C Milwaukee W Morgan Avenue; Ints W/ 20th, 16th, 13th & 6th St (LOC STR, Milwaukee County C Milwaukee, W Morgan Avenue). Let by Wisconsin DOT on April 8, 2025, Milwaukee. 3 bids received; low bid $2,427,145 by Lalonde Contractors Incorporated.
- Owner
- Wisconsin DOT
- Letting
- 08 APR 2025
- Pay items
- 156
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lalonde Contractors Incorporated | $2,427,145 | Low |
| 2 | Zenith Tech., Inc. - Waukesha | $2,555,228 | +5.0% |
| 3 | Zignego Company, Inc. | $2,654,423 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lalonde Contractors Incorporated | 2. Zenith Tech., Inc. - Waukesha | 3. Zignego Company, Inc. |
|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 770 | $27.88 | $25.00 | $20.00 |
| 2 | Removing curb & gutter (204.0150) | LF | 180 | $17.69 | $24.00 | $20.00 |
| 3 | Removing concrete sidewalk (204.0155) | SY | 707 | $18.05 | $17.00 | $20.00 |
| 4 | Removing concrete bases (204.0195) | EACH | 24 | $250.00 | $525.81 | $500.00 |
| 5 | Removing (item description) 301. lighting units (204.9060.S) | EACH | 41 | $920.00 | $706.35 | $706.35 |
| 6 | Excavation common (205.0100) | CY | 169.40 | $71.81 | $60.00 | $50.00 |
| 7 | Excavation, hauling, and disposal of petroleum contaminated soil (205.0501.S) | TON | 30.50 | $193.14 | $130.00 | $200.00 |
| 8 | Finishing roadway (project) 001. 2984-21-73 (213.0100) | EACH | 1 | $3,808.00 | $3,269.03 | $1,000.00 |
| 9 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 225 | $51.05 | $55.00 | $50.00 |
| 10 | Concrete base 8-inch (320.0145) | SY | 206 | $85.06 | $86.87 | $150.00 |
| 11 | Concrete pavement 8-inch (415.0080) | SY | 41 | $130.01 | $113.68 | $150.00 |
| 12 | Drilled tie bars (416.0610) | EACH | 461 | $24.23 | $11.39 | $30.00 |
| 13 | Drilled dowel bars (416.0620) | EACH | 181 | $28.86 | $25.71 | $30.00 |
| 14 | Asphaltic surface (465.0105) | TON | 27 | $394.00 | $388.89 | $394.00 |
| 15 | Concrete curb & gutter 31-inch (601.0331) | LF | 861 | $66.12 | $67.42 | $75.00 |
| 16 | Concrete curb pedestrian (601.0600) | LF | 196 | $67.15 | $26.30 | $75.00 |
| 17 | Concrete sidewalk 5-inch (602.0410) | SF | 5,670 | $9.58 | $14.06 | $17.00 |
| 18 | Curb ramp detectable warning field natural patina (602.0515) | SF | 274 | $52.07 | $30.84 | $50.00 |
| 19 | Curb ramp detectable warning field radial natural patina (602.0615) | SF | 158 | $72.73 | $45.52 | $100.00 |
| 20 | Adjusting inlet covers (611.8115) | EACH | 1 | $811.00 | $1,500.00 | $2,000.00 |
| 21 | Mobilization (619.1000) | EACH | 1 | $109,084 | $147,752 | $227,000 |
| 22 | Concrete median sloped nose (620.0300) | SF | 401 | $18.46 | $21.65 | $20.00 |
| 23 | Topsoil (625.0100) | SY | 221 | $5.95 | $10.00 | $5.95 |
| 24 | Mobilizations erosion control (628.1905) | EACH | 2 | $200.00 | $100.00 | $200.00 |
| 25 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $200.00 | $10.00 | $200.00 |
| 26 | Inlet protection type A (628.7005) | EACH | 3 | $105.00 | $50.00 | $105.00 |
| 27 | Inlet protection type D (628.7020) | EACH | 41 | $95.00 | $125.00 | $95.00 |
| 28 | Sod lawn (631.1000) | SY | 221 | $9.95 | $25.00 | $9.95 |
| 29 | Field office type C (642.5201) | EACH | 1 | $16,468 | $13,609 | $20,000 |
