TxDOT contract A00214129 bid tabulation
BRIDGE PREVENTATIVE MAINTENANCE, IH0045 (Various to Various). Let by Texas DOT on July 9, 2025, Freestone, Bryan District. 6 bids received; low bid $405,447 by Cross Plus Construction, LLC, -10% against the engineer's estimate of $451,815.
- Owner
- Texas DOT
- Letting
- 09 JUL 2025
- Pay items
- 38
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cross Plus Construction, LLC | $405,447 | Low | -10% |
| 2 | BK Field Operations LLC | $427,172 | +5.0% | -5.0% |
| 3 | Road Doctors LLC | $427,445 | +5.0% | -5.0% |
| 4 | Rhino Equity, LLC | $459,840 | +13% | +2.0% |
| 5 | Pathfield Investments LLC | $471,021 | +16% | +4.0% |
| 6 | Built Right Construction of Oklahoma, LLC | $660,085 | +63% | +46% |
Engineer's estimate: $451,815.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Cross Plus Construction, LLC | 2. BK Field Operations LLC | 3. Road Doctors LLC | 4. Rhino Equity, LLC | 5. Pathfield Investments LLC | 6. Built Right Construction of Oklahoma, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 131 | $30.00 | $25.00 | $65.00 | $30.00 | $30.00 | $20.00 | $50.00 |
| 2 | Excavation (roadway & channel) (110-7004) | CY | 80 | $100.00 | $55.00 | $125.00 | $30.00 | $18.00 | $30.00 | $35.00 |
| 3 | Embankment (vehicle)(OC)(type A) (132-7013) | CY | 522 | $30.00 | $41.00 | $25.00 | $55.00 | $70.00 | $150.00 | $75.00 |
| 4 | FL BS (CMP in place)(tya GR1-2)(in vehicle) (247-7136) | CY | 210 | $55.00 | $42.00 | $140.00 | $150.00 | $100.00 | $60.00 | $100.00 |
| 5 | Cem stabil BKFL (400-7010) | CY | 89 | $250.00 | $325.00 | $300.00 | $200.00 | $200.00 | $280.00 | $750.00 |
| 6 | Flowable backfill (401-7001) | CY | 6.30 | $500.00 | $566.00 | $400.00 | $350.00 | $300.00 | $230.00 | $750.00 |
| 7 | Temporary special shoring (403-7001) | SF | 160 | $35.00 | $55.00 | $35.00 | $20.00 | $40.00 | $30.00 | $150.00 |
| 8 | Temporary special shoring (cofferdam) (403-7002) | SF | 399 | $35.00 | $45.00 | $50.00 | $20.00 | $70.00 | $30.00 | $150.00 |
| 9 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 116 | $240.00 | $200.00 | $140.00 | $130.00 | $180.00 | $180.00 | $350.00 |
| 10 | Concrete structure repair (standard) (429-7009) | SF | 14 | $300.00 | $200.00 | $150.00 | $150.00 | $150.00 | $95.00 | $400.00 |
| 11 | Riprap (concrete)(4 in) (432-7001) | CY | 25 | $800.00 | $855.00 | $575.00 | $400.00 | $700.00 | $650.00 | $850.00 |
| 12 | Riprap (concrete)(flume) (432-7012) | CY | 2.10 | $1,500.00 | $1,258.00 | $1,000.00 | $1,400.00 | $1,000.00 | $800.00 | $850.00 |
| 13 | Riprap (mow strip)(4 in) (432-7013) | CY | 29 | $550.00 | $900.00 | $525.00 | $400.00 | $800.00 | $600.00 | $850.00 |
| 14 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 110 | $300.00 | $250.00 | $175.00 | $200.00 | $220.00 | $180.00 | $400.00 |
| 15 | Bedding material (6 in) (432-7050) | CY | 56 | $180.00 | $125.00 | $140.00 | $200.00 | $100.00 | $250.00 | $200.00 |
| 16 | Concrete box culvert (10 FT X 6 FT)(extend) (462-7089) | LF | 15 | $1,800.00 | $1,500.00 | $2,400.00 | $1,400.00 | $1,000.00 | $1,500.00 | $5,000.00 |
| 17 | RC pipe (CL III)(24 in) (464-7005) | LF | 8 | $200.00 | $200.00 | $550.00 | $600.00 | $130.00 | $120.00 | $350.00 |
| 18 | Wingwall (FW - S) (HW=5 FT) (466-7161) | EACH | 0.50 | $12,500 | $12,000 | $15,000 | $36,000 | $10,000 | $17,000 | $7,500.00 |
| 19 | Wingwall (FW - S) (HW=9 FT) (466-7165) | EACH | 2 | $25,000 | $12,000 | $8,000.00 | $23,000 | $35,000 | $28,000 | $8,500.00 |
| 20 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 1 | $2,800.00 | $3,500.00 | $4,800.00 | $1,300.00 | $2,000.00 | $2,700.00 | $3,000.00 |
| 21 | Removing structure (set) (496-7004) | EACH | 1 | $800.00 | $1,000.00 | $2,200.00 | $300.00 | $500.00 | $1,000.00 | $500.00 |
| 22 | Removing structure (wingwall) (496-7005) | EACH | 2.50 | $2,000.00 | $500.00 | $1,000.00 | $2,000.00 | $5,000.00 | $1,800.00 | $1,500.00 |
| 23 | Removing structure (pipe) (496-7007) | LF | 12 | $50.00 | $25.00 | $175.00 | $50.00 | $50.00 | $25.00 | $50.00 |
| 24 | Mobilization (500-7001) | LS | 1 | $40,000 | $35,000 | $75,000 | $50,000 | $25,000 | $40,000 | $60,000 |
| 25 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $7,000.00 | $5,000.00 | $1.00 | $2,500.00 | $5,000.00 | $7,000.00 | $4,500.00 |
| 26 | Portable changeable message sign (503-7001) | DAY | 61 | $120.00 | $40.00 | $55.00 | $150.00 | $200.00 | $300.00 | $50.00 |
| 27 | TMA (stationary) (505-7001) | DAY | 29 | $200.00 | $500.00 | $1.00 | $200.00 | $150.00 | $250.00 | $300.00 |
| 28 | Temporary sediment control fence (install) (506-7039) | LF | 500 | $4.50 | $1.00 | $2.00 | $3.00 | $4.00 | $5.00 | $5.00 |
| 29 | Temporary sediment control fence (remove) (506-7041) | LF | 500 | $1.50 | $1.00 | $1.00 | $1.00 | $1.00 | $2.00 | $2.00 |
| 30 | One-way traffic control (port traffic signal) (510-7003) | MO | 2 | $6,500.00 | $6,000.00 | $14,000 | $8,200.00 | $10,000 | $5,000.00 | $10,000 |
| 31 | Metal W-beam guard fence (timber post) (540-7001) | LF | 338 | $35.00 | $42.00 | $27.00 | $30.00 | $40.00 | $30.00 | $35.00 |
| 32 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 62 | $110.00 | $88.00 | $100.00 | $150.00 | $70.00 | $90.00 | $130.00 |
| 33 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,300.00 | $3,500.00 | $3,500.00 | $3,500.00 | $4,000.00 | $3,100.00 | $5,000.00 |
| 34 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 8 | $50.00 | $50.00 | $25.00 | $80.00 | $110.00 | $40.00 | $50.00 |
| 35 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 20 | $300.00 | $200.00 | $250.00 | $250.00 | $200.00 | $65.00 | $500.00 |
| 36 | Concrete CRCK repair(discrete)(rout and seal) (780-7003) | LF | 174 | $100.00 | $55.00 | $45.00 | $80.00 | $50.00 | $20.00 | $65.00 |
| 37 | Carbon fiber reinforced polymer protection (786-7001) | SF | 19 | $180.00 | $125.00 | $450.00 | $500.00 | $450.00 | $68.00 | $225.00 |
| 38 | Maintenance speed limit signing (7010-7002) | DAY | 13 | $250.00 | $200.00 | $1.00 | $150.00 | $50.00 | $200.00 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 9, 2025. Compiled by Mirage Metrics.