TxDOT contract A00212001 bid tabulation
Bridge Maintenance, Various (Various Locations in Bastrop, Caldwell, to Hays, Lee and Travis Counties.). Let by Texas DOT on May 1, 2025, Travis, Austin District. 8 bids received; low bid $2,334,542 by Icos Management, LLC, -30% against the engineer's estimate of $3,325,546.
- Owner
- Texas DOT
- Letting
- 01 MAY 2025
- Pay items
- 46
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Icos Management, LLC | $2,334,542 | Low | -30% |
| 2 | SCR Civil Construction, LLC | $2,461,841 | +5.0% | -26% |
| 3 | Premier Contractors LLC | $2,499,331 | +7.0% | -25% |
| 4 | Structural Integrity Group LLC | $2,594,478 | +11% | -22% |
| 5 | Pathfield Investments LLC | $2,736,830 | +17% | -18% |
| 6 | Roy Jorgensen Associates, Inc. | $3,446,875 | +48% | +4.0% |
| 7 | Built Right Construction of Oklahoma, LLC | $3,579,680 | +53% | +8.0% |
| 8 | Grey Sky Construction LLC | $4,316,235 | +85% | +30% |
Engineer's estimate: $3,325,546.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Icos Management, LLC | 2. SCR Civil Construction, LLC | 3. Premier Contractors LLC | 4. Structural Integrity Group LLC | 5. Pathfield Investments LLC | 6. Roy Jorgensen Associates, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 12 | $3,500.00 | $3,850.00 | $700.00 | $100.00 | $1,300.00 | $100.00 | $2,000.00 |
| 2 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 12 | $3,500.00 | $4,400.00 | $1,200.00 | $300.00 | $1,400.00 | $500.00 | $2,500.00 |
| 3 | Removing concrete (riprap) (104-7007) | CY | 25 | $300.00 | $140.00 | $130.00 | $200.00 | $580.00 | $140.00 | $500.00 |
| 4 | Flexible pavement structure repair(2") (351-7001) | SY | 1 | $250.00 | $1,100.00 | $2,000.00 | $40.00 | $1,785.00 | $1,200.00 | $6,500.00 |
| 5 | Flexible pavement structure repair(10") (351-7009) | SY | 20 | $766.00 | $550.00 | $1,000.00 | $120.00 | $625.00 | $2,200.00 | $2,250.00 |
| 6 | Cem stabil BKFL (400-7010) | CY | 92 | $1,700.00 | $440.00 | $750.00 | $300.00 | $434.00 | $550.00 | $180.00 |
| 7 | Flowable backfill (401-7001) | CY | 66 | $1,700.00 | $550.00 | $750.00 | $350.00 | $1,180.00 | $600.00 | $500.00 |
| 8 | Class C concrete (collar) (420-7061) | EACH | 14 | $1,000.00 | $4,400.00 | $3,250.00 | $2,500.00 | $5,300.00 | $2,500.00 | $12,500 |
| 9 | Concrete paint finish (427-7002) | SF | 950 | $0.60 | $22.00 | $12.00 | $5.00 | $8.00 | $75.00 | $10.00 |
| 10 | Penetrating concrete surface treatment (428-7001) | SY | 1,920 | $10.00 | $28.00 | $26.00 | $30.00 | $25.00 | $35.00 | $20.00 |
| 11 | Concrete structure repair(clean & coat WTH epoxy) (429-7001) | SF | 1,000 | $260.00 | $132.00 | $50.00 | $310.00 | $100.00 | $60.00 | $200.00 |
| 12 | Concrete structure repair (epoxy mortar) (429-7002) | SF | 55 | $350.00 | $220.00 | $295.00 | $350.00 | $171.00 | $300.00 | $275.00 |
| 13 | Concrete structure repair(rapid deck rep(PRT DPT) (429-7004) | SF | 30 | $250.00 | $440.00 | $350.00 | $200.00 | $232.00 | $280.00 | $180.00 |
| 14 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 100 | $250.00 | $550.00 | $450.00 | $300.00 | $350.00 | $320.00 | $250.00 |
| 15 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 2,521 | $285.00 | $200.00 | $175.00 | $300.00 | $148.00 | $220.00 | $300.00 |
| 16 | Concrete structure repair (standard) (429-7009) | SF | 63 | $300.00 | $165.00 | $200.00 | $200.00 | $140.00 | $120.00 | $200.00 |
| 17 | Riprap (concrete)(CL B)(5 in) (432-7008) | CY | 25 | $1,850.00 | $550.00 | $1,344.00 | $1,200.00 | $940.00 | $1,200.00 | $900.00 |
| 18 | Riprap (stone type F)(dry)(18 in) (432-7018) | CY | 15 | $350.00 | $220.00 | $330.00 | $300.00 | $336.00 | $380.00 | $250.00 |
