (786-7001) | SF | 294 | $130.00 | $134.31 | $140.00 | $135.00 |
| 40 | Concrete beam repair (788-7001) | EACH | 6 | $5,600.00 | $8,470.00 | $12,000 | $5,000.00 |
| 41 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 12 | $1,500.00 | $1,815.00 | $2,000.00 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.