| 30 | Traffic control drums (643.0300) | DAY | 33,300 | $0.10 | $0.18 | $0.10 |
| 31 | Traffic control barricades type II (643.0410) | DAY | 2,700 | $0.25 | $0.15 | $0.25 |
| 32 | Traffic control barricades type III (643.0420) | DAY | 1,980 | $0.25 | $0.55 | $0.25 |
| 33 | Traffic control warning lights type A (643.0705) | DAY | 3,960 | $0.08 | $0.12 | $0.08 |
| 34 | Traffic control warning lights type C (643.0715) | DAY | 1,560 | $0.10 | $0.12 | $0.10 |
| 35 | Traffic control arrow boards (643.0800) | DAY | 240 | $5.00 | $12.50 | $5.00 |
| 36 | Traffic control signs (643.0900) | DAY | 11,220 | $0.25 | $0.16 | $0.25 |
| 37 | Traffic control covering signs type II (643.0920) | EACH | 5 | $50.00 | $95.00 | $50.00 |
| 38 | Traffic control signs PCMS (643.1050) | DAY | 56 | $35.00 | $22.50 | $35.00 |
| 39 | Temporary marking line removable tape 4-inch (643.3150) | LF | 16,144 | $1.30 | $1.40 | $1.30 |
| 40 | Temporary marking crosswalk removable tape 6-inch (643.3350) | LF | 1,013 | $1.95 | $2.15 | $1.95 |
| 41 | Traffic control (643.5000) | EACH | 1 | $21,000 | $21,000 | $21,000 |
| 42 | Temporary pedestrian surface asphalt (644.1410) | SF | 98 | $36.48 | $1.00 | $10.00 |
| 43 | Temporary pedestrian curb ramp (644.1601) | DAY | 540 | $8.00 | $7.00 | $20.00 |
| 44 | Temporary pedestrian detectable warning field (644.1605) | SF | 170 | $12.00 | $6.50 | $50.00 |
| 45 | Temporary pedestrian barricade (644.1810) | LF | 1,132 | $4.00 | $5.25 | $4.00 |
| 46 | Marking line epoxy 4-inch (646.1020) | LF | 7,557 | $1.45 | $0.40 | $1.45 |
| 47 | Marking line epoxy 6-inch (646.2020) | LF | 4,100 | $2.25 | $0.50 | $2.25 |
| 48 | Marking line epoxy 8-inch (646.3020) | LF | 1,256 | $2.95 | $1.05 | $2.95 |
| 49 | Marking arrow epoxy (646.5020) | EACH | 36 | $95.00 | $340.25 | $95.00 |
| 50 | Marking word epoxy (646.5120) | EACH | 12 | $125.00 | $391.00 | $125.00 |
| 51 | Marking symbol epoxy (646.5220) | EACH | 17 | $105.00 | $328.80 | $105.00 |
| 52 | Marking stop line epoxy 12-inch (646.6020) | LF | 1,786 | $4.45 | $13.90 | $4.45 |
| 53 | Marking yield line epoxy 18-inch (646.6220) | EACH | 59 | $6.65 | $34.05 | $6.65 |
| 54 | Marking removal line water blasting 4-inch (646.9010) | LF | 4,734 | $0.40 | $0.40 | $0.40 |
| 55 | Marking removal line water blasting 6-inch (646.9012) | LF | 37 | $5.00 | $1.00 | $5.00 |
| 56 | Marking removal line water blasting 8-inch (646.9110) | LF | 1,085 | $0.90 | $1.10 | $0.90 |
| 57 | Marking removal line water blasting wide (646.9210) | LF | 2,744 | $2.00 | $2.50 | $2.00 |
| 58 | Marking removal special marking water blasting (646.9310) | EACH | 22 | $95.00 | $175.00 | $95.00 |
| 59 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 861 | $1.50 | $1.16 | $4.45 |
| 60 | Construction staking electrical installations (project) 001. 2984-21- 73 (650.8501) | EACH | 1 | $5,000.00 | $1,650.00 | $5,700.00 |
| 61 | Construction staking curb ramps (650.9000) | EACH | 36 | $165.00 | $325.00 | $145.00 |
| 62 | Construction staking sidewalk (project) 001. 2984-21-73 (650.9500) | EACH | 1 | $5,000.00 | $2,500.00 | $2,160.00 |
| 63 | Construction staking supplemental control (project) 001. 2984-21-73 (650.9911) | EACH | 1 | $5,000.00 | $1,500.00 | $2,100.00 |
| 64 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 285 | $12.35 | $14.48 | $14.48 |
| 65 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 1,545 | $17.55 | $15.82 | $15.82 |
| 66 | Conduit special 3-inch (652.0615) | LF | 2,895 | $28.90 | $31.38 | $31.38 |
| 67 | Removing pull boxes (653.0905) | EACH | 6 | $300.00 | $109.43 | $109.43 |
| 68 | Concrete bases type 1 (654.0101) | EACH | 22 | $1,140.00 | $1,093.62 | $1,093.62 |
| 69 | Concrete bases type 5 (654.0105) | EACH | 9 | $1,350.00 | $1,203.94 | $1,203.94 |
| 70 | Concrete bases type 10 (654.0110) | EACH | 9 | $7,500.00 | $6,597.11 | $6,597.11 |
| 71 | Concrete bases type 10-special (654.0120) | EACH | 6 | $9,500.00 | $8,206.81 | $8,206.81 |
| 72 | Cable traffic signal 5-14 AWG (655.0230) | LF | 3,720 | $2.85 | $1.84 | $1.84 |
| 73 | Cable traffic signal 7-14 AWG (655.0240) | LF | 90 | $3.20 | $3.33 | $3.33 |
| 74 | Cable traffic signal 9-14 AWG (655.0250) | LF | 595 | $3.60 | $4.18 | $4.18 |
| 75 | Cable traffic signal 12-14 AWG (655.0260) | LF | 185 | $4.20 | $4.18 | $4.18 |
| 76 | Cable traffic signal 15-14 AWG (655.0270) | LF | 2,065 | $5.00 | $4.81 | $4.81 |
| 77 | Cable traffic signal 19-14 AWG (655.0280) | LF | 1,850 | $5.70 | $5.92 | $5.92 |
| 78 | Cable type UF 2-12 AWG grounded (655.0305) | LF | 5,630 | $2.30 | $1.00 | $1.00 |
| 79 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 2,430 | $1.15 | $2.60 | $2.60 |
| 80 | Traffic signal evp detector cable (655.0900) | LF | 2,725 | $1.05 | $1.70 | $1.70 |
| 81 | Pedestal bases (657.0100) | EACH | 22 | $665.00 | $386.24 | $386.24 |
| 82 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 9 | $980.00 | $706.86 | $706.86 |
| 83 | Poles type 9 (657.0345) | EACH | 1 | $9,956.00 | $8,762.45 | $8,762.45 |
| 84 | Poles type 10 (657.0350) | EACH | 9 | $10,890 | $10,730 | $10,730 |
| 85 | Poles type 10-special (657.0352) | EACH | 6 | $12,995 | $13,188 | $13,188 |
| 86 | Traffic signal standards aluminum 3.5-FT (657.0405) | EACH | 3 | $565.00 | $483.53 | $483.53 |
| 87 | Traffic signal standards aluminum 13-FT (657.0420) | EACH | 15 | $975.00 | $909.21 | $909.21 |
| 88 | Traffic signal standards aluminum 10-FT (657.0430) | EACH | 4 | $900.00 | $854.28 | $854.28 |
| 89 | Monotube arms 15-FT (657.0515) | EACH | 2 | $4,890.00 | $4,020.36 | $4,020.36 |
| 90 | Monotube arms 25-FT (657.0525) | EACH | 2 | $5,195.00 | $4,552.67 | $4,552.67 |
| 91 | Monotube arms 30-FT (657.0530) | EACH | 6 | $5,990.00 | $5,752.80 | $5,752.80 |
| 92 | Monotube arms 35-FT-special (657.0536) | EACH | 2 | $6,810.00 | $7,177.40 | $7,177.40 |
| 93 | Monotube arms 40-FT-special (657.0541) | EACH | 2 | $6,900.00 | $7,302.44 | $7,302.44 |
| 94 | Monotube arms 45-FT-special (657.0546) | EACH | 2 | $6,990.00 | $7,414.63 | $7,414.63 |
| 95 | Traffic signal face 3S 12-inch (658.0173) | EACH | 74 | $995.00 | $1,002.69 | $1,002.69 |
| 96 | Traffic signal face 4S 12-inch (658.0174) | EACH | 2 | $1,675.00 | $1,306.52 | $1,306.52 |
| 97 | Pedestrian signal face 12-inch (658.0412) | EACH | 32 | $995.00 | $539.32 | $539.32 |
| 98 | Signal mounting hardware (location) 001. S. 20TH street (658.5070) | EACH | 1 | $6,155.00 | $4,270.65 | $4,270.65 |
| 99 | Signal mounting hardware (location) 002. S. 16TH street (658.5070) | EACH | 1 | $6,820.00 | $5,047.75 | $5,047.75 |
