TxDOT contract A00211554 bid tabulation
Landscape Development, Various (VARIOUS LOCATIONS ALONG to US 79). Let by Texas DOT on September 5, 2025, Rusk, Tyler District. 7 bids received; low bid $119,461 by GV Landscape and Construction LLC, -16% against the engineer's estimate of $142,213.
- Owner
- Texas DOT
- Letting
- 05 SEP 2025
- Pay items
- 16
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | GV Landscape and Construction LLC | $119,461 | Low | -16% |
| 2 | Tight Line Construction, LLC | $136,485 | +14% | -4.0% |
| 3 | Rare Earth Landscape Solutions LLC | $143,023 | +20% | +1.0% |
| 4 | Texas Road Construction, LLC | $160,808 | +35% | +13% |
| 5 | Central North Construction, LLC | $187,428 | +57% | +32% |
| 6 | G & L Construction, Inc. | $214,781 | +80% | +51% |
| 7 | Cross Plus Construction, LLC | $256,618 | +115% | +80% |
Engineer's estimate: $142,213.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. GV Landscape and Construction LLC | 2. Tight Line Construction, LLC | 3. Rare Earth Landscape Solutions LLC | 4. Texas Road Construction, LLC | 5. Central North Construction, LLC | 6. G & L Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (curb) (104-7016) | LF | 62 | $25.00 | $25.00 | $50.00 | $50.00 | $50.00 | $125.00 | $40.00 |
| 2 | Removing concrete (miscellaneous) (104-7046) | SY | 9 | $50.00 | $60.00 | $125.00 | $50.00 | $250.00 | $252.00 | $30.00 |
| 3 | Irrigation system (170-7001) | LS | 1 | $10,000 | $35,000 | $35,000 | $4,000.00 | $22,000 | $25,000 | $16,000 |
| 4 | Plant bed preparation (192-7009) | SY | 253 | $3.00 | $3.00 | $15.00 | $71.00 | $36.00 | $10.00 | $50.00 |
| 5 | Landscape edge (type I) (192-7017) | LF | 418 | $88.00 | $3.00 | $60.00 | $85.00 | $40.00 | $65.00 | $27.00 |
| 6 | Loose aggregate GRND cover (192-7022) | SY | 110 | $40.00 | $30.00 | $40.00 | $27.00 | $25.00 | $85.00 | $17.00 |
| 7 | Plant material (3 gal) (192-7028) | EACH | 326 | $30.00 | $28.00 | $30.00 | $28.00 | $35.00 | $75.00 | $20.00 |
| 8 | Plant material (5 gal) (192-7029) | EACH | 15 | $35.00 | $33.00 | $45.00 | $50.00 | $65.00 | $125.00 | $25.00 |
| 9 | Irrig sys oper and maintenance (193-7007) | MO | 3 | $5,000.00 | $1,500.00 | $1,000.00 | $2,500.00 | $1,000.00 | $5,500.00 | $5,000.00 |
| 10 | Mobilization (500-7001) | LS | 1 | $16,000 | $30,000 | $15,000 | $14,365 | $25,000 | $8,500.00 | $6,000.00 |
| 11 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $3,000.00 | $2,000.00 | $3,000.00 | $5,465.00 | $3,500.00 | $3,250.00 | $9,000.00 |
| 12 | TMA (stationary) (505-7001) | DAY | 65 | $200.00 | $150.00 | $1.00 | $1.00 | $300.00 | $250.00 | $500.00 |
| 13 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 200 | $5.00 | $3.00 | $10.00 | $1.00 | $5.00 | $10.00 | $25.00 |
| 14 | Biodegradable erosion control logs (remove) (506-7046) | LF | 200 | $2.00 | $1.00 | $2.00 | $1.00 | $5.00 | $1.00 | $15.00 |
| 15 | Concrete curb (type II) (529-7002) | LF | 459 | $35.00 | $15.00 | $35.00 | $38.00 | $55.00 | $65.00 | $120.00 |
| 16 | Driveways (ACP) (530-7010) | SY | 50 | $90.00 | $150.00 | $100.00 | $150.00 | $75.00 | $15.00 | $215.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.