VDOT contract C0000115201C01B bid tabulation
Sidewalk construction. Let by Virginia DOT on October 28, 2026, Henrico, Richmond. 4 bids received; low bid $638,317 by FLB Contractors, Inc..
- Owner
- Virginia DOT
- Letting
- 28 OCT 2026
- Pay items
- 70
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | FLB Contractors, Inc. | $638,317 | Low |
| 2 | North Construction, Inc. | $900,848 | +41% |
| 3 | M & F Concrete, Inc. | $911,645 | +43% |
| 4 | Sagres Construction Corporation | $1,160,000 | +82% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. FLB Contractors, Inc. | 2. North Construction, Inc. | 3. M & F Concrete, Inc. | 4. Sagres Construction Corporation |
|---|---|---|---|---|---|---|---|
| 0001-0010 | Clearing and grubbing (301SD20-0001) | LS | 1 | $10,210 | $25,000 | $35,776 | $162,000 |
| 0001-0020 | Regular excavation (303SD20-0001) | CY | 413 | $50.00 | $140.00 | $416.00 | $91.61 |
| 0001-0030 | Embankment (303SD20-0010) | CY | 156 | $35.00 | $63.13 | $416.00 | $105.08 |
| 0001-0040 | Siltation control excavation (303SD20-0029) | CY | 179.70 | $10.00 | $110.00 | $1.04 | $93.10 |
| 0001-0050 | Inlet protection type B (303SD20-0031) | EACH | 3 | $415.00 | $200.00 | $312.00 | $182.91 |
| 0001-0060 | Temp. silt fence type A (303SD20-0034) | LF | 969 | $4.50 | $6.88 | $10.40 | $6.10 |
| 0001-0070 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 381 | $65.00 | $70.00 | $45.29 | $89.70 |
| 0001-0080 | Asphalt concrete TY. SM- 12.5D const (315SD20-0002) | TON | 150 | $200.00 | $250.00 | $273.00 | $294.44 |
| 0001-0090 | Asphalt concrete TY. IM- 19.0D const (315SD20-0005) | TON | 59 | $215.00 | $300.00 | $442.00 | $290.20 |
| 0001-0100 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 60 | $210.00 | $250.00 | $429.00 | $283.49 |
| 0001-0110 | Saw-cut asphalt concrete saw-cut (315SD20-0104) | LF | 403 | $4.50 | $5.00 | $10.40 | $4.71 |
| 0001-0120 | Curb, STD. CG-2 (502SD20-0011) | LF | 401 | $35.00 | $62.00 | $31.20 | $110.00 |
| 0001-0130 | Comb. curb & gutter, STD. CG-6 (502SD20-0022) | LF | 71 | $40.00 | $75.00 | $33.28 | $120.00 |
| 0001-0140 | Comb. curb & gutter, rad. CG-6 (502SD20-0023) | LF | 229 | $45.00 | $75.00 | $33.28 | $120.00 |
| 0001-0150 | Entrance gutter CG-9D (502SD20-0029) | SY | 54 | $135.00 | $225.00 | $140.40 | $225.00 |
| 0001-0160 | CG-12 detectable warning surface (504SD20-0002) | SY | 11 | $385.00 | $500.00 | $561.60 | $625.00 |
| 0001-0170 | Hydr. cement conc. sidewalk 4" (504SD20-0003) | SY | 581 | $125.00 | $165.00 | $79.56 | $125.00 |
| 0001-0180 | Demo. of pavement flexible (508SD20-0004) | SY | 265 | $80.00 | $38.00 | $116.17 | $40.00 |
| 0001-0190 | Adjust exist. valve & box (510SD20-0038) | EACH | 1 | $1,105.00 | $1,000.00 | $832.00 | $1,428.00 |
| 0001-0200 | Adjust exist frame & cover (510SD20-0050) | EACH | 1 | $985.00 | $2,500.00 | $832.00 | $1,440.59 |
| 0001-0210 | NS reconstruct exist. structure top with A DI- precast top (510SX20-0035) | EACH | 3 | $4,310.00 | $6,250.00 | $10,088 | $5,979.30 |
| 0001-0220 | NS adjust exist. sewer cleanout (510SX20-0046) | EACH | 2 | $785.00 | $1,268.01 | $832.00 | $1,689.44 |
| 0001-0230 | NS adjust exist. small gas valve box (510SX20-0046) | EACH | 7 | $875.00 | $850.00 | $832.00 | $1,059.59 |
| 0001-0240 | Type 3 barricade 8' (512SD20-0013) | EACH | 20 | $225.00 | $437.50 | $468.00 | $216.89 |
| 0001-0250 | Temporary sign (512SD20-0014) | SF | 1,072 | $25.00 | $1.00 | $36.40 | $37.85 |
| 0001-0260 | Truck mounted attenuator (512SD20-0023) | HR | 608 | $5.00 | $75.00 | $31.20 | $78.83 |
| 0001-0270 | Group 2 channelizing devices (512SD20-0024) | DAY | 12,360 | $0.10 | $2.03 | $2.08 | $1.94 |
| 0001-0280 | Port.changeable mess. sign (512SD20-0025) | HR | 720 | $9.50 | $15.00 | $7.28 | $24.52 |
| 0001-0290 | Electronic arrow board (512SD20-0026) | HR | 608 | $10.00 | $10.00 | $5.20 | $16.04 |
| 0001-0300 | Mobilization (513SD20-0001) | LS | 1 | $185,700 | $100,000 | $43,501 | $85,250 |
| 0001-0310 | Flex. pave.tie-in planing above 2"-4" (515SD20-0003) | SY | 94 | $60.00 | $68.75 | $169.00 | $142.86 |
| 0001-0320 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 1,115 | $7.00 | $20.58 | $18.20 | $20.20 |
| 0001-0330 | Demolition of building wooden fence D-1 parcel 5 (516SD20-0002) | LS | 1 | $3,000.00 | $3,750.00 | $2,496.00 | $10,000 |
| 0001-0340 | Demolition of building wooden fence D-2 parcel 6 (516SD20-0002) | LS | 1 | $550.00 | $3,750.00 | $5,304.00 | $10,000 |
| 0001-0350 | Demolition of building wooden fence D-4 parcel 10 (516SD20-0002) | LS | 1 | $4,100.00 | $4,500.00 | $6,552.00 | $10,000 |
| 0001-0360 | Demolition of building wooden fence D-5 parcel 11 (516SD20-0002) | LS | 1 | $300.00 | $6,875.00 | $4,992.00 | $10,000 |
| 0001-0370 | Demolition of building wooden fence D-6 parcel 11 (516SD20-0002) | LS | 1 | $1,210.00 | $5,312.50 | $1,809.60 | $10,000 |
| 0001-0380 | Demolition of building wooden fence D-7 parcel 5 (516SD20-0002) | LS | 1 | $1,500.00 | $3,750.00 | $832.00 | $10,000 |
| 0001-0390 | Demolition of building wooden fence D-8 parcel 6 (516SD20-0002) | LS | 1 | $1,000.00 | $3,750.00 | $832.00 | $10,000 |
| 0001-0400 | Clearing parcel light post D-902 parcel 5 (516SD20-0003) | LS | 1 | $875.00 | $3,750.00 | $1,248.00 | $10,000 |
| 0001-0410 | Clearing parcel wooden fence sta. 107+07 - 109+62 remove and reset (516SD20-0003) | LS | 1 | $7,810.00 | $27,000 | $26,910 | $10,000 |
| 0001-0420 | Clearing parcel wooden retaining wall D-900 parcel 5 (516SD20-0003) | LS | 1 | $1,310.00 | $9,375.00 | $1,560.00 | $10,000 |
| 0001-0430 | Clearing parcel wooden retaining wall D-901 parcel 5 (516SD20-0003) | LS | 1 | $1,310.00 | $9,375.00 | $1,560.00 | $10,000 |
