TxDOT letting results, November 15, 2022
22 contracts let by Texas DOT on November 15, 2022, $4,965,372 in low bids, a median of 3 bidders per contract. On the 22 with an engineer's estimate, the low bid came in under it 10 times; median low bid +1.0% against the estimate.
- Owner
- Texas DOT
- Contracts
- 22
- Low bids, total
- $4,965,372
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 11220201 | IH0020 Tree trimming and brush removal from VARIOUS LOCATIONS WITHIN to SOUTH TARRANT COUNTY | Fort Worth District | 4 | Pathfield Investments LLC | $364,950 | $426,598 | +17% | +17% | TxDOT |
| 11220802 | IH0020 Hot mix from VARIOUS LOCATIONS to IN ABILENE DISTRICT | Abilene District | 1 | RK Hall, LLC | $299,900 | +12% | TxDOT | ||
| 11221607 | FM0774 Flexible base from VARIOUS | Corpus Christi District | 3 | Digg Commercial, LLC | $286,000 | $287,625 | +1.0% | -2.0% | TxDOT |
| 11221608 | FM3036 Flexible base from VARIOUS | Corpus Christi District | 3 | Digg Commercial, LLC | $286,000 | $359,125 | +26% | -2.0% | TxDOT |
| 11221604 | US0181 Hot mix from VARIOUS | Corpus Christi District | 2 | Brauntex Materials, Inc. | $285,600 | $299,200 | +5.0% | -3.0% | TxDOT |
| 11221603 | US0059 Bridge scour repair from US 59 SB @ COLETO CR RES to 1.80 MI E OF FM 2987 | Corpus Christi District | 8 | MB Western Industrial Contracting Co. | $282,477 | $293,869 | +4.0% | -1.0% | TxDOT |
| 11221703 | SH0006 Tree removal from VARIOUS to VARIOUS | Bryan District | 2 | GV Landscape and Construction LLC | $269,400 | $313,925 | +17% | +82% | TxDOT |
| 11221806 | US0080 Storm sewer and drain inlet cleaning from VARIOUS ROADWAYS IN THE SOUTHEAST to DALLAS COUNTY MAINTENANCE SECTION | Dallas District | 3 | Shalom Services Corporation | $268,980 | $390,050 | +45% | +1.0% | TxDOT |
| 11221805 | IH0030 Storm sewer and drain inlet cleaning from VARIOUS ROADWAYS IN THE NORTHEAST to DALLAS COUNTY MAINTENANCE SECTION | Dallas District | 3 | Shalom Services Corporation | $267,905 | $397,550 | +48% | 0.0% | TxDOT |
| 11221822 | FM2728 Aggregate from KAUFMAN/ROCKWALL to MAINTENANCE SECTION | Dallas District | 1 | Arcosa LWS, LLC | $265,000 | +2.0% | TxDOT | ||
| 11220202 | IH0020 Cleaning and sealing cracks from VARIOUS LOCATIONS WITHIN to SOUTH TARRANT COUNTY | Fort Worth District | 3 | D & M Contractors, LLC | $239,921 | $287,337 | +20% | +22% | TxDOT |
| 11221605 | US0059 Flexible base from VARIOUS | Corpus Christi District | 3 | Brauntex Materials, Inc. | $235,625 | $260,000 | +10% | -19% | TxDOT |
| 11221606 | US0059 Flexible base from VARIOUS | Corpus Christi District | 4 | Brauntex Materials, Inc. | $235,625 | $292,500 | +24% | -19% | TxDOT |
| 11221823 | FM2728 Flexible base from KAUFMAN/ROCKWALL to MAINTENANCE SECTION | Dallas District | 4 | FNH Construction, LLC | $232,000 | $360,320 | +55% | +4.0% | TxDOT |
| 11221713 | IH0045 Rock/riprap from VARIOUS to VARIOUS | Bryan District | 3 | Touchstone Resources, LLC | $193,900 | $215,600 | +11% | +4.0% | TxDOT |
| 11221709 | IH0045 Cutback from VARIOUS to VARIOUS | Bryan District | 2 | Martin Resource Management Corporation | $181,320 | $224,640 | +24% | -6.0% | TxDOT |
| 11221820 | US0380 Hot mix from DENTON COUNTY to MAINTENANCE SECTION | Dallas District | 2 | Eurovia Atlantic Coast LLC | $181,300 | $196,000 | +8.0% | -19% | TxDOT |
| 11221602 | US0059 Bridge preventative maintenance from VARIOUS | Corpus Christi District | 5 | American Infrastructure Maintenance Management LLC | $148,260 | $195,303 | +32% | -8.0% | TxDOT |
| 11221601 | US0059 Bridge preventative maintenance from VARIOUS | Corpus Christi District | 5 | American Infrastructure Maintenance Management LLC | $138,880 | $174,454 | +26% | -18% | TxDOT |
| 11220801 | US0084 Winter weather material from VARIOUS LOCATIONS to IN ABILENE DISTRICT | Abilene District | 3 | NSG Logistics, LLC | $134,009 | $136,500 | +2.0% | +1.0% | TxDOT |
| 11221609 | SH0044 Winter weather material from VARIOUS | Corpus Christi District | 2 | Touchstone Resources, LLC | $104,960 | $104,960 | 0.0% | +5.0% | TxDOT |
| 11221610 | US0181 Winter weather material from VARIOUS | Corpus Christi District | 2 | Southwest Envirotx Partners, LLC | $63,360 | $63,360 | 0.0% | +5.0% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.