TxDOT contract A00220151 bid tabulation
METAL BEAM GUARD FENCE REPAIR, US0290 (VARIOUS LOCATIONS IN BASTROP to CALDWELL AND LEE COUNTIES). Let by Texas DOT on May 13, 2026, Bastrop, Austin District. 5 bids received; low bid $757,352 by Ross Sa Enterprise LLC, -22% against the engineer's estimate of $970,617.
- Owner
- Texas DOT
- Letting
- 13 MAY 2026
- Pay items
- 43
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ross Sa Enterprise LLC | $757,352 | Low | -22% |
| 2 | Austin Barricade Company, L.L.C. | $972,811 | +28% | 0.0% |
| 3 | Rhino Equity, LLC | $978,339 | +29% | +1.0% |
| 4 | T&L Cleaning Services LLC | $1,205,334 | +59% | +24% |
| 5 | Shalom Services Corporation | $1,335,956 | +76% | +38% |
Engineer's estimate: $970,617.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ross Sa Enterprise LLC | 2. Austin Barricade Company, L.L.C. | 3. Rhino Equity, LLC | 4. T&L Cleaning Services LLC | 5. Shalom Services Corporation |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 1,600 | $8.00 | $1.00 | $1.00 | $0.50 | $50.00 | $25.00 |
| 2 | Riprap (mow strip)(4 in) (432-7013) | CY | 150 | $630.00 | $1.00 | $10.00 | $100.00 | $400.00 | $500.00 |
| 3 | Mobilization (callout 1) (500-7003) | EACH | 500 | $400.00 | $1.00 | $0.25 | $1.00 | $1.00 | $100.00 |
| 4 | TMA (stationary) (505-7001) | DAY | 180 | $200.00 | $1.00 | $1.00 | $1.00 | $1.00 | $800.00 |
| 5 | Temporary sediment control fence (install) (506-7039) | LF | 10 | $4.50 | $1.00 | $8.00 | $1.00 | $500.00 | $1.00 |
| 6 | Temporary sediment control fence (remove) (506-7041) | LF | 10 | $3.00 | $1.00 | $8.00 | $1.00 | $500.00 | $1.00 |
| 7 | Downstream anchor terminal section (540-7015) | EACH | 12 | $1,500.00 | $1.00 | $100.00 | $1,400.00 | $1,500.00 | $1,600.00 |
| 8 | Remove metal beam guard fence (542-7001) | LF | 150 | $4.00 | $1.00 | $50.00 | $0.50 | $1.00 | $10.00 |
| 9 | Cable barrier system (install)(TL-4) (543-7002) | LF | 80 | $30.00 | $1.00 | $25.00 | $20.00 | $500.00 | $15.00 |
| 10 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 8 | $2,500.00 | $1.00 | $1,000.00 | $2,500.00 | $4,000.00 | $3,000.00 |
| 11 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $3,300.00 | $1.00 | $400.00 | $500.00 | $3,000.00 | $3,500.00 |
| 12 | Guardrail end treatment (remove) (544-7003) | EACH | 8 | $250.00 | $1.00 | $1.00 | $50.00 | $1,000.00 | $300.00 |
| 13 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 20 | $23.00 | $1.00 | $800.00 | $30.00 | $15.00 | $35.00 |
| 14 | Install delineator assembly (D-SY)SZ 2(WC)GND(BI) (658-7029) | EACH | 4 | $100.00 | $1.00 | $500.00 | $100.00 | $15.00 | $100.00 |
| 15 | Replace rail element (W-beam) (770-7001) | LF | 5,600 | $9.00 | $28.00 | $40.00 | $30.00 | $24.00 | $18.00 |
| 16 | Replace rail element (thrie-beam) (770-7002) | LF | 100 | $75.00 | $25.00 | $35.00 | $100.00 | $20.00 | $30.00 |
| 17 | Repl rail elmnt(thrie-BM trans to W-BM) (770-7003) | EACH | 30 | $35.00 | $1.00 | $5.00 | $1.00 | $300.00 | $191.00 |
| 18 | Replace timber post W/O concrete FND (770-7006) | EACH | 150 | $91.00 | $60.00 | $50.00 | $100.00 | $1.00 | $75.00 |
