WisDOT contract 20250408027 bid tabulation

Mequon Road, City of Mequon; Washington Co Line to Buntrock Ave (STH 167, Ozaukee County Mequon Road). Let by Wisconsin DOT on April 8, 2025, Ozaukee. 6 bids received; low bid $3,487,164 by Vinton Construction Company.

Owner
Wisconsin DOT
Letting
08 APR 2025
Pay items
210
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Vinton Construction Company$3,487,164Low
2Stark Pavement Corporation$3,530,000+1.0%
3Lalonde Contractors Incorporated$3,674,527+5.0%
4Zignego Company, Inc.$3,701,130+6.0%
5Zenith Tech., Inc. - Waukesha$3,822,084+10%
6Michels Road & Stone, Inc.$3,898,649+12%
WisDOT contract 20250408027: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Vinton Construction Company2. Stark Pavement Corporation3. Lalonde Contractors Incorporated4. Zignego Company, Inc.5. Zenith Tech., Inc. - Waukesha6. Michels Road & Stone, Inc.
1Grubbing (201.0205)STA8$349.00$527.50$349.00$1.00$250.00$250.00
2Removing small pipe culverts (203.0100)EACH1$1,285.00$500.00$500.00$1,500.00$1,120.00$1,120.00
3Debris containment over waterway (structure) 01. C-45-31 (203.0335)EACH1$4,144.00$4,144.00$4,144.00$4,144.00$4,144.00$4,144.00
4Removing concrete pavement (204.0100)SY793$9.88$9.80$18.26$20.00$17.90$17.90
5Removing asphaltic surface (204.0110)SY218$12.10$7.50$16.28$20.00$17.90$17.90
6Removing asphaltic surface butt joints (204.0115)SY110$3.20$3.20$3.20$3.20$11.35$3.20
7Removing asphaltic surface milling (204.0120)SY64,600$1.86$1.96$1.96$1.96$2.25$1.96
8Removing curb & gutter (204.0150)LF1,011$10.00$9.50$12.74$10.00$6.00$6.00
9Removing concrete sidewalk (204.0155)SY243$18.00$8.25$12.04$20.00$4.05$4.05
10Removing concrete bases (204.0195)EACH24$307.40$250.00$250.00$500.00$350.00$307.40
11Removing inlets (204.0220)EACH1$342.50$500.00$500.00$1,200.00$500.00$500.00
12Removing storm sewer (size) 01. 18-inch (204.0245)LF17$29.26$30.00$30.00$20.00$47.80$47.80
13Removing (item description) 01. retaining wall R-45-42 (204.9060.S)EACH1$4,500.00$3,109.90$6,848.00$5,000.00$1,270.00$1,270.00
14Removing (item description) 02. (traffic signals STH 167 & granville RD.) (204.9060.S)EACH1$4,304.67$5,000.00$5,000.00$5,000.00$6,500.00$4,304.67
15Removing (item description) 03. (traffic signals STH 167 & wasaukee RD.) (204.9060.S)EACH1$4,304.67$5,000.00$5,000.00$5,000.00$6,500.00$4,304.67
16Removing (item description) 04. (loop detector wire & lead-in cable STH 167 & granville RD.) (204.9060.S)EACH1$1,434.89$500.00$500.00$500.00$1,500.00$1,434.89
17Removing (item description) 05. (loop detector wire & lead-in cable STH 167 & granville RD.) (204.9060.S)EACH1$1,434.89$500.00$500.00$500.00$1,500.00$1,434.89
18Excavation common (205.0100)CY1,237$48.10$30.55$55.40$25.00$25.00$25.00
19Backfill granular grade 1 (209.1100)CY100$59.92$40.00$40.00$49.00$48.80$48.80
20Prepare foundation for asphaltic shoulders (211.0400)STA79$115.00$115.00$115.00$115.00$200.00$115.00
21Finishing roadway (project) 01. 1380-02-70 (213.0100)EACH1$2,000.00$4,000.00$3,056.00$1,000.00$1,883.90$5,000.00
