TxDOT contract A00212752 bid tabulation
Landscape Development, GREENLEE DR (At Tippit Middle School to .). Let by Texas DOT on July 1, 2025, Williamson, Austin District. 5 bids received; low bid $1,125,475 by Rare Earth Landscape Solutions LLC, -27% against the engineer's estimate of $1,536,457.
- Owner
- Texas DOT
- Letting
- 01 JUL 2025
- Pay items
- 35
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Rare Earth Landscape Solutions LLC | $1,125,475 | Low | -27% |
| 2 | Encino Landscape, Inc. | $1,404,435 | +25% | -9.0% |
| 3 | Apex Landscape & Irrigation, LLC | $1,436,029 | +28% | -7.0% |
| 4 | C. E. Barker, LTD. | $2,361,826 | +110% | +54% |
| 5 | Abescape Landscaping, LLC | $3,210,082 | +185% | +109% |
Engineer's estimate: $1,536,457.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Rare Earth Landscape Solutions LLC | 2. Encino Landscape, Inc. | 3. Apex Landscape & Irrigation, LLC | 4. C. E. Barker, LTD. | 5. Abescape Landscaping, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Tree protection (install) (100-7014) | LF | 5,200 | $15.00 | $12.00 | $10.00 | $1.25 | $44.19 | $200.00 |
| 2 | Tree protection (remove) (100-7016) | LF | 5,200 | $10.00 | $1.40 | $1.00 | $1.00 | $3.67 | $20.00 |
| 3 | Excavation (special) (110-7003) | CY | 58 | $200.00 | $45.00 | $50.00 | $70.00 | $61.02 | $50.00 |
| 4 | Embankment (vehicle)(OC)(type A) (132-7013) | CY | 58 | $100.00 | $86.50 | $50.00 | $75.00 | $97.84 | $75.00 |
| 5 | Embankment (vehicle)(OC)(type B) (132-7015) | CY | 522 | $110.00 | $55.00 | $60.00 | $60.00 | $97.84 | $65.00 |
| 6 | Embankment (org)(OC)(type D) (132-7027) | CY | 58 | $50.00 | $45.00 | $60.00 | $75.00 | $97.84 | $70.00 |
| 7 | Furn & place topsoil (vehicle) (160-7007) | CY | 691.50 | $50.00 | $55.00 | $60.00 | $40.00 | $119.94 | $50.00 |
| 8 | Drill seed (permanent_urban_clay) (164-7012) | SY | 21,533 | $0.75 | $1.00 | $1.00 | $1.00 | $1.26 | $0.50 |
| 9 | Vegetative watering (168-7001) | TGL | 98 | $100.00 | $135.00 | $100.00 | $2.00 | $239.88 | $100.00 |
| 10 | Irrigation system (170-7001) | LS | 1 | $200,000 | $68,000 | $220,000 | $337,500 | $254,709 | $280,000 |
| 11 | Mulch (192-7001) | CY | 251 | $75.00 | $90.00 | $60.00 | $50.00 | $58.92 | $2.10 |
| 12 | Plant soil mix (192-7003) | CY | 113 | $250.00 | $95.50 | $100.00 | $90.00 | $153.60 | $95.00 |
| 13 | Plant soil mix (planting soil) (192-7004) | CY | 832 | $200.00 | $66.50 | $60.00 | $90.00 | $122.04 | $90.00 |
| 14 | Plant bed preparation (192-7009) | SY | 3,015 | $5.00 | $5.00 | $3.00 | $4.00 | $97.21 | $3.50 |
| 15 | Landscape edge (type I) (192-7017) | LF | 582.70 | $25.00 | $27.00 | $30.00 | $25.00 | $18.94 | $55.00 |
| 16 | Landscape edge (type II) (192-7018) | LF | 1,108.70 | $30.00 | $18.00 | $40.00 | $22.50 | $31.56 | $55.00 |
| 17 | Plant material (1 gal) (192-7026) | EACH | 17,902 | $10.50 | $7.75 | $15.00 | $10.75 | $21.46 | $12.00 |
| 18 | Plant material (5 gal) (192-7029) | EACH | 52 | $40.00 | $30.00 | $40.00 | $40.00 | $63.13 | $50.00 |
| 19 | Landscape establish (193-7001) | MO | 24 | $3,000.00 | $3,250.00 | $2,000.00 | $3,000.00 | $7,259.38 | $2,000.00 |
| 20 | Irrig sys oper and maintenance (193-7007) | MO | 24 | $1,500.00 | $3,500.00 | $1,000.00 | $2,000.00 | $7,259.38 | $1,500.00 |
| 21 | Rdside amenity (gate) (194-7009) | EACH | 1 | $60,000 | $50,000 | $20,000 | $102,500 | $50,500 | $2,000.00 |
| 22 | Rdside amenity (removing & reset) (194-7020) | EACH | 40 | $200.00 | $90.00 | $500.00 | $150.00 | $220.94 | $5,500.00 |
| 23 | Retaining wall (stone) (423-7014) | SF | 130.50 | $200.00 | $95.00 | $75.00 | $90.00 | $40.07 | $155.00 |
| 24 | Retaining wall (special) (423-7029) | SF | 857.50 | $75.00 | $20.00 | $80.00 | $90.00 | $43.14 | $145.00 |
| 25 | Mobilization (500-7001) | LS | 1 | $153,300 | $104,580 | $225,000 | $133,000 | $235,000 | $232,500 |
| 26 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $3,500.00 | $8,070.00 | $3,000.00 | $8,500.00 | $1,893.75 | $75,000 |
| 27 | TMA (stationary) (505-7001) | DAY | 20 | $350.00 | $1.00 | $300.00 | $1.00 | $252.50 | $2,500.00 |
| 28 | Construction perimeter fence (506-7034) | LF | 1,528 | $15.00 | $5.00 | $20.00 | $35.00 | $6.31 | $5.00 |
| 29 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 300 | $10.00 | $6.50 | $10.00 | $1.00 | $10.10 | $10.00 |
| 30 | Biodegradable erosion control logs (remove) (506-7046) | LF | 300 | $4.00 | $2.00 | $1.00 | $1.00 | $3.79 | $5.00 |
| 31 | Concrete sidewalks (4") (531-7001) | SY | 1,158 | $100.00 | $155.00 | $100.00 | $80.00 | $64.52 | $125.00 |
| 32 | Curb ramps (type 2) (531-7006) | EACH | 1 | $4,000.00 | $3,500.00 | $2,000.00 | $3,000.00 | $4,513.44 | $3,500.00 |
| 33 | Chain link fence (install) (6') (550-7001) | LF | 100 | $55.00 | $65.00 | $40.00 | $35.00 | $47.34 | $45.00 |
| 34 | Gate (install)(6'X4') (550-7012) | EACH | 1 | $1,650.00 | $1,500.00 | $2,000.00 | $2,700.00 | $1,104.69 | $600.00 |
| 35 | Steel fence (remove) (5007-7001) | LF | 100 | $35.00 | $50.00 | $20.00 | $8.00 | $0.44 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.