WisDOT contract 20250513009 bid tabulation

1228-09-76. Let by Wisconsin DOT on May 13, 2025, Milwaukee. 4 bids received; low bid $4,431,169 by Lalonde Contractors Incorporated.

Owner
Wisconsin DOT
Letting
13 MAY 2025
Pay items
234
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Lalonde Contractors Incorporated$4,431,169Low
2Zignego Company, Inc.$4,476,630+1.0%
3Michels Road & Stone, Inc.$4,686,112+6.0%
4Zenith Tech., Inc. - Waukesha$4,853,769+10%
WisDOT contract 20250513009: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Lalonde Contractors Incorporated2. Zignego Company, Inc.3. Michels Road & Stone, Inc.4. Zenith Tech., Inc. - Waukesha
1Removing structure (structure) 01. B-40-265 (203.0220)EACH1$127,000$127,000$127,000$127,000
2Removing concrete pavement (204.0100)SY2,947$13.71$10.26$8.00$25.00
3Removing concrete surface partial depth (204.0109.S)SF206,253$0.15$0.15$0.15$0.15
4Removing asphaltic surface (204.0110)SY24$20.29$50.00$22.00$80.00
5Removing asphaltic surface milling (204.0120)SY34,020$6.86$6.86$6.86$6.86
6Removing curb & gutter (204.0150)LF235$16.07$20.00$11.00$25.00
7Removing concrete sidewalk (204.0155)SY704$16.71$20.00$11.00$20.00
8Removing guardrail (204.0165)LF500$3.90$4.00$4.00$4.00
9Removing fence (204.0170)LF300$4.50$4.50$4.50$4.50
10Removing concrete bases (204.0195)EACH20$350.67$500.00$350.67$350.67
11Removing (item description) 01. removing traffic signals street lighting, holt at 4TH (204.9060.S)EACH1$5,590.17$5,590.17$5,590.17$5,590.17
12Removing (item description) 02. removing traffic signals street lighting, 6TH at mineral (204.9060.S)EACH1$6,479.74$6,479.74$6,479.74$6,479.74
13Removing (item description) 03. removing loop detector wire and lead-in cable (204.9060.S)EACH1$1,067.49$1,067.49$1,067.49$1,067.49
14Excavation common (205.0100)CY1,476$28.33$18.00$21.00$65.00
15Finishing roadway (project) 01. 1228-09-76 (213.0100)EACH1$4,760.00$1,000.00$2,500.00$3,457.54
16Base aggregate dense 1 1/4-inch (305.0120)TON2,185$27.87$24.00$22.00$49.00
17Base aggregate open-graded (310.0110)TON12$20.00$50.00$20.00$45.00
18Select crushed material (312.0110)TON943$25.10$24.00$25.00$50.00
19Concrete base 8-inch (320.0145)SY220$78.30$100.00$101.00$89.37
20Removing pavement for base patching (390.0100)CY886$76.14$70.00$105.00$150.00
21Base patching concrete shes (390.0405)CY886$309.50$412.00$400.00$300.00
22Concrete pavement 9-inch (415.0090)SY385$148.14$111.00$122.00$134.66
23Concrete pavement approach slab hes (415.1410)SY40$559.21$300.00$475.00$413.74
24Drilled tie bars (416.0610)EACH857$13.42$20.00$16.00$9.89
25Drilled dowel bars (416.0620)EACH3,566$16.41$20.00$20.00$10.00
26Concrete pavement replacement shes (416.1725)SY315$221.52$180.00$187.00$192.89
27Tack coat (455.0605)GAL5,035$2.40$2.40$2.40$2.40
28Incentive density HMA pavement (460.2000)DOL5,470$1.00$1.00$1.00$1.00
29HMA pavement 3 MT 58-28 V (460.6623)TON3,779$111.50$111.50$111.50$111.50
30HMA pavement 4 MT 58-28 V (460.6624)TON4,753$123.50$123.50$123.50$123.50
31Asphaltic surface driveways and field entrances (465.0120)TON5$125.00$125.00$125.00$125.00