22Base aggregate dense 3/4-inch (305.0110)TON1,000$30.00$23.20$30.71$0.01$30.45$30.45
23Base aggregate dense 1 1/4-inch (305.0120)TON3,140$0.01$24.25$29.66$0.01$30.45$30.45
24Shaping shoulders (305.0500)STA147$50.00$63.15$56.69$100.00$20.00$20.00
25Base patching concrete shes (390.0405)CY4$1,000.00$1,100.00$987.00$1,000.00$550.99$1,000.00
26Drilled tie bars (416.0610)EACH1,905$7.65$9.00$10.79$15.00$5.49$11.85
27Drilled dowel bars (416.0620)EACH7,587$13.75$12.00$13.54$15.00$11.65$18.70
28Concrete pavement repair (416.1710)SY3,009$83.82$82.00$92.37$108.00$102.37$102.84
29Concrete pavement repair shes (416.1715)SY100$185.00$110.00$197.82$250.00$139.19$118.68
30Concrete pavement replacement (416.1720)SY2,461$87.82$85.00$88.84$108.00$110.97$88.66
31Continuous diamond grinding concrete pavement (420.1000)SY24,022$6.70$6.63$5.27$5.27$7.50$5.27
32Tack coat (455.0605)GAL4,510$3.00$3.00$3.00$3.00$2.25$3.00
33Incentive density HMA pavement (460.2000)DOL3,029$1.00$1.00$1.00$1.00$1.00$1.00
34HMA pavement 3 MT 58-28 S (460.6223)TON223$136.00$136.00$136.00$136.00$122.00$136.00
35HMA pavement 4 MT 58-28 S (460.6224)TON7,049$69.90$69.90$69.90$69.90$68.25$69.90
36Asphaltic surface patching (465.0110)TON163$147.00$147.00$147.00$147.00$167.85$147.00
37Asphaltic surface driveways and field entrances (465.0120)TON44$147.00$147.00$147.00$147.00$105.00$147.00
38Concrete surface repair (509.1500)SF19$30.00$30.00$30.00$30.00$30.00$30.00
39Concrete collars for pipe (520.8000)EACH1$850.00$700.00$700.00$750.00$1,000.00$1,000.00
40Culvert pipe reinforced concrete class III 54-inch (522.0154)LF72$476.04$430.00$430.00$451.00$624.00$624.00
41Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH1$1,081.27$900.00$900.00$1,647.00$823.00$823.00
42Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH2$1,582.56$1,300.00$1,300.00$2,152.00$1,466.00$1,466.00
43Apron endwalls for culvert pipe reinforced concrete 54-inch (522.1054)EACH2$3,915.06$4,500.00$4,500.00$6,349.00$3,384.00$3,384.00
44Concrete curb & gutter 30-inch type A (601.0409)LF752$45.00$47.00$51.63$51.12$54.34$51.87
45Concrete curb & gutter 30-inch type D (601.0411)LF639$48.00$47.00$51.63$47.41$50.46$49.38
46Concrete sidewalk 5-inch (602.0410)SF25,552$5.95$7.00$5.71$4.53$4.90$5.48
47Curb ramp detectable warning field yellow (602.0505)SF120$35.00$50.00$43.87$32.96$34.49$55.86
48Curb ramp detectable warning field radial yellow (602.0605)SF202$50.00$55.00$63.26$48.26$50.51$61.38
49Concrete driveway 7-inch (602.0815)SY196$75.00$72.00$83.64$71.57$75.95$93.65
50Riprap medium (606.0200)CY1$100.00$1,950.00$841.00$1,000.00$500.00$200.00
51Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF37$110.13$75.00$75.00$103.00$79.50$79.50
52Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF130$142.96$90.00$90.00$115.00$89.70$89.70
53Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF12$148.94$95.00$95.00$116.00$91.50$91.50
54Reconstructing manholes (611.0420)EACH3$1,575.33$1,800.00$1,800.00$3,187.00$2,500.00$2,500.00
