TxDOT contract A00214053 bid tabulation

CULVERT REPAIR, US0096 (WITHIN THE LUFKIN DISTRICT to WITHIN THE LUFKIN DISTRICT). Let by Texas DOT on September 17, 2025, San Augustine, Lufkin District. 7 bids received; low bid $617,373 by A R Brothers Construction Services, Inc., -20% against the engineer's estimate of $772,027.

Owner
Texas DOT
Letting
17 SEP 2025
Pay items
33
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1A R Brothers Construction Services, Inc.$617,373Low-20%
2Garret Shields Infrastructure$637,114+3.0%-17%
3Rhino Equity, LLC$645,679+5.0%-16%
4Aad Contracting Inc.$747,646+21%-3.0%
5Lakey, Inc.$753,379+22%-2.0%
6Icos Management, LLC$797,209+29%+3.0%
7Blacksmith Ventures LLC$836,733+36%+8.0%
TxDOT contract A00214053: bids by rank

Engineer's estimate: $772,027.

Bid tabulation

LinePay itemUnitQuantityEstimate1. A R Brothers Construction Services, Inc.2. Garret Shields Infrastructure3. Rhino Equity, LLC4. Aad Contracting Inc.5. Lakey, Inc.6. Icos Management, LLC
1Embankment (vehicle)(OC)(type C) (132-7017)CY454$50.00$27.00$30.00$35.00$55.00$35.00$58.00
2Spec excavation work (hyd excavator) (158-7002)HR50$100.00$50.00$80.00$80.00$100.00$125.00$225.00
3Block sodding (162-7002)SY1,616$10.00$10.25$10.00$7.00$8.00$9.85$10.00
4Broadcast seed (temporary_warm) (164-7005)SY1,616$1.00$0.17$0.50$1.50$1.50$1.00$1.00
5Broadcast seed (temporary_cool) (164-7006)SY1,616$1.00$0.17$0.50$1.50$1.50$1.00$2.00
6Vegetative watering (168-7001)TGL103$20.00$10.00$50.00$30.00$20.00$34.50$12.00
7Cut & restoring pavement (400-7006)SY124$300.00$160.00$200.00$120.00$200.00$200.00$200.00
8Cem stabil BKFL (400-7010)CY396$175.00$250.00$260.00$220.00$250.00$350.00$345.00
9Trench excavation protection (402-7001)LF250$50.00$10.00$1.00$30.00$33.00$10.00$30.00
10Class C concrete (collar) (420-7061)EACH9$2,000.00$500.00$1,000.00$1,300.00$1,500.00$1,155.00$2,450.00
11Riprap (stone common)(dry)(24 in) (432-7034)CY123$400.00$205.00$200.00$250.00$280.00$200.00$280.00
12RC pipe (CL III)(18 in) (464-7003)LF70$125.00$100.00$100.00$110.00$110.00$100.00$95.00
13RC pipe (CL III)(36 in) (464-7009)LF432$225.00$210.00$260.00$260.00$210.00$150.00$270.00
14RC pipe (CL III)(48 in) (464-7011)LF6$400.00$250.00$400.00$500.00$300.00$270.00$335.00
15Headwall (CH - FW - 0) (diameter= 36 in) (466-7009)EACH1$8,000.00$9,500.00$10,000$11,000$11,600$13,080$13,000
16Headwall (CH - FW - 0) (diameter= 48 in) (466-7011)EACH1$15,000$11,000$10,000$12,000$15,000$13,245$11,000
17Headwall (CH - FW - 0) (diameter= 72 in) (466-7015)EACH1$20,000$19,000$12,000$15,000$18,000$27,835$13,000
18Headwall (CH - PW - 0) (diameter= 54 in) (466-7108)EACH3$20,000$21,000$12,000$14,000$18,000$27,835$19,000
19Headwall (CH - PW - 0) (diameter= 72 in) (466-7111)EACH2$25,000$23,000$15,000$19,000$23,000$27,835$24,500
20Headwall (CH - PW - S) (diameter= 42 in) (466-7121)EACH1$15,000$11,200$10,000$14,000$16,000$21,888$18,000
21Headwall (CH - PW - S) (diameter= 54 in) (466-7123)EACH1$20,000$17,500$15,000$15,000$18,000$21,888$25,350
22Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306)EACH8$1,000.00$1,050.00$1,500.00$1,100.00$1,200.00$1,285.65$1,100.00
23Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366)EACH6$4,000.00$3,800.00$4,000.00$4,000.00$4,500.00$5,000.00$2,800.00
24Clean existing culverts (480-7001)EACH4$4,500.00$2,500.00$2,000.00$4,000.00$5,000.00$5,000.00$3,200.00
25Removing structure (headwall) (496-7006)EACH7$1,500.00$2,500.00$1,000.00$2,000.00$1,500.00$2,300.00$1,200.00
26Removing structure (pipe) (496-7037)EACH6$2,000.00$2,000.00$100.00$500.00$90.00$1,700.00$1,100.00
27Mobilization (500-7001)LS1$75,000$61,000$60,000$35,000$65,000$36,000$76,000
28Barricades, signs and traffic handling (502-7001)MO6$10,000$1,200.00$5,000.00$5,000.00$7,000.00$5,000.00$3,000.00
29TMA (stationary) (505-7001)DAY120$150.00$50.00$300.00$200.00$300.00$250.00$350.00
30Temporary sediment control fence (install) (506-7039)LF1,138$4.00$4.00$5.00$4.00$4.00$4.57$5.00
31Temporary sediment control fence (remove) (506-7041)LF1,138$1.25$1.15$1.00$1.50$1.00$1.25$1.50
32Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH27$50.00$118.00$30.00$130.00$100.00$107.50$38.00
33Driftwood removal (735-7061)LS1$7,500.00$3,050.00$5,000.00$20,000$20,000$5,000.00$2,500.00
TxDOT contract A00214053: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of September 17, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy