WisDOT contract 20250114045 bid tabulation
C New Berlin Moorland Road; CTH Es to CTH D (CTH O, Waukesha County C New Berlin, Mooreland Rd). Let by Wisconsin DOT on January 14, 2025, Waukesha. 8 bids received; low bid $8,340,785 by Hoffman Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 14 JAN 2025
- Pay items
- 224
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Hoffman Construction Company | $8,340,785 | Low |
| 2 | Zignego Company, Inc. | $8,444,961 | +1.0% |
| 3 | Musson Bros., Inc. | $8,513,335 | +2.0% |
| 4 | Stark Pavement Corporation | $8,537,649 | +2.0% |
| 5 | Lalonde Contractors Incorporated | $8,746,241 | +5.0% |
| 6 | Vinton Construction Company | $8,796,378 | +5.0% |
| 7 | Michels Road & Stone, Inc. | $9,129,591 | +9.0% |
| 8 | James Peterson Sons, Inc. | $9,265,290 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hoffman Construction Company | 2. Zignego Company, Inc. | 3. Musson Bros., Inc. | 4. Stark Pavement Corporation | 5. Lalonde Contractors Incorporated | 6. Vinton Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 9 | $850.00 | $800.00 | $850.00 | $858.50 | $400.00 | $850.00 |
| 2 | Clearing (201.0120) | ID | 246 | $50.00 | $25.00 | $50.00 | $50.50 | $33.00 | $50.00 |
| 3 | Grubbing (201.0205) | STA | 9 | $200.00 | $400.00 | $200.00 | $202.00 | $140.00 | $200.00 |
| 4 | Grubbing (201.0220) | ID | 246 | $10.00 | $20.00 | $10.00 | $10.10 | $4.00 | $10.00 |
| 5 | Removing concrete pavement (204.0100) | SY | 54,322 | $5.00 | $5.00 | $2.20 | $2.20 | $4.45 | $1.00 |
| 6 | Removing curb & gutter (204.0150) | LF | 1,290 | $5.00 | $5.00 | $3.30 | $3.30 | $5.58 | $6.50 |
| 7 | Removing concrete sidewalk (204.0155) | SY | 488 | $10.00 | $10.00 | $3.10 | $3.10 | $7.72 | $9.00 |
| 8 | Removing concrete bases (204.0195) | EACH | 14 | $304.68 | $200.00 | $166.00 | $304.68 | $304.68 | $304.68 |
| 9 | Removing manholes (204.0210) | EACH | 13 | $500.00 | $500.00 | $1,161.00 | $505.00 | $575.00 | $515.00 |
| 10 | Removing inlets (204.0220) | EACH | 56 | $500.00 | $500.00 | $916.00 | $404.00 | $375.00 | $335.00 |
| 11 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 1,483 | $12.00 | $12.00 | $23.00 | $10.10 | $19.00 | $10.70 |
| 12 | Removing storm sewer (size) 02. 15-inch (204.0245) | LF | 448 | $12.00 | $12.00 | $22.00 | $12.12 | $19.00 | $10.70 |
| 13 | Removing storm sewer (size) 03. 18-inch (204.0245) | LF | 253 | $12.00 | $12.00 | $22.00 | $14.14 | $20.00 | $12.60 |
| 14 | Removing storm sewer (size) 05. 24-inch (204.0245) | LF | 99 | $16.00 | $16.00 | $22.00 | $20.20 | $22.00 | $16.00 |
| 15 | Removing storm sewer (size) 06. 27-inch (204.0245) | LF | 442 | $16.00 | $16.00 | $22.00 | $23.23 | $25.00 | $16.25 |
| 16 | Removing storm sewer (size) 07. 30-inch (204.0245) | LF | 283 | $16.00 | $16.00 | $22.00 | $25.25 | $30.00 | $16.75 |
| 17 | Removing (item description) 01.traffic signals ( CTH O (S moorland RD) & W ryerson RD) (204.9060.S) | EACH | 1 | $5,559.84 | $5,559.84 | $5,559.84 | $5,559.84 | $5,559.84 | $5,559.84 |
| 18 | Removing (item description) 02.traffic signals ( CTH O (S moorland RD) & W coffee RD) (204.9060.S) | EACH | 1 | $3,790.80 | $3,790.80 | $3,790.80 | $3,790.80 | $3,790.80 | $3,790.80 |
| 19 | Removing (item description) 01. landscaping bricks (204.9090.S) | LF | 20 | $20.00 | $50.00 | $25.50 | $50.00 | $9.00 | $9.00 |
| 20 | Excavation common (205.0100) | CY | 43,086 | $0.01 | $0.01 | $13.00 | $13.00 | $14.84 | $22.03 |
| 21 | Backfill structure type B (210.2100) | CY | 48 | $50.00 | $50.00 | $47.50 | $47.50 | $38.00 | $60.00 |
| 22 | Finishing roadway (project) 01. 2722-08-71 (213.0100) | EACH | 1 | $100.00 | $1,000.00 | $500.00 | $30,000 | $3,000.00 | $6,000.00 |
| 23 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 23,235 | $0.01 | $0.01 | $11.50 | $11.50 | $20.73 | $13.11 |
| 24 | Base aggregate open-graded (310.0110) | TON | 82 | $25.00 | $25.00 | $14.50 | $59.59 | $24.00 | $42.35 |
| 25 | Select crushed material (312.0110) | TON | 20,682 | $0.01 | $0.01 | $18.50 | $18.50 | $16.29 | $20.05 |
| 26 | Coloring concrete custom (405.0200) | CY | 40 | $144.62 | $223.36 | $144.62 | $250.00 | $116.66 | $130.00 |
| 27 | Stamping colored concrete (405.1000) | CY | 40 | $703.49 | $269.56 | $703.49 | $430.00 | $281.96 | $300.00 |
| 28 | Concrete pavement 10 1/2-inch (415.0105) | SY | 46,987 | $59.27 | $63.84 | $59.27 | $61.40 | $63.03 | $61.69 |
| 29 | Concrete pavement hes 10 1/2- inch (415.1105) | SY | 4,423 | $87.90 | $76.00 | $87.90 | $69.75 | $80.41 | $65.69 |
| 30 | Drilled tie bars (416.0610) | EACH | 90 | $9.69 | $30.00 | $9.69 | $13.50 | $12.70 | $10.00 |
| 31 | Drilled dowel bars (416.0620) | EACH | 120 | $13.29 | $30.00 | $13.29 | $17.00 | $16.55 | $18.00 |
| 32 | Tack coat (455.0605) | GAL | 80 | $2.50 | $4.00 | $4.00 | $10.00 | $4.00 | $4.00 |
| 33 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 81 | $445.00 | $216.00 | $216.00 | $400.00 | $216.00 | $216.00 |
| 34 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 96 | $255.00 | $186.00 | $186.00 | $385.00 | $186.00 | $186.00 |
| 35 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 60 | $255.00 | $259.00 | $259.00 | $410.00 | $259.00 | $259.00 |
| 36 | Asphaltic surface driveways and field entrances (465.0120) | TON | 96 | $445.00 | $245.00 | $245.00 | $375.00 | $245.00 | $245.00 |
| 37 | Asphaltic surface temporary (465.0125) | TON | 513 | $109.00 | $126.00 | $126.00 | $115.00 | $126.00 | $126.00 |
| 38 | Cold patch (495.1000.S) | TON | 50 | $0.01 | $100.00 | $37.50 | $450.00 | $273.30 | $300.00 |
| 39 | Sheet membrane waterproofing for buried structures (516.0610.S) | SY | 310 | $45.00 | $80.00 | $80.00 | $123.00 | $73.00 | $80.00 |
| 40 | Concrete collars for pipe (520.8000) | EACH | 15 | $1,000.00 | $1,000.00 | $958.00 | $353.50 | $838.00 | $950.00 |
| 41 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 1 | $1,500.00 | $1,500.00 | $1,435.00 | $1,666.50 | $1,064.00 | $965.00 |
| 42 | Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015) | EACH | 2 | $1,600.00 | $1,600.00 | $1,470.00 | $1,709.93 | $1,491.00 | $1,085.00 |
| 43 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 2 | $1,700.00 | $1,700.00 | $1,494.00 | $1,826.08 | $1,550.00 | $1,290.00 |
| 44 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 44 | $112.70 | $33.96 | $112.70 | $55.00 | $40.17 | $65.00 |
| 45 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 22,209 | $15.23 | $20.71 | $15.23 | $21.00 | $22.56 | $25.00 |
| 46 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 33 | $16.32 | $68.45 | $16.32 | $55.00 | $42.89 | $65.00 |
| 47 | Concrete curb & gutter 6-inch sloped 30-inch type G (601.0413) | LF | 88 | $17.04 | $59.96 | $17.04 | $55.00 | $43.77 | $65.00 |
| 48 | Concrete curb & gutter integral 30- inch type D (601.0452) | LF | 1,126 | $19.54 | $22.00 | $19.54 | $30.00 | $16.75 | $25.00 |
| 49 | Concrete curb pedestrian (601.0600) | LF | 88 | $101.53 | $64.48 | $101.53 | $42.00 | $48.32 | $44.00 |
| 50 | Concrete sidewalk 5-inch (602.0410) | SF | 10,035 | $7.48 | $8.38 | $7.48 | $6.50 | $7.50 | $10.50 |
| 51 | Curb ramp detectable warning field yellow (602.0505) | SF | 140 | $52.87 | $31.09 | $52.87 | $50.00 | $41.15 | $45.00 |
| 52 | Concrete driveway 7-inch (602.0815) | SY | 368 | $69.26 | $95.08 | $69.26 | $70.00 | $70.16 | $55.00 |
| 53 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 1,409 | $68.00 | $68.00 | $119.00 | $83.83 | $87.00 | $98.75 |
| 54 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 544 | $70.00 | $70.00 | $103.00 | $101.00 | $92.00 | $112.35 |
| 55 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 684 | $72.00 | $72.00 | $98.00 | $102.01 | $117.00 | $115.00 |
| 56 | Storm sewer pipe reinforced concrete class III 21-inch (608.0321) | LF | 380 | $84.00 | $84.00 | $125.00 | $136.35 | $142.00 | $148.00 |
| 57 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 49 | $90.00 | $90.00 | $144.00 | $146.45 | $163.00 | $194.80 |
| 58 | Storm sewer pipe reinforced concrete class III 27-inch (608.0327) | LF | 442 | $120.00 | $120.00 | $158.00 | $163.62 | $173.00 | $172.90 |
| 59 | Storm sewer pipe reinforced concrete class III 30-inch (608.0330) | LF | 283 | $130.00 | $133.00 | $157.00 | $184.83 | $225.00 | $185.30 |
| 60 | Manhole covers type J (611.0530) | EACH | 2 | $800.00 | $800.00 | $793.00 | $777.70 | $550.00 | $516.00 |
| 61 | Inlet covers type H-S (611.0639) | EACH | 59 | $1,000.00 | $1,000.00 | $919.00 | $1,004.95 | $800.00 | $695.00 |
| 62 | Inlet covers type MS-A (611.0645) | EACH | 8 | $800.00 | $800.00 | $839.00 | $808.00 | $585.00 | $550.00 |
| 63 | Catch basins 4-FT diameter (611.1004) | EACH | 5 | $3,000.00 | $3,000.00 | $3,862.00 | $3,761.24 | $5,700.00 | $5,135.00 |
| 64 | Catch basins 5-FT diameter (611.1005) | EACH | 6 | $6,200.00 | $6,200.00 | $5,812.00 | $6,128.68 | $8,150.00 | $6,885.00 |
| 65 | Catch basins 6-FT diameter (611.1006) | EACH | 1 | $10,000 | $10,000 | $11,527 | $9,015.26 | $12,600 | $9,895.00 |
| 66 | Manholes 4-FT diameter (611.2004) | EACH | 2 | $2,500.00 | $2,500.00 | $4,997.00 | $3,665.29 | $5,690.00 | $4,575.00 |
| 67 | Inlets 2X3-FT (611.3230) | EACH | 55 | $2,000.00 | $2,000.00 | $2,237.00 | $2,788.61 | $2,112.00 | $2,950.00 |
| 68 | Adjusting manhole covers (611.8110) | EACH | 10 | $400.00 | $400.00 | $728.00 | $809.01 | $895.00 | $550.00 |
| 69 | Adjusting inlet covers (611.8115) | EACH | 21 | $400.00 | $400.00 | $728.00 | $809.01 | $895.00 | $500.00 |
| 70 | Cover plates temporary (611.8120.S) | EACH | 7 | $400.00 | $400.00 | $454.00 | $353.50 | $250.00 | $520.00 |
| 71 | Salvaged manhole covers (611.9705) | EACH | 7 | $500.00 | $500.00 | $366.00 | $454.50 | $250.00 | $565.00 |
| 72 | Salvaged inlet covers (611.9710) | EACH | 21 | $500.00 | $500.00 | $261.00 | $454.50 | $250.00 | $565.00 |
| 73 | Pipe underdrain 6-inch (612.0106) | LF | 830 | $25.00 | $25.00 | $29.00 | $33.33 | $35.00 | $22.10 |
| 74 | Insulation board polystyrene (inch) 01. 2-inch (612.0902.S) | SY | 76 | $75.00 | $75.00 | $10.00 | $21.21 | $14.00 | $28.00 |
| 75 | Maintenance and repair of haul roads (project) 01. 2722-08-71 (618.0100) | EACH | 1 | $1.00 | $1.00 | $100.00 | $5,000.00 | $1.00 | $0.01 |
| 76 | Mobilization (619.1000) | EACH | 1 | $1,775,157 | $1,609,000 | $735,000 | $520,428 | $278,915 | $409,000 |
| 77 | Concrete median sloped nose (620.0300) | SF | 723 | $12.59 | $34.54 | $12.59 | $15.50 | $15.21 | $15.00 |
| 78 | Water (624.0100) | MGAL | 320.10 | $0.01 | $0.01 | $0.01 | $0.01 | $54.40 | $0.01 |
| 79 | Topsoil (625.0100) | SY | 26,383 | $5.00 | $5.00 | $2.60 | $2.60 | $6.42 | $3.42 |
| 80 | Mulching (627.0200) | SY | 1,510 | $0.30 | $0.30 | $0.30 | $0.30 | $0.30 | $0.30 |
| 81 | Silt fence (628.1504) | LF | 1,573 | $1.76 | $1.76 | $1.76 | $1.76 | $2.13 | $2.13 |
| 82 | Silt fence maintenance (628.1520) | LF | 1,573 | $0.10 | $0.10 | $0.10 | $0.10 | $0.01 | $0.01 |
| 83 | Silt fence heavy duty (628.1530.S) | LF | 244 | $13.00 | $13.00 | $13.00 | $13.00 | $13.00 | $13.00 |
| 84 | Silt fence heavy duty maintenance (628.1535.S) | LF | 244 | $1.00 | $1.00 | $1.00 | $1.00 | $0.01 | $0.01 |
| 85 | Mobilizations erosion control (628.1905) | EACH | 16 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 86 | Mobilizations emergency erosion control (628.1910) | EACH | 9 | $50.00 | $50.00 | $50.00 | $50.00 | $25.00 | $25.00 |
| 87 | Inlet protection type A (628.7005) | EACH | 94 | $60.00 | $60.00 | $60.00 | $60.00 | $50.00 | $50.00 |
| 88 | Inlet protection type B (628.7010) | EACH | 3 | $95.00 | $95.00 | $95.00 | $95.00 | $50.00 | $50.00 |
| 89 | Inlet protection type C (628.7015) | EACH | 4 | $95.00 | $95.00 | $95.00 | $95.00 | $50.00 | $50.00 |
| 90 | Inlet protection type D (628.7020) | EACH | 123 | $95.00 | $95.00 | $95.00 | $95.00 | $120.00 | $120.00 |
| 91 | Temporary ditch checks (628.7504) | LF | 20 | $15.00 | $15.00 | $15.00 | $15.00 | $8.00 | $8.00 |
| 92 | Culvert pipe checks (628.7555) | EACH | 15 | $30.00 | $30.00 | $30.00 | $30.00 | $25.00 | $25.00 |
| 93 | Fertilizer type B (629.0210) | CWT | 18 | $80.00 | $80.00 | $80.00 | $80.00 | $80.00 | $80.00 |
| 94 | Seeding mixture no. 40 (630.0140) | LB | 30 | $15.00 | $15.00 | $15.00 | $15.00 | $13.00 | $13.00 |
| 95 | Seeding temporary (630.0200) | LB | 40 | $10.00 | $10.00 | $10.00 | $10.00 | $3.00 | $3.00 |
| 96 | Seed water (630.0500) | MGAL | 500 | $11.50 | $11.50 | $11.50 | $11.50 | $10.00 | $10.00 |
| 97 | Sod water (631.0300) | MGAL | 647 | $40.00 | $40.00 | $40.00 | $40.00 | $10.00 | $10.00 |
| 98 | Sod lawn (631.1000) | SY | 14,172 | $6.85 | $6.85 | $6.85 | $6.85 | $6.50 | $6.50 |
| 99 | Signs type II reflective H (637.2210) | SF | 899.46 | $19.10 | $19.10 | $19.10 | $19.10 | $21.10 | $21.10 |
| 100 | Signs type II reflective H folding (637.2215) | SF | 96.98 | $28.00 | $28.00 | $28.00 | $28.00 | $30.00 | $30.00 |
| 101 | Signs type II reflective F (637.2230) | SF | 85 | $19.10 | $19.10 | $19.10 | $19.10 | $23.10 | $23.10 |
| 102 | Removing signs type II (638.2602) | EACH | 120 | $30.00 | $30.00 | $30.00 | $30.00 | $13.00 | $13.00 |
| 103 | Removing small sign supports (638.3000) | EACH | 63 | $30.00 | $30.00 | $30.00 | $30.00 | $13.00 | $13.00 |
| 104 | Field office type D (642.5401) | EACH | 1 | $25,000 | $20,000 | $19,800 | $16,000 | $19,390 | $15,000 |
| 105 | Traffic control drums (643.0300) | DAY | 85,043 | $0.07 | $0.12 | $0.12 | $0.12 | $0.12 | $0.12 |
| 106 | Traffic control barricades type III (643.0420) | DAY | 9,796 | $0.20 | $0.68 | $0.68 | $0.68 | $0.68 | $0.68 |
| 107 | Traffic control flexible tubular marker posts (643.0500) | EACH | 119 | $25.00 | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 |
| 108 | Traffic control flexible tubular marker bases (643.0600) | EACH | 119 | $5.00 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 109 | Traffic control warning lights type A (643.0705) | DAY | 4,626 | $0.10 | $0.10 | $0.10 | $0.10 | $0.10 | $0.10 |
| 110 | Traffic control warning lights type C (643.0715) | DAY | 8,585 | $0.10 | $0.10 | $0.10 | $0.10 | $0.10 | $0.10 |
| 111 | Traffic control arrow boards (643.0800) | DAY | 642 | $5.00 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 |
| 112 | Traffic control signs (643.0900) | DAY | 17,245 | $0.15 | $0.40 | $0.40 | $0.40 | $0.40 | $0.40 |
| 113 | Traffic control signs PCMS (643.1050) | DAY | 70 | $30.00 | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 114 | Temporary marking line paint 4- inch (643.3105) | LF | 14,950 | $0.28 | $0.48 | $0.48 | $0.48 | $0.48 | $0.48 |
| 115 | Temporary marking line removable tape 4-inch (643.3150) | LF | 15,451 | $1.35 | $0.78 | $0.78 | $0.78 | $0.78 | $0.78 |
| 116 | Temporary marking line paint 8- inch (643.3205) | LF | 1,474 | $0.55 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 117 | Temporary marking line removable tape 8-inch (643.3250) | LF | 1,035 | $2.70 | $1.65 | $1.65 | $1.65 | $1.65 | $1.65 |
| 118 | Traffic control (643.5000) | EACH | 1 | $40,000 | $38,187 | $38,187 | $38,187 | $38,187 | $38,187 |
| 119 | Temporary pedestrian surface matting (644.1440) | SF | 857 | $8.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 120 | Temporary pedestrian curb ramp (644.1601) | DAY | 987 | $10.00 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 121 | Temporary pedestrian detectable warning field (644.1605) | SF | 120 | $20.00 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 122 | Temporary pedestrian barricade (644.1810) | LF | 528 | $7.50 | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 |
| 123 | Geotextile type DF schedule A (645.0111) | SY | 387 | $3.00 | $3.00 | $1.00 | $16.16 | $2.50 | $4.15 |
| 124 | Geogrid type SR (645.0220) | SY | 8,334 | $2.00 | $2.00 | $2.20 | $2.20 | $1.78 | $2.75 |
| 125 | Marking line epoxy 4-inch (646.1020) | LF | 25,138 | $0.80 | $0.80 | $0.80 | $0.40 | $0.80 | $0.80 |
| 126 | Marking line epoxy 6-inch (646.2020) | LF | 75 | $1.00 | $1.00 | $1.00 | $0.50 | $1.00 | $1.00 |
| 127 | Marking line epoxy 8-inch (646.3020) | LF | 4,293 | $1.35 | $1.35 | $1.35 | $0.93 | $1.35 | $1.35 |
| 128 | Marking arrow epoxy (646.5020) | EACH | 39 | $225.00 | $225.00 | $225.00 | $306.64 | $225.00 | $225.00 |
| 129 | Marking word epoxy (646.5120) | EACH | 6 | $250.00 | $250.00 | $250.00 | $352.38 | $250.00 | $250.00 |
| 130 | Marking symbol epoxy (646.5220) | EACH | 1 | $350.00 | $350.00 | $350.00 | $297.00 | $350.00 | $350.00 |
| 131 | Marking stop line epoxy 18-inch (646.6120) | LF | 488 | $12.00 | $12.00 | $12.00 | $13.05 | $12.00 | $12.00 |
| 132 | Marking diagonal epoxy 12-inch (646.7120) | LF | 2,433 | $8.00 | $8.00 | $8.00 | $12.55 | $8.00 | $8.00 |
| 133 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 690 | $11.00 | $11.00 | $11.00 | $12.11 | $11.00 | $11.00 |
| 134 | Marking curb epoxy (646.8120) | LF | 366 | $8.50 | $8.50 | $8.50 | $6.20 | $8.50 | $8.50 |
| 135 | Marking island nose epoxy (646.8220) | EACH | 13 | $300.00 | $300.00 | $300.00 | $242.00 | $300.00 | $300.00 |
| 136 | Marking removal line 4-inch (646.9000) | LF | 1,100 | $0.75 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 137 | Marking removal line 8-inch (646.9100) | LF | 780 | $1.45 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 138 | Marking removal special marking (646.9300) | EACH | 3 | $125.00 | $155.00 | $155.00 | $155.00 | $155.00 | $155.00 |
| 139 | Construction staking storm sewer (650.4000) | EACH | 162 | $110.00 | $115.00 | $115.00 | $115.00 | $115.00 | $110.00 |
| 140 | Construction staking concrete pavement (650.7000) | LF | 5,970 | $3.00 | $2.50 | $2.50 | $2.50 | $2.50 | $3.00 |
| 141 | Construction staking electrical installations (project) 01. 2722-08- 71 (650.8501) | EACH | 1 | $5,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $5,000.00 |
| 142 | Construction staking curb ramps (650.9000) | EACH | 14 | $130.00 | $135.00 | $135.00 | $135.00 | $135.00 | $130.00 |
| 143 | Construction staking sidewalk (project) 01. 2722-08-71 (650.9500) | EACH | 1 | $800.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $800.00 |
| 144 | Construction staking supplemental control (project) 01. 2722-08-71 (650.9911) | EACH | 1 | $4,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $4,000.00 |
| 145 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 1,898 | $8.90 | $8.90 | $8.90 | $8.90 | $8.90 | $8.90 |
| 146 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 7,898 | $10.35 | $10.35 | $10.35 | $10.35 | $10.35 | $10.35 |
| 147 | Conduit special 3-inch (652.0615) | LF | 122 | $46.52 | $46.52 | $46.52 | $46.52 | $46.52 | $46.52 |
| 148 | Install conduit into existing item (652.0700.S) | EACH | 6 | $408.29 | $408.29 | $408.29 | $408.29 | $408.29 | $408.29 |
| 149 | Pull boxes steel 24X42-inch (653.0140) | EACH | 24 | $1,444.34 | $1,444.34 | $1,444.34 | $1,444.34 | $1,444.34 | $1,444.34 |
| 150 | Removing pull boxes (653.0905) | EACH | 14 | $112.27 | $112.27 | $112.27 | $112.27 | $112.27 | $112.27 |
| 151 | Concrete bases type 1 (654.0101) | EACH | 6 | $992.79 | $992.79 | $992.79 | $992.79 | $992.79 | $992.79 |
| 152 | Concrete bases type 2 (654.0102) | EACH | 2 | $1,327.82 | $1,327.82 | $1,327.82 | $1,327.82 | $1,327.82 | $1,327.82 |
| 153 | Concrete bases type 5 (654.0105) | EACH | 2 | $1,191.55 | $1,191.55 | $1,191.55 | $1,191.55 | $1,191.55 | $1,191.55 |
| 154 | Concrete bases type 10 (654.0110) | EACH | 3 | $6,243.30 | $6,243.30 | $6,243.30 | $6,243.30 | $6,243.30 | $6,243.30 |
| 155 | Concrete bases type 10-special (654.0120) | EACH | 2 | $7,959.15 | $7,959.15 | $7,959.15 | $7,959.15 | $7,959.15 | $7,959.15 |
| 156 | Concrete control cabinet bases type 9 special (654.0217) | EACH | 1 | $2,511.95 | $2,511.95 | $2,511.95 | $2,511.95 | $2,511.95 | $2,511.95 |
| 157 | Cable traffic signal 3-14 AWG (655.0210) | LF | 2,232 | $1.35 | $1.35 | $1.35 | $1.35 | $1.35 | $1.35 |
| 158 | Cable traffic signal 5-14 AWG (655.0230) | LF | 1,052 | $1.62 | $1.62 | $1.62 | $1.62 | $1.62 | $1.62 |
| 159 | Cable traffic signal 7-14 AWG (655.0240) | LF | 1,464 | $2.23 | $2.23 | $2.23 | $2.23 | $2.23 | $2.23 |
| 160 | Cable traffic signal 12-14 AWG (655.0260) | LF | 4,432 | $3.31 | $3.31 | $3.31 | $3.31 | $3.31 | $3.31 |
| 161 | Cable traffic signal 19-12 AWG (655.0275) | LF | 281 | $4.86 | $4.86 | $4.86 | $4.86 | $4.86 | $4.86 |
| 162 | Cable type UF 2-12 AWG grounded (655.0305) | LF | 744 | $1.70 | $1.70 | $1.70 | $1.70 | $1.70 | $1.70 |
| 163 | Cable type UF 2-10 AWG grounded (655.0320) | LF | 1,180 | $2.12 | $2.12 | $2.12 | $2.12 | $2.12 | $2.12 |
| 164 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 10,188 | $1.04 | $1.04 | $1.04 | $1.04 | $1.04 | $1.04 |
| 165 | Electrical wire lighting 12 AWG (655.0610) | LF | 2,622 | $0.95 | $0.95 | $0.95 | $0.95 | $0.95 | $0.95 |
| 166 | Electrical wire lighting 6 AWG (655.0625) | LF | 12,201 | $1.55 | $1.55 | $1.55 | $1.55 | $1.55 | $1.55 |
| 167 | Traffic signal evp detector cable (655.0900) | LF | 2,232 | $1.20 | $1.20 | $1.20 | $1.20 | $1.20 | $1.20 |
| 168 | Electrical service meter breaker pedestal (location) 01. CTH O (S moorland RD) & W ryerson RD (656.0201) | EACH | 1 | $1,316.17 | $1,316.17 | $1,316.17 | $1,316.17 | $1,316.17 | $1,316.17 |
| 169 | Pedestal bases (657.0100) | EACH | 3 | $369.72 | $369.72 | $369.72 | $369.72 | $369.72 | $369.72 |
| 170 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 4 | $724.96 | $724.96 | $724.96 | $724.96 | $724.96 | $724.96 |
| 171 | Poles type 3 (657.0310) | EACH | 2 | $3,336.41 | $3,336.41 | $3,336.41 | $3,336.41 | $3,336.41 | $3,336.41 |
| 172 | Poles type 5-aluminum (657.0322) | EACH | 2 | $2,067.33 | $2,067.33 | $2,067.33 | $2,067.33 | $2,067.33 | $2,067.33 |
| 173 | Poles type 9 (657.0345) | EACH | 1 | $8,176.02 | $8,176.02 | $8,176.02 | $8,176.02 | $8,176.02 | $8,176.02 |
| 174 | Poles type 9-special (657.0347) | EACH | 2 | $10,597 | $10,597 | $10,597 | $10,597 | $10,597 | $10,597 |
| 175 | Poles type 10 (657.0350) | EACH | 2 | $9,941.83 | $9,941.83 | $9,941.83 | $9,941.83 | $9,941.83 | $9,941.83 |
| 176 | Traffic signal standards aluminum 13-FT (657.0420) | EACH | 2 | $886.24 | $886.24 | $886.24 | $886.24 | $886.24 | $886.24 |
| 177 | Traffic signal standards aluminum 15-FT (657.0425) | EACH | 7 | $1,015.59 | $1,015.59 | $1,015.59 | $1,015.59 | $1,015.59 | $1,015.59 |
| 178 | Monotube arms 20-FT (657.0520) | EACH | 2 | $4,189.73 | $4,189.73 | $4,189.73 | $4,189.73 | $4,189.73 | $4,189.73 |
| 179 | Monotube arms 25-FT (657.0525) | EACH | 1 | $4,693.39 | $4,693.39 | $4,693.39 | $4,693.39 | $4,693.39 | $4,693.39 |
| 180 | Monotube arms 45-FT-special (657.0546) | EACH | 2 | $7,040.79 | $7,040.79 | $7,040.79 | $7,040.79 | $7,040.79 | $7,040.79 |
| 181 | Luminaire arms single member 4- inch clamp 6-FT (657.0609) | EACH | 2 | $335.03 | $335.03 | $335.03 | $335.03 | $335.03 | $335.03 |
| 182 | Luminaire arms steel type 10 pole clamp 15-FT (657.0820) | EACH | 8 | $1,217.34 | $1,217.34 | $1,217.34 | $1,217.34 | $1,217.34 | $1,217.34 |
| 183 | Traffic signal face 3S 12-inch (658.0173) | EACH | 12 | $920.57 | $920.57 | $920.57 | $920.57 | $920.57 | $920.57 |
| 184 | Traffic signal face 4S 12-inch (658.0174) | EACH | 17 | $1,130.91 | $1,130.91 | $1,130.91 | $1,130.91 | $1,130.91 | $1,130.91 |
| 185 | Signal mounting hardware (location) 01. CTH O (S moorland RD) & W ryerson RD (658.5070) | EACH | 1 | $3,370.36 | $3,370.36 | $3,370.36 | $3,370.36 | $3,370.36 | $3,370.36 |
| 186 | Signal mounting hardware (location) 02.CTH O (S moorland RD) & W coffee RD (658.5070) | EACH | 1 | $4,416.23 | $4,416.23 | $4,416.23 | $4,416.23 | $4,416.23 | $4,416.23 |
| 187 | Luminaires utility LED C (659.1125) | EACH | 10 | $563.34 | $563.34 | $563.34 | $563.34 | $563.34 | $563.34 |
| 188 | Temporary traffic signals for intersections (location) 01. CTH O (S moorland RD) & W ryerson RD (661.0201) | EACH | 1 | $36,424 | $36,424 | $36,424 | $36,424 | $36,424 | $36,424 |
| 189 | Temporary traffic signals for intersections (location) 02.CTH O (S moorland RD) & W coffee RD (661.0201) | EACH | 1 | $33,573 | $33,573 | $33,573 | $33,573 | $33,573 | $33,573 |
| 190 | Communication vault type 1 (673.0105) | EACH | 4 | $2,912.03 | $2,912.03 | $2,912.03 | $2,912.03 | $2,912.03 | $2,912.03 |
| 191 | Sawing asphalt (690.0150) | LF | 947 | $1.15 | $1.39 | $1.15 | $1.15 | $1.15 | $1.75 |
| 192 | Sawing concrete (690.0250) | LF | 1,669 | $2.25 | $2.00 | $2.25 | $2.25 | $2.25 | $2.35 |
| 193 | Incentive flexural strength concrete pavement (715.0715) | DOL | 15,293 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 194 | Incentive iri ride (740.0440) | DOL | 14,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 195 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 3,500 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 196 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 12,000 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 197 | Special 01. 15-foot decorative light pole (SPV.0060) | EACH | 13 | $7,536.63 | $7,536.63 | $7,536.63 | $7,536.63 | $7,536.63 | $7,536.63 |
| 198 | Special 02. decorative luminaire arm (SPV.0060) | EACH | 13 | $700.43 | $700.43 | $700.43 | $700.43 | $700.43 | $700.43 |
| 199 | Special 03. decorative LED luminaire (SPV.0060) | EACH | 13 | $4,106.47 | $4,106.47 | $4,106.47 | $4,106.47 | $4,106.47 | $4,106.47 |
| 200 | Special 04. decorative pole mounted banner arm (SPV.0060) | EACH | 13 | $1,584.23 | $1,584.23 | $1,584.23 | $1,584.23 | $1,584.23 | $1,584.23 |
| 201 | Special 05. concrete bases type 5 modified (SPV.0060) | EACH | 13 | $1,196.61 | $1,196.61 | $1,196.61 | $1,196.61 | $1,196.61 | $1,196.61 |
| 202 | Special 06. furnish and install dead-front gfci (SPV.0060) | EACH | 13 | $293.76 | $293.76 | $293.76 | $293.76 | $293.76 | $293.76 |
| 203 | Special 07. connect to existing storm sewer (SPV.0060) | EACH | 11 | $1,000.00 | $1,000.00 | $1,000.00 | $1,404.91 | $405.00 | $950.00 |
| 204 | Special 08. remove, salvage, and reinstall signs (SPV.0060) | EACH | 7 | $125.00 | $125.00 | $125.00 | $125.00 | $90.00 | $90.00 |
| 205 | Special 09. adjusting sanitary manhole covers (SPV.0060) | EACH | 19 | $1,000.00 | $1,000.00 | $1,356.00 | $1,984.65 | $1,737.00 | $880.00 |
| 206 | Special 10. adjusting water valve boxes (SPV.0060) | EACH | 32 | $400.00 | $400.00 | $407.00 | $555.50 | $441.00 | $300.00 |
| 207 | Special 11. adjusting water manhole covers (SPV.0060) | EACH | 3 | $1,000.00 | $1,000.00 | $728.00 | $1,051.41 | $597.00 | $600.00 |
| 208 | Special 12. evp equipment installation CTH O (S moorland RD) & W ryerson RD (SPV.0060) | EACH | 1 | $2,959.70 | $2,959.70 | $2,959.70 | $2,959.70 | $2,959.70 | $2,959.70 |
| 209 | Special 13. reinstall temporary evp equipment CTH O (S moorland RD) & W ryerson RD (SPV.0060) | EACH | 1 | $5,733.71 | $5,733.71 | $5,733.71 | $5,733.71 | $5,733.71 | $5,733.71 |
| 210 | Special 14. temporary video detection for intersections CTH O (S moorland RD) &W ryerson (SPV.0060) | EACH | 1 | $14,536 | $14,536 | $14,536 | $14,536 | $14,536 | $14,536 |
| 211 | Special 15. traffic signal controller and cabinet (SPV.0060) | EACH | 1 | $29,317 | $29,317 | $29,317 | $29,317 | $29,317 | $29,317 |
| 212 | Special 16. video vehicle detection system CTH O (S moorland RD) & W ryerson RD (SPV.0060) | EACH | 1 | $39,038 | $39,038 | $39,038 | $39,038 | $39,038 | $39,038 |
| 213 | Special 17. accessible pedestrian system CTH O (S moorland RD) & W coffee RD (SPV.0060) | EACH | 1 | $12,092 | $12,092 | $12,092 | $12,092 | $12,092 | $12,092 |
| 214 | Special 18. relocating hydrant (SPV.0060) | EACH | 4 | $5,000.00 | $5,000.00 | $8,555.00 | $8,445.62 | $5,570.00 | $5,845.00 |
| 215 | Special 19. reconstructing sanitary manholes (SPV.0060) | EACH | 2 | $2,000.00 | $2,000.00 | $1,536.00 | $4,559.14 | $4,250.00 | $2,835.00 |
| 216 | Special 22. posts tubular steel 1.75X1.75-inch X 13-FT (SPV.0060) | EACH | 40 | $165.00 | $165.00 | $165.00 | $165.00 | $200.00 | $200.00 |
| 217 | Special 23. posts tubular steel 1.75X1.75-inch X 14-FT (SPV.0060) | EACH | 72 | $165.00 | $165.00 | $165.00 | $165.00 | $200.00 | $200.00 |
| 218 | Special 24. sand bags (SPV.0060) | EACH | 50 | $50.00 | $25.00 | $25.00 | $25.00 | $19.00 | $19.00 |
| 219 | Special 25. drain tile sump connection (SPV.0060) | EACH | 25 | $1,000.00 | $1,000.00 | $980.00 | $876.68 | $497.00 | $550.00 |
| 220 | Special 26. section corner monuments (SPV.0060) | EACH | 1 | $1,500.00 | $1,000.00 | $1,500.00 | $0.01 | $1,522.00 | $1,000.00 |
| 221 | Special 27. reconnect evp system CTH O (S moorland RD) &W coffee RD (SPV.0060) | EACH | 1 | $1,540.38 | $1,540.38 | $1,540.38 | $1,540.38 | $1,540.38 | $1,540.38 |
| 222 | Special 28. spot repair existing storm sewer (SPV.0060) | EACH | 1 | $5,000.00 | $5,000.00 | $7,773.00 | $10,957 | $3,268.00 | $6,165.00 |
| 223 | Special 01. clean existing storm sewer (SPV.0090) | LF | 1,759 | $3.45 | $3.45 | $10.50 | $10.20 | $3.45 | $8.55 |
| 224 | Special 02. video detector cable (SPV.0090) | LF | 1,150 | $4.77 | $4.77 | $4.77 | $4.77 | $4.77 | $4.77 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.