55Reconstructing inlets (611.0430)EACH22$972.73$2,000.00$2,000.00$2,550.00$2,500.00$2,500.00
56Manhole covers type J (611.0530)EACH1$467.78$900.00$900.00$1,205.00$1,210.00$1,210.00
57Inlet covers type H (611.0624)EACH1$691.44$1,250.00$1,250.00$1,205.00$1,442.00$1,442.00
58Inlet covers type MS (611.0642)EACH1$477.28$725.00$725.00$1,205.00$955.00$955.00
59Manholes 4-FT diameter (611.2004)EACH1$4,406.99$4,700.00$4,700.00$3,721.00$3,000.00$3,000.00
60Inlets 4-FT diameter (611.3004)EACH1$4,375.34$4,500.00$4,500.00$3,497.00$3,000.00$3,000.00
61Inlets median 1 grate (611.3901)EACH1$3,048.44$3,600.00$3,600.00$2,902.00$2,500.00$2,500.00
62Adjusting manhole covers (611.8110)EACH4$510.00$900.00$900.00$1,182.00$1,620.00$1,620.00
63Adjusting inlet covers (611.8115)EACH15$476.00$950.00$950.00$1,182.00$1,620.00$1,620.00
64Cover plates temporary (611.8120.S)EACH7$346.71$400.00$400.00$900.00$350.00$350.00
65Barrier system grading shaping finishing (614.0010)EACH1$7,000.00$4,100.00$1,500.00$11,500$2,500.00$6,600.00
66Adjusting steel plate beam guard (614.0400)LF100$10.00$12.90$12.00$12.00$16.00$12.90
67Replacing guardrail posts and blocks (614.0950)EACH7$100.00$115.00$125.00$125.00$100.00$115.00
68Replacing guardrail rail and hardware (614.0951)LF100$25.00$25.00$25.00$25.00$12.00$25.00
69Fence safety (616.0700.S)LF500$1.00$4.00$3.35$3.35$3.50$4.00
70Maintenance and repair of haul roads (project) 01. 1380-02-70 (618.0100)EACH1$0.01$1,500.00$1.00$1.00$1.00$1.00
71Mobilization (619.1000)EACH1$147,000$89,913$107,814$189,000$146,172$329,196
72Concrete median sloped nose (620.0300)SF107$15.00$25.00$16.90$14.85$15.87$18.13
73Water (624.0100)MGAL30$30.00$85.00$54.00$50.00$75.00$75.00
74Topsoil (625.0100)SY6,688$6.37$7.00$4.80$4.80$8.00$8.00
75Mulching (627.0200)SY6,688$0.01$0.31$0.38$0.38$0.25$0.31
76Erosion bales (628.1104)EACH100$0.01$11.25$10.00$10.00$16.00$11.25
77Silt fence (628.1504)LF1,579$2.10$1.64$1.95$1.95$2.50$1.64
78Silt fence maintenance (628.1520)LF1,579$0.01$0.05$0.01$0.01$0.10$0.05
79Mobilizations erosion control (628.1905)EACH4$50.00$150.00$150.00$150.00$250.00$150.00
80Mobilizations emergency erosion control (628.1910)EACH6$0.01$90.00$150.00$150.00$300.00$90.00
81Erosion mat urban class I type A (628.2006)SY5,830$2.00$1.69$1.70$1.70$1.80$1.69
82Erosion mat urban class I type B (628.2008)SY858$2.00$1.71$1.75$1.75$1.85$1.71
83Inlet protection type A (628.7005)EACH13$50.00$89.10$95.00$95.00$125.00$89.10
84Inlet protection type B (628.7010)EACH5$50.00$38.50$50.00$50.00$50.00$38.50
85Inlet protection type D (628.7020)EACH210$110.00$65.00$70.00$70.00$125.00$65.00
86Culvert pipe checks (628.7555)EACH13$20.00$38.10$16.00$16.00$20.00$38.10
87Rock bags (628.7570)EACH100$1.00$8.00$10.00$10.00$20.00$8.00
88Fertilizer type B (629.0210)CWT9$80.00$79.50$80.00$80.00$80.00$79.50
89Seeding mixture no. 30 (630.0130)LB304$9.00$8.50$7.95$7.95$8.50$8.50
90Seeding temporary (630.0200)LB182$3.00$3.25$2.95$2.95$5.00$3.25
91Seed water (630.0500)MGAL150$10.00$10.00$12.00$12.00$25.00$10.00
92Posts wood 4X6-inch X 18-FT (634.0618)EACH38$140.00$88.50$105.00$105.00$125.00$88.50
93Signs type II reflective H (637.2210)SF379.68$22.00$19.50$20.00$20.00$28.00$19.50
94Signs type II reflective H folding (637.2215)SF104.52$30.00$23.90$28.00$28.00$32.00$23.90
95Signs type II reflective F (637.2230)SF220$24.00$18.45$22.00$22.00$28.00$18.45
96Moving signs type II (638.2102)EACH49$90.00$75.00$90.00$90.00$75.00$75.00
97Removing small sign supports (638.3000)EACH18$20.00$18.50$28.00$28.00$35.00$18.50
98Field office type B (642.5001)EACH1$10,000$9,000.00$26,210$20,000$14,012$26,000
99Traffic control drums (643.0300)DAY29,703$0.18$0.18$0.18$0.10$0.18$0.18
100Traffic control barricades type III (643.0420)DAY10,019$0.40$0.40$0.40$0.25$0.40$0.40
101Traffic control warning lights type A (643.0705)DAY20,038$0.10$0.10$0.10$0.05$0.10$0.10
102Traffic control warning lights type C (643.0715)DAY1,033$0.46$0.46$0.46$0.10$0.46$0.46
103Traffic control arrow boards (643.0800)DAY28$25.00$25.00$25.00$8.00$25.00$25.00
104Traffic control signs (643.0900)DAY42,547$0.21$0.21$0.21$0.20$0.21$0.21
105Traffic control covering signs type II (643.0920)EACH10$46.33$46.33$46.33$50.00$46.33$46.33
106Traffic control signs fixed message (643.1000)SF105$22.00$22.00$22.00$15.00$22.00$22.00
107Traffic control signs PCMS (643.1050)DAY128$45.00$45.00$45.00$25.00$45.00$45.00
108Traffic control cones 42-inch (643.1070)DAY298$2.67$2.67$2.67$1.00$2.67$2.67
109Temporary marking line removable tape 6-inch (643.3180)LF7,495$2.26$2.26$2.26$1.60$2.26$2.26
110Temporary marking crosswalk removable tape 6-inch (643.3350)LF809$3.11$3.11$3.11$1.95$3.11$3.11
111Traffic control (643.5000)EACH1$17,000$17,000$17,000$22,232$17,000$17,000
112Temporary pedestrian surface asphalt (644.1410)SF2,752$0.01$6.75$8.67$5.00$8.00$6.75
113Temporary pedestrian curb ramp (644.1601)DAY665$3.75$3.75$3.75$5.00$3.75$3.75
114Temporary pedestrian detectable warning field (644.1605)SF360$5.70$5.70$5.70$50.00$5.70$5.70
115Temporary pedestrian barricade (644.1810)LF3,584$2.00$2.00$2.00$3.50$2.00$2.00
116Geotextile type HR (645.0120)SY52$10.00$10.00$8.16$10.00$20.00$10.00
117Marking line epoxy 4-inch (646.1020)LF3,016$0.34$0.70$0.80$0.34$0.34$0.34
118Marking line epoxy 6-inch (646.2020)LF466$0.44$0.90$0.90$0.44$0.44$0.44
119Marking line grooved black epoxy 6-inch (646.2025)LF4,549$1.95$1.00$1.40$1.95$1.95$1.95
120Marking line grooved wet ref epoxy 6-inch (646.2040)LF82,878$1.20$1.27$1.60$1.20$1.20$1.20
121Marking line epoxy 8-inch (646.3020)LF1,058$0.87$1.50$1.20$0.87$0.87$0.87
122Marking line grooved wet ref epoxy 10-inch (646.4040)LF8,362$2.47$2.75$3.20$2.47$2.47$2.47
123Marking arrow epoxy (646.5020)EACH61$288.23$220.00$320.00$288.23$288.23$288.23
124Marking word epoxy (646.5120)EACH16$331.26$240.00$350.00$331.26$331.26$331.26
125Marking stop line epoxy 18-inch (646.6120)LF758$12.27$13.00$16.50$12.27$12.27$12.27
126Marking yield line epoxy 18-inch (646.6220)EACH57$28.83$65.00$95.00$28.83$28.83$28.83
127Marking diagonal epoxy 12-inch (646.7120)LF1,866$11.77$10.00$8.00$11.77$11.77$11.77
128Marking crosswalk epoxy transverse line 6-inch (646.7420)LF1,865$11.39$10.00$13.00$11.39$11.39$11.39
129Marking crosswalk epoxy block style 24-inch (646.7520)LF114$19.88$17.50$22.00$19.88$19.88$19.88
130Marking corrugated median epoxy (646.8020)SF2,304$7.05$7.50$5.00$7.05$7.05$7.05
131Marking curb epoxy (646.8120)LF310$5.79$8.25$6.00$5.79$5.79$5.79
132Marking island nose epoxy (646.8220)EACH26$227.32$275.00$275.00$227.32$227.32$227.32
133Construction staking storm sewer (650.4000)EACH3$55.55$125.00$55.55$55.55$55.55$55.55
134Construction staking curb gutter and curb & gutter (650.5500)LF619$0.67$1.50$0.67$0.67$0.67$0.67
135Construction staking pipe culverts (650.6000)EACH1$150.00$200.00$150.00$150.00$150.00$150.00
136Construction staking resurfacing reference (650.8000)LF20,186$0.11$0.29$0.11$0.11$0.11$0.11
137Construction staking electrical installations (project) 01. 1380-02- 70 (650.8501)EACH1$5,495.94$3,200.00$5,495.94$5,495.94$5,495.94$5,495.94
138Construction staking curb ramps (650.9000)EACH23$175.00$200.00$175.00$175.00$175.00$175.00
139Construction staking sidewalk (project) 01. 1380-02-70 (650.9500)EACH1$3,423.97$4,000.00$3,423.97$3,423.97$3,423.97$3,423.97
140Construction staking supplemental control (project) 01. 1380-02-70 (650.9911)EACH1$533.96$1,850.00$533.96$533.96$533.96$533.96
141Construction staking slope stakes (650.9920)LF4,789$0.87$1.00$0.87$0.87$0.87$0.87
142Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF1,506$7.51$8.00$8.00$8.00$7.80$7.51
143Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF1,283$9.81$10.00$10.00$10.00$15.00$9.81
144Conduit special 2-inch (652.0605)LF1,380$18.22$25.00$25.00$25.00$25.00$18.22
145Conduit special 3-inch (652.0615)LF1,557$27.09$26.00$26.00$26.00$45.00$27.09
146Conduit loop detector (652.0800)LF3,440$6.43$7.00$7.00$7.00$8.00$6.43
147Pull boxes steel 24X36-inch (653.0135)EACH10$1,333.45$900.00$900.00$900.00$1,200.00$1,333.45
148Pull boxes steel 24X42-inch (653.0140)EACH31$1,249.64$1,100.00$1,100.00$1,100.00$1,300.00$1,249.64
149Removing pull boxes (653.0905)EACH33$128.04$200.00$200.00$200.00$200.00$128.04
150Concrete bases type 1 (654.0101)EACH8$966.11$750.00$750.00$750.00$1,200.00$966.11
151Concrete bases type 2 (654.0102)EACH4$1,535.88$1,300.00$1,300.00$1,300.00$1,380.00$1,535.88
152Concrete bases type 10 (654.0110)EACH2$6,810.75$8,600.00$8,600.00$8,600.00$8,500.00$6,810.75
153Concrete bases type 10-special (654.0120)EACH6$8,870.66$12,000$12,000$12,000$10,000$8,870.66
154Concrete control cabinet bases type 9 special (654.0217)EACH2$2,756.11$2,200.00$2,200.00$2,200.00$2,200.00$2,756.11
155Cable traffic signal 5-14 AWG (655.0230)LF905$1.62$1.50$1.50$1.50$1.50$1.62
156Cable traffic signal 7-14 AWG (655.0240)LF632$2.09$2.25$2.25$2.25$1.81$2.09
157Cable traffic signal 12-14 AWG (655.0260)LF4,747$3.16$3.25$3.25$3.25$2.80$3.16
158Cable traffic signal 15-14 AWG (655.0270)LF317$3.69$5.50$5.50$5.50$3.60$3.69