| 19 | Replace steel post W/O concrete FND (770-7007) | EACH | 10 | $30.00 | $1.00 | $55.00 | $1.00 | $100.00 | $65.00 |
| 20 | Replace timber post W/ concrete FND (770-7008) | EACH | 150 | $101.00 | $60.00 | $50.00 | $100.00 | $1.00 | $70.00 |
| 21 | Replace steel post W/ concrete FND (770-7009) | EACH | 8 | $5.00 | $1.00 | $100.00 | $1.00 | $100.00 | $80.00 |
| 22 | Realign posts (770-7010) | EACH | 150 | $125.00 | $25.00 | $50.00 | $35.00 | $1.00 | $20.00 |
| 23 | Replace terminal anchor posts (770-7012) | EACH | 2 | $5.00 | $1.00 | $1.00 | $1.00 | $100.00 | $500.00 |
| 24 | Rem obsolete get & repl W/ SGT (770-7013) | EACH | 130 | $1,500.00 | $2,900.00 | $3,000.00 | $3,200.00 | $4,000.00 | $3,500.00 |
| 25 | Repl single gdrail terminal impact head (770-7015) | EACH | 6 | $772.00 | $400.00 | $1,000.00 | $800.00 | $1,000.00 | $1,500.00 |
| 26 | Replace blockout (770-7018) | EACH | 350 | $48.00 | $10.00 | $20.00 | $30.00 | $10.00 | $45.00 |
| 27 | Reset SGT impact head (770-7020) | EACH | 20 | $270.00 | $1.00 | $200.00 | $1.00 | $1.00 | $200.00 |
| 28 | Replace SGT object marker (770-7021) | EACH | 4 | $42.00 | $1.00 | $500.00 | $1.00 | $1.00 | $49.00 |
| 29 | Replace SGT cable anchor (770-7022) | EACH | 4 | $223.00 | $1.00 | $500.00 | $1.00 | $1.00 | $95.00 |
| 30 | Replace SGT cable assembly (770-7023) | EACH | 8 | $132.00 | $1.00 | $1.00 | $1.00 | $1.00 | $100.00 |
| 31 | Replace SGT strut (770-7024) | EACH | 8 | $148.00 | $1.00 | $1.00 | $1.00 | $1.00 | $100.00 |
| 32 | Repair rail element (curved rail) (770-7027) | LF | 80 | $20.00 | $20.00 | $50.00 | $1.00 | $30.00 | $30.00 |
| 33 | Replace posts (TL-4)(gibraltar) (771-7005) | EACH | 200 | $215.00 | $110.00 | $300.00 | $200.00 | $150.00 | $200.00 |
| 34 | Replace posts (TL-4)(NU-cable) (771-7006) | EACH | 20 | $1.00 | $1.00 | $100.00 | $1.00 | $1.00 | $100.00 |
| 35 | Replace posts (TL-4)(trinity) (771-7007) | EACH | 600 | $200.00 | $230.00 | $300.00 | $215.00 | $300.00 | $150.00 |
| 36 | Replace posts (TL-4)(brifen) (771-7008) | EACH | 20 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $114.00 |
| 37 | Cable splice / turnbuckle (TL-4) (771-7010) | EACH | 20 | $20.00 | $1.00 | $1.00 | $50.00 | $150.00 | $153.00 |
| 38 | Repair or replace cable barrier terminal sec(TL-4) (771-7014) | EACH | 80 | $500.00 | $200.00 | $1.00 | $1,000.00 | $500.00 | $1,000.00 |
| 39 | Replace cable (TL-4) (771-7016) | LF | 800 | $5.00 | $1.00 | $3.00 | $1.00 | $0.01 | $5.00 |
| 40 | Check / RE-tension cable (TL-4) (771-7018) | EACH | 100 | $44.00 | $1.00 | $1.00 | $50.00 | $1.00 | $123.00 |
| 41 | Replace (wide quad) (774-7031) | EACH | 2 | $2,500.00 | $1.00 | $2,500.00 | $1,500.00 | $1.00 | $35,000 |
| 42 | Repair (wide quad) (774-7032) | LF | 20 | $500.00 | $600.00 | $500.00 | $750.00 | $250.00 | $1,000.00 |
| 43 | Concrete rail repair (in-kind) (778-7001) | LF | 8 | $395.00 | $1.00 | $500.00 | $50.00 | $25.00 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 13, 2026. Compiled by Mirage Metrics.