| 0001-0440 | Clearing parcel wooden retaining wall D-903 parcel 4 (516SD20-0003) | LS | 1 | $1,310.00 | $7,812.50 | $1,560.00 | $10,000 |
| 0001-0450 | Construction surveying constr. (517SD20-0001) | LS | 1 | $47,800 | $50,000 | $7,150.00 | $69,377 |
| 0001-0460 | 1" water service line (520SD20-0003) | LF | 136 | $57.00 | $180.00 | $312.00 | $250.00 |
| 0001-0470 | 1" water meter box & yoke (520SD20-0168) | EACH | 2 | $3,000.00 | $3,500.00 | $2,600.00 | $4,088.49 |
| 0001-0480 | 6" sanitary service lateral connection (520SD20-0183) | LF | 9 | $380.00 | $607.11 | $780.00 | $400.00 |
| 0001-0490 | Manhole frame & cover F & C-1 (520SD20-0274) | EACH | 1 | $1,000.00 | $3,000.00 | $1,248.00 | $12,000 |
| 0001-0500 | 6" sewer cleanout (520SX20-0006) | EACH | 1 | $850.00 | $3,935.73 | $832.00 | $5,000.00 |
| 0001-0510 | Topsoil class B (602SD20-0006) | CY | 133 | $33.00 | $93.75 | $83.20 | $147.76 |
| 0001-0520 | Temporary seed (603SD20-0002) | LB | 33 | $1.00 | $28.00 | $20.80 | $14.13 |
| 0001-0530 | Regular seed (603SD20-0003) | LB | 89 | $1.50 | $28.00 | $20.80 | $11.78 |
| 0001-0540 | Overseeding (603SD20-0004) | LB | 71 | $0.85 | $28.00 | $7.28 | $10.17 |
| 0001-0550 | Legume seed (603SD20-0005) | LB | 6 | $7.00 | $28.00 | $7.28 | $23.56 |
| 0001-0560 | Legume overseeding (603SD20-0006) | LB | 5 | $6.00 | $28.00 | $7.28 | $23.56 |
| 0001-0570 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 1,997 | $0.25 | $7.00 | $6.24 | $4.06 |
| 0001-0580 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 1,997 | $0.30 | $8.00 | $6.24 | $10.41 |
| 0001-0590 | Fertilizer nitrogen - N (603SD20-0014) | LB | 33 | $1.00 | $21.41 | $20.80 | $4.71 |
| 0001-0600 | Fertilizer phosphorous - P (603SD20-0015) | LB | 23 | $1.00 | $19.21 | $20.80 | $4.71 |
| 0001-0610 | Fertilizer potassium - K (603SD20-0016) | LB | 23 | $1.00 | $15.44 | $20.80 | $4.71 |
| 0001-0620 | Lime (603SD20-0017) | TON | 1.82 | $5.00 | $1,000.00 | $832.00 | $529.99 |
| 0001-0630 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 30 | $12.00 | $42.60 | $62.40 | $61.50 |
| 0001-0640 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 30 | $10.00 | $52.00 | $62.40 | $61.50 |
| 0001-0650 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 6 | $300.00 | $10.00 | $832.00 | $1,001.10 |
| 0001-0660 | Sign panel (701SD20-0001) | SF | 25 | $40.00 | $58.00 | $72.80 | $64.78 |
| 0001-0670 | Remove existing manhole/junction box (703SD20-0048) | EACH | 2 | $500.00 | $2,000.00 | $1,040.00 | $2,355.53 |
| 0001-0680 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 1,269 | $4.50 | $4.50 | $1.44 | $2.46 |
| 0001-0690 | Type B class II PVMT line MRKG 6" (704SD20-0012) | LF | 357 | $5.00 | $6.50 | $5.20 | $4.58 |
| 0001-0700 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 51 | $18.00 | $59.96 | $35.10 | $29.44 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of October 28, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way