159Cable type UF 2-10 AWG grounded (655.0320)LF1,658$1.99$2.10$2.10$2.10$2.00$1.99
160Electrical wire traffic signals 10 AWG (655.0515)LF2,805$1.20$1.30$1.30$1.30$1.05$1.20
161Electrical wire lighting 12 AWG (655.0610)LF1,728$1.03$1.00$1.00$1.00$0.95$1.03
162Loop detector lead in cable (655.0700)LF11,660$1.71$1.90$1.90$1.90$1.35$1.71
163Loop detector wire (655.0800)LF8,166$1.29$1.40$1.40$1.40$0.95$1.29
164Traffic signal evp detector cable (655.0900)LF1,928$2.14$2.00$2.00$2.00$2.00$2.14
165Electrical service meter breaker pedestal (location) 01. STH 167 & granville RD. (656.0201)EACH1$1,631.11$1,500.00$1,500.00$1,500.00$1,800.00$1,631.11
166Electrical service meter breaker pedestal (location) 02. STH 167 & wasaukee RD. (656.0201)EACH1$1,631.11$1,500.00$1,500.00$1,500.00$1,800.00$1,631.11
167Pedestal bases (657.0100)EACH8$336.49$275.00$275.00$275.00$260.00$336.49
168Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH4$785.95$650.00$650.00$650.00$610.00$785.95
169Poles type 3 (657.0310)EACH4$4,239.33$3,800.00$3,800.00$3,800.00$4,000.00$4,239.33
170Traffic signal standards aluminum 13-FT (657.0420)EACH2$982.11$900.00$900.00$900.00$656.00$982.11
171Traffic signal standards aluminum 15-FT (657.0425)EACH8$1,029.77$750.00$750.00$750.00$750.00$1,029.77
172Luminaire arms single member 4 1/2-inch clamp 6-FT (657.0610)EACH8$422.36$600.00$600.00$600.00$310.00$422.36
173Traffic signal face 3S 12-inch (658.0173)EACH24$935.15$800.00$800.00$800.00$720.00$935.15
174Traffic signal face 4S 12-inch (658.0174)EACH16$1,207.93$1,100.00$1,100.00$1,100.00$1,050.00$1,207.93
175Signal mounting hardware (location) 01. (STH 167 & granville RD.) (658.5070)EACH1$6,761.55$6,310.00$6,310.00$6,310.00$3,000.00$6,761.55
176Signal mounting hardware (location) 02. (STH 167 & wasaukee RD.) (658.5070)EACH1$5,488.36$5,385.00$5,385.00$5,385.00$3,800.00$5,488.36
177Luminaires utility LED C (659.1125)EACH12$903.06$400.00$400.00$400.00$255.00$903.06
178Lamp, ballast, LED, switch disposal by contractor (659.5000.S)EACH54$28.70$125.00$125.00$125.00$75.00$28.70
179Temporary traffic signals for intersections (location) 01. (STH 167 & granville RD.) (661.0201)EACH1$56,757$49,000$49,000$49,000$45,000$56,757
180Temporary traffic signals for intersections (location) 02. (STH 167 & wausakee RD.) (661.0201)EACH1$56,757$48,000$49,000$49,000$45,000$56,757
181Generators (661.0300)DAY2$935.50$300.00$300.00$300.00$500.00$935.50
182Install camera assembly (677.0200)EACH2$8,636.57$8,000.00$8,000.00$8,000.00$7,500.00$8,636.57
183Sawing asphalt (690.0150)LF2,376$1.39$1.39$1.10$1.10$1.39$1.39
184Sawing concrete (690.0250)LF15,590$1.85$1.85$2.00$2.00$1.85$1.85
185Incentive iri ride (740.0440)DOL15,293$1.00$1.00$1.00$1.00$1.00$1.00
186On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,200$5.00$5.00$5.00$5.00$5.00$5.00
187On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS4,320$5.00$5.00$5.00$5.00$5.00$5.00
188Special 01. transp & install state furnished traf sig cabinet at STH 167 & granville RD (SPV.0060)EACH1$3,587.22$8,500.00$8,500.00$8,500.00$2,000.00$3,587.22