32Asphaltic surface temporary (465.0125)TON44$125.00$125.00$125.00$125.00
33Concrete masonry bridges (502.0100)CY38$2,610.00$2,610.00$2,610.00$2,610.00
34Protective surface treatment (502.3200)SY61$7.00$7.00$7.00$7.00
35Pigmented surface sealer reseal (502.3205)SY366$25.00$25.00$25.00$25.00
36Pigmented surface sealer (502.3210)SY34$20.00$20.00$20.00$20.00
37Protective surface treatment reseal (502.3215)SY749$10.00$10.00$10.00$10.00
38Prestressed girder type I 36-inch (503.0136)LF69$565.00$565.00$565.00$565.00
39Bar steel reinforcement HS coated structures (505.0600)LB7,407$2.12$2.12$2.12$2.12
40Bar couplers no. 8 (505.0908)EACH6$180.00$180.00$180.00$180.00
41Bearing pads elastomeric non- laminated (506.2605)EACH2$150.00$150.00$150.00$150.00
42Preparation decks type 1 (509.0301)SY1$350.00$350.00$350.00$350.00
43Sawing pavement deck preparation areas (509.0310.S)LF10$50.00$50.00$50.00$50.00
44Curb repair (509.1200)LF4$200.00$200.00$200.00$200.00
45Concrete surface repair (509.1500)SF41$230.00$230.00$230.00$230.00
46Concrete masonry deck repair (509.2100.S)CY1$4,500.00$4,500.00$4,500.00$4,500.00
47Polymer overlay (509.5100.S)SY3,504$37.94$37.94$37.94$37.94
48Epoxy injection crack repair (509.9025.S)LF194$80.00$80.00$80.00$80.00
49Cored holes 2-inch diameter (509.9026.S)EACH1$700.00$700.00$700.00$700.00
50Anchor assemblies poles on structures (531.8990)EACH1$1,851.78$1,851.78$1,851.78$1,852.75
51Concrete curb & gutter 19-inch (601.0319)LF15$48.00$100.00$45.00$75.86
52Concrete curb & gutter 31-inch (601.0331)LF1,269$52.48$36.00$45.00$55.11
53Concrete curb pedestrian (601.0600)LF301$52.90$36.00$67.00$51.66
54Concrete sidewalk 5-inch (602.0410)SF6,152$13.05$7.50$8.30$19.86
55Curb ramp detectable warning field yellow (602.0505)SF457$43.95$30.00$57.00$36.52
56Curb ramp detectable warning field radial yellow (602.0605)SF147$62.64$45.00$65.00$53.47
57Concrete driveway hes 6-inch (602.0860)SY29$100.04$100.00$136.00$73.71
58Concrete barrier temporary precast delivered (603.8000)LF250$22.00$22.00$22.00$22.00
59Concrete barrier temporary precast installed (603.8125)LF250$8.00$8.00$8.00$8.00
60Reconstructing catch basins (611.0410)EACH1$3,500.00$1,500.00$3,500.00$5,800.00
61Reconstructing inlets (611.0430)EACH2$3,200.00$1,500.00$3,200.00$5,800.00
62Adjusting manhole covers (611.8110)EACH1$3,500.00$1,000.00$3,500.00$2,000.00
63Adjusting inlet covers (611.8115)EACH7$2,000.00$1,000.00$2,000.00$1,700.00
64Pipe underdrain wrapped 6-inch (612.0406)LF100$25.00$30.00$25.00$45.00
65Crash cushions permanent (614.0800)EACH1$34,701$26,500$26,500$30,731
66MGS guardrail 3 (614.2300)LF450$27.90$30.00$30.00$30.00
67MGS guardrail terminal eat (614.2610)EACH1$3,600.00$3,800.00$3,800.00$3,800.00
68MGS guardrail terminal type 2 (614.2620)EACH1$3,800.00$3,000.00$3,000.00$3,000.00
69Fence chain link 6-FT (616.0206)LF1,090$39.70$39.70$39.70$42.15
70Gates chain link (width) 01. 22-FT (616.0329)EACH1$3,075.00$3,075.00$3,075.00$3,500.00
71Fence chain link salvaged 8-FT (616.0408)LF88$174.00$174.00$174.00$250.00