| 100 | Signal mounting hardware (location) 003. S. 13TH street (658.5070) | EACH | 1 | $6,820.00 | $5,047.75 | $5,047.75 |
| 101 | Signal mounting hardware (location) 004. S. 6TH. street (658.5070) | EACH | 1 | $6,750.00 | $4,965.95 | $4,965.95 |
| 102 | Lamp, ballast, LED, switch disposal by contractor (659.5000.S) | EACH | 41 | $25.00 | $29.19 | $29.19 |
| 103 | Temporary traffic signals for intersections (location) 001. S.20TH street (661.0201) | EACH | 1 | $17,500 | $51,105 | $51,105 |
| 104 | Temporary traffic signals for intersections (location) 002. S. 16TH street (661.0201) | EACH | 1 | $18,000 | $52,862 | $52,862 |
| 105 | Temporary traffic signals for intersections (location) 003. S.13TH. street (661.0201) | EACH | 1 | $21,500 | $55,495 | $55,495 |
| 106 | Temporary traffic signals for intersections (location) 004. S.6TH. street (661.0201) | EACH | 1 | $24,000 | $65,829 | $65,829 |
| 107 | Remove cable (674.0300) | LF | 4,830 | $2.00 | $2.54 | $2.54 |
| 108 | Sawing asphalt (690.0150) | LF | 56 | $1.20 | $1.20 | $3.52 |
| 109 | Sawing concrete (690.0250) | LF | 1,770 | $2.20 | $2.20 | $2.17 |
| 110 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 800 | $5.00 | $5.00 | $5.00 |
| 111 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 3,000 | $5.00 | $5.00 | $5.00 |
| 112 | Special 001. adjusting water valve boxes (SPV.0060) | EACH | 2 | $534.00 | $1,200.00 | $2,000.00 |
| 113 | Special 002. adjusting water manhole (SPV.0060) | EACH | 2 | $1,507.00 | $1,800.00 | $2,500.00 |
| 114 | Special 003. utility line opening (ulo) (SPV.0060) | EACH | 20 | $1,778.79 | $1,600.00 | $1.00 |
| 115 | Special 004. section corner monuments (SPV.0060) | EACH | 2 | $1,801.00 | $2,483.92 | $1,000.00 |
| 116 | Special 201. install city precast controller base (SPV.0060) | EACH | 4 | $1,250.00 | $1,246.21 | $1,246.21 |
| 117 | Special 203. concrete bases type 10 spread footing (SPV.0060) | EACH | 1 | $11,500 | $9,220.72 | $9,220.72 |
| 118 | Special 205. atc controller and cabinet installed (SPV.0060) | EACH | 4 | $37,500 | $36,460 | $36,460 |
| 119 | Special 215. electrical service pedestal (SPV.0060) | EACH | 3 | $3,350.00 | $1,779.90 | $1,779.90 |
| 120 | Special 218. EVP1 direction detector (SPV.0060) | EACH | 16 | $1,570.00 | $1,461.39 | $1,461.39 |
| 121 | Special 221. evp phase selector card 4 channel (SPV.0060) | EACH | 4 | $4,995.00 | $4,835.02 | $4,835.02 |
| 122 | Special 223. evp confirmation light (SPV.0060) | EACH | 16 | $189.00 | $539.63 | $539.63 |
| 123 | Special 225. vehicular video detection system 2 cameras (SPV.0060) | EACH | 1 | $34,700 | $33,241 | $33,241 |
| 124 | Special 243. remove traffic signals (20TH street) (SPV.0060) | EACH | 1 | $6,500.00 | $5,176.01 | $5,176.01 |
| 125 | Special 244. remove traffic signals (16TH street) (SPV.0060) | EACH | 1 | $7,000.00 | $5,176.01 | $5,176.01 |
| 126 | Special 245 remove traffic signals (13TH street) (SPV.0060) | EACH | 1 | $8,000.00 | $5,176.01 | $5,176.01 |
| 127 | Special 246 remove traffic signals (6TH street) (SPV.0060) | EACH | 1 | $8,500.00 | $6,538.17 | $6,538.17 |
| 128 | Special 267. pedestrian countdown signal face 12-inch (SPV.0060) | EACH | 32 | $1,370.00 | $539.32 | $539.32 |
| 129 | Special 268. voice instruction audible push button (SPV.0060) | EACH | 32 | $1,315.00 | $1,199.02 | $1,199.02 |
| 130 | Special 269. voice instruction audible control unit (SPV.0060) | EACH | 4 | $3,820.00 | $3,879.73 | $3,879.73 |
| 131 | Special 302. fiberglass/polymer concrete pull box 13"X24"X24" (SPV.0060) | EACH | 35 | $1,260.00 | $1,281.67 | $1,281.67 |
| 132 | Special 303. fiberglass/polymer concrete pull box 17"X30"X24" (SPV.0060) | EACH | 38 | $1,475.00 | $1,375.89 | $1,375.89 |
| 133 | Special 310. remove poles (SPV.0060) | EACH | 19 | $900.00 | $644.11 | $644.11 |
| 134 | Special 312. poles type A-26 (gray concrete, direct bury) (SPV.0060) | EACH | 3 | $3,990.00 | $3,794.40 | $3,794.40 |
| 135 | Special 325. pole 30-FT aluminum bolt down (SPV.0060) | EACH | 9 | $2,620.00 | $1,889.08 | $1,889.08 |
| 136 | Special 334. 40' wood poles (SPV.0060) | EACH | 29 | $1,216.00 | $2,836.89 | $2,836.89 |
| 137 | Special 338. primary or secondary riser (SPV.0060) | EACH | 23 | $890.00 | $784.34 | $784.34 |
| 138 | Special 343. submersible multitap 4-port pre-insulated connector (SPV.0060) | EACH | 69 | $120.00 | $204.37 | $204.37 |
| 139 | Special 345. luminaire arm single member 6-foot (SPV.0060) | EACH | 23 | $450.00 | $322.83 | $322.83 |
| 140 | Special 346. luminaire arm single member 6-foot wood pole mount (SPV.0060) | EACH | 21 | $225.00 | $322.83 | $322.83 |
| 141 | Special 347. luminaire arm single member 8-foot (special) (SPV.0060) | EACH | 6 | $1,274.00 | $792.17 | $792.17 |
| 142 | Special 353. equipment grounding electrode (SPV.0060) | EACH | 17 | $680.00 | $229.65 | $229.65 |
| 143 | Special 355. A21-26 city furnished mounting clamp (single bracket) (SPV.0060) | EACH | 3 | $500.00 | $583.78 | $583.78 |
| 144 | Special 375. luminaire utility 2LED (SPV.0060) | EACH | 13 | $445.00 | $668.62 | $668.62 |
| 145 | Special 376. luminaire utility 3LED (SPV.0060) | EACH | 49 | $445.00 | $668.62 | $668.62 |
| 146 | Special 881. inline 5A fast acting fuse with holder (SPV.0060) | EACH | 25 | $105.00 | $311.45 | $311.45 |
| 147 | Special 002. marking line 24-inch epoxy stop line (SPV.0090) | LF | 454 | $8.95 | $14.80 | $8.95 |
| 148 | Special 300. cable type 1#8 AWG 5KV concentric city furnished (SPV.0090) | LF | 1,580 | $4.89 | $6.01 | $6.01 |
| 149 | Special 301. electrical cable 1#6 primary linewire 5KV (SPV.0090) | LF | 1,900 | $6.40 | $7.08 | $7.08 |
| 150 | Special 302. electrical cable 3#6AL triplex (SPV.0090) | LF | 1,620 | $6.03 | $3.01 | $3.01 |
| 151 | Special 304. electrical cable 2#2/1#4 AL triplex (SPV.0090) | LF | 3,260 | $6.30 | $3.39 | $3.39 |
| 152 | Special 319. liquidtight flexible nonmetallic conduit 1 1/2INCH (SPV.0090) | LF | 900 | $14.75 | $7.69 | $7.69 |
| 153 | Special 323. electrical cable type 3#4/1#8 xlpe use-2 (SPV.0090) | LF | 290 | $17.50 | $10.36 | $10.36 |
| 154 | Special 324. electrical cable type 4#2/1#8 xlpe use-2 (SPV.0090) | LF | 3,110 | $16.10 | $9.03 | $9.03 |
| 155 | Special 325. conduit 3-inch HDPE schedule 40 (SPV.0090) | LF | 3,210 | $24.60 | $32.74 | $32.74 |
| 156 | Special 001. excavation, hauling and disposal of cvoc contaminated soil (SPV.0195) | TON | 5.50 | $487.92 | $350.00 | $200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.