189Special 02. transp & install state furnished traf sig cabinet at STH 167 & wasaukee RD (SPV.0060)EACH1$3,587.22$8,500.00$8,500.00$8,500.00$2,000.00$3,587.22
190Special 03. remove & install wireless communication equipment at STH 167 & granville RD (SPV.0060)EACH1$9,467.20$2,000.00$2,000.00$2,000.00$6,000.00$9,467.20
191Special 04. remove & install wireless communication equipment at STH 167 & wasaukee RD (SPV.0060)EACH1$9,467.20$2,000.00$2,000.00$2,000.00$6,000.00$9,467.20
192Special 06. cleaning manhole (SPV.0060)EACH12$250.00$500.00$500.00$500.00$175.00$175.00
193Special 07. cleaning inlet (SPV.0060)EACH59$169.49$300.00$300.00$500.00$175.00$175.00
194Special 08. adjusting city of mequon sanitary sewer manhole covers (SPV.0060)EACH2$1,150.00$1,800.00$1,675.76$3,191.00$2,000.00$2,000.00
195Special 09. adjusting mequon water utility water boxes (SPV.0060)EACH2$355.50$900.00$279.50$1,200.00$300.00$300.00
196Special 10. strapping (C-45-31) (SPV.0060)EACH1$3,700.00$3,700.00$3,700.00$3,700.00$3,700.00$3,700.00
197Special 11. temporary water diversion little menomonee creek (SPV.0060)EACH1$9,750.00$9,750.00$9,750.00$9,750.00$9,750.00$9,750.00
198Special 13. utility line opening (SPV.0060)EACH5$800.00$850.00$1,650.00$1,000.00$700.00$700.00
199Special 15. TRN & inst state furn evp det heads W/conf beacons at STH 167 & granville RD (SPV.0060)EACH1$2,624.67$1,800.00$1,800.00$1,800.00$4,500.00$2,624.67
200Special 16. TRN & inst state furn evp det heads W/conf beacons at STH 167 & wasaukee RD (SPV.0060)EACH1$2,624.67$1,800.00$1,800.00$1,800.00$4,500.00$2,624.67
201Special 17. transport & install state furnished luminaire arms steel 15- FT (SPV.0060)EACH4$697.87$500.00$500.00$500.00$450.00$697.87
202Special 18. transport & install state furnished poles type 9 special (SPV.0060)EACH4$1,493.17$2,000.00$2,000.00$2,000.00$2,200.00$1,493.17
203Special 19. transport & install state furnished poles type 10 (SPV.0060)EACH2$1,493.17$2,400.00$2,400.00$2,400.00$2,200.00$1,493.17
204Special 20. transport & install state furnished poles type 10 special (SPV.0060)EACH2$1,493.17$2,500.00$2,500.00$2,500.00$3,500.00$1,493.17
205Special 21. transport & install state furnished monotube arms 30-FT (SPV.0060)EACH2$1,659.57$1,800.00$1,800.00$1,800.00$3,500.00$1,659.57
206Special 22. transport & install state furnished monotube arms 40-FT special (SPV.0060)EACH1$1,659.57$2,000.00$2,000.00$2,000.00$4,500.00$1,659.57
207Special 23. transport & install state furnished monotube arms 45-FT special (SPV.0060)EACH5$1,957.44$2,000.00$2,200.00$2,200.00$4,500.00$1,957.44
208Special 01. minor retaining wall cap replacement (SPV.0090)LF107$4.00$25.90$48.00$48.00$22.50$25.90
209Special 01. coarse aggregate mix for stream bed (SPV.0195)TON14$194.78$60.00$60.00$500.00$168.00$100.00
210Special 02. asphaltic repair (SPV.0195)TON1,476$91.10$91.10$91.10$91.10$115.00$91.10
WisDOT contract 20250408027: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way