72Maintenance and repair of haul roads (project) 01. 1228-09-76 (618.0100)EACH1$1.00$1.00$0.01$1.00
73Mobilization (619.1000)EACH1$292,806$385,000$487,856$479,829
74Concrete median sloped nose (620.0300)SF158$17.28$20.00$18.00$38.21
75Water (624.0100)MGAL40$54.40$50.00$60.00$50.00
76Topsoil (625.0100)SY570$5.95$5.95$16.00$16.00
77Mulching (627.0200)SY150$2.00$0.50$0.50$0.50
78Mobilizations erosion control (628.1905)EACH4$150.00$250.00$250.00$250.00
79Mobilizations emergency erosion control (628.1910)EACH2$150.00$300.00$300.00$300.00
80Inlet protection type D (628.7020)EACH100$85.00$115.00$115.00$115.00
81Tracking pads (628.7560)EACH2$1,477.00$1,000.00$100.00$1.21
82Fertilizer type B (629.0210)CWT1$95.00$100.00$100.00$100.00
83Seeding temporary (630.0200)LB4$35.00$50.00$50.00$50.00
84Sod water (631.0300)MGAL17$50.00$100.00$100.00$100.00
85Sod lawn (631.1000)SY570$7.95$12.50$12.50$12.50
86Posts wood 4X6-inch X 14-FT (634.0614)EACH16$110.00$75.00$75.00$75.00
87Posts wood 4X6-inch X 16-FT (634.0616)EACH49$115.00$90.00$90.00$90.00
88Posts wood 4X6-inch X 18-FT (634.0618)EACH21$120.00$110.00$110.00$110.00
89Posts wood 4X6-inch X 20-FT (634.0620)EACH8$125.00$125.00$125.00$125.00
90Signs type II reflective H (637.2210)SF1,417.80$21.00$21.00$21.00$21.00
91Signs type II reflective H folding (637.2215)SF169.68$27.00$28.00$28.00$28.00
92Signs type II reflective F (637.2230)SF409.50$23.00$21.00$21.00$21.00
93Moving signs type II (638.2102)EACH7$110.00$75.00$75.00$75.00
94Removing signs type II (638.2602)EACH224$28.00$35.00$35.00$35.00
95Removing small sign supports (638.3000)EACH116$28.00$35.00$35.00$35.00
96Moving small sign supports (638.4000)EACH3$100.00$100.00$100.00$100.00
97Traffic control drums (643.0300)DAY31,273$0.10$0.10$0.10$0.10
98Traffic control barricades type III (643.0420)DAY2,642$0.45$0.45$0.45$0.45
99Traffic control warning lights type A (643.0705)DAY5,284$0.08$0.08$0.08$0.08
100Traffic control warning lights type C (643.0715)DAY5,335$0.08$0.08$0.08$0.08
101Traffic control arrow boards (643.0800)DAY453$12.00$12.00$12.00$12.00
102Traffic control signs (643.0900)DAY18,708$0.35$0.35$0.35$0.35
103Traffic control covering signs type I (643.0910)EACH8$175.00$175.00$175.00$175.00
104Traffic control covering signs type II (643.0920)EACH10$0.35$0.35$0.35$0.35
105Traffic control signs fixed message (643.1000)SF343$12.50$12.50$12.50$12.50
106Traffic control signs PCMS (643.1050)DAY453$20.00$20.00$20.00$20.00
107Traffic control cones 42-inch (643.1070)DAY1,738$0.10$0.10$0.10$0.10
108Temporary marking line paint 4- inch (643.3105)LF1,942$0.40$0.40$0.40$0.40
109Temporary marking line removable tape 6-inch (643.3180)LF2,892$1.20$1.20$1.20$1.20
110Temporary marking line paint 8- inch (643.3205)LF4,922$0.65$0.65$0.65$0.65
111Temporary marking arrow removable tape (643.3550)EACH2$65.00$65.00$65.00$65.00
112Temporary marking stop line paint 18-inch (643.3805)LF717$4.00$4.00$4.00$4.00
113Temporary marking removable mask out tape 6-inch (643.3960)LF80$3.00$3.00$3.00$3.00
114Traffic control interim lane closure (643.4100)EACH8$850.00$850.00$850.00$850.00
115Traffic control (643.5000