| 19 | Riprap (stone protection)(18 in) (432-7043) | CY | 1,410 | $250.00 | $200.00 | $260.00 | $250.00 | $286.00 | $310.00 | $325.00 |
| 20 | Riprap (stone protection)(24 in) (432-7045) | CY | 1,077 | $320.00 | $200.00 | $210.00 | $255.00 | $295.00 | $370.00 | $275.00 |
| 21 | Bedding material (6 in) (432-7050) | CY | 25 | $440.00 | $550.00 | $200.00 | $420.00 | $345.00 | $200.00 | $180.00 |
| 22 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 496 | $80.00 | $55.00 | $56.00 | $65.00 | $40.00 | $65.00 | $35.00 |
| 23 | Cleaning and sealing joints (foam) (438-7010) | LF | 60 | $100.00 | $110.00 | $215.00 | $420.00 | $60.00 | $60.00 | $200.00 |
| 24 | Raising existing struct (495-7002) | EACH | 2 | $8,000.00 | $44,000 | $27,000 | $25,000 | $30,200 | $25,000 | $75,000 |
| 25 | Mobilization (500-7001) | LS | 1 | $252,583 | $265,000 | $246,100 | $240,000 | $305,000 | $270,000 | $340,000 |
| 26 | Barricades, signs and traffic handling (502-7001) | MO | 14 | $20,000 | $200.00 | $14,700 | $1.00 | $21,000 | $5,000.00 | $12,500 |
| 27 | Portable changeable message sign (503-7001) | DAY | 12 | $187.62 | $100.00 | $300.00 | $1.00 | $820.00 | $200.00 | $500.00 |
| 28 | TMA (stationary) (505-7001) | DAY | 260 | $473.03 | $100.00 | $225.00 | $1.00 | $1.00 | $1.00 | $750.00 |
| 29 | TMA (mobile operation) (505-7003) | DAY | 100 | $473.33 | $100.00 | $700.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 30 | Sandbags for erosion control (506-7035) | EACH | 120 | $40.00 | $1.00 | $14.00 | $10.00 | $5.00 | $10.00 | $25.00 |
| 31 | Temporary SDMT cont fence (inlet protection) (506-7040) | LF | 900 | $10.00 | $2.00 | $8.00 | $3.00 | $2.00 | $25.00 | $10.00 |
| 32 | Temporary sediment control fence (remove) (506-7041) | LF | 900 | $10.00 | $1.00 | $2.30 | $3.00 | $1.00 | $10.00 | $1.00 |
| 33 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 120 | $28.34 | $5.00 | $14.00 | $7.00 | $2.00 | $30.00 | $15.00 |
| 34 | Biodegradable erosion control logs (remove) (506-7046) | LF | 120 | $50.00 | $1.00 | $2.30 | $5.00 | $1.00 | $10.00 | $2.50 |
| 35 | Concrete sidewalks (4") (531-7001) | SY | 10 | $170.00 | $550.00 | $1,030.00 | $400.00 | $100.00 | $1,500.00 | $420.00 |
| 36 | Guardrail end treatment (move & reset) (544-7002) | EACH | 2 | $250.00 | $4,400.00 | $600.00 | $1,200.00 | $6,750.00 | $12,000 | $2,000.00 |
| 37 | Driftwood removal (735-7060) | CY | 105 | $750.00 | $165.00 | $180.00 | $1.00 | $320.00 | $120.00 | $160.00 |
| 38 | Repair (steel pedestrian rail) (776-7003) | LF | 100 | $100.00 | $330.00 | $91.00 | $75.00 | $760.00 | $450.00 | $275.00 |
| 39 | Concrete rail repair (miscellaneous) (778-7002) | LF | 4 | $320.00 | $1,100.00 | $2,201.00 | $400.00 | $851.00 | $2,500.00 | $1,500.00 |
| 40 | CNC crack repair (discrete)(inject) (780-7002) | LF | 80 | $200.00 | $110.00 | $156.00 | $150.00 | $96.00 | $105.00 | $225.00 |
| 41 | Bridge joint repair (header) (785-7002) | LF | 80 | $340.00 | $440.00 | $240.00 | $400.00 | $234.00 | $350.00 | $275.00 |
| 42 | Bridge joint replacement (armor) (785-7010) | LF | 140 | $400.00 | $550.00 | $788.00 | $250.00 | $595.00 | $450.00 | $825.00 |
| 43 | Carbon fiber reinforced polymer protection (786-7001) | SF | 286 | $150.00 | $200.00 | $136.00 | $120.00 | $106.00 | $380.00 | $250.00 |
| 44 | Concrete beam repair (788-7001) | EACH | 2 | $20,000 | $11,000 | $8,900.00 | $16,000 | $9,100.00 | $25,000 | $12,500 |
| 45 | Bridge deck cleaning (7001-7001) | SY | 771 | $15.00 | $22.00 | $39.00 | $15.00 | $9.25 | $30.00 | $5.00 |
| 46 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 4 | $5,600.00 | $8,800.00 | $2,000.00 | $1,100.00 | $1,175.00 | $2,000.00 | $8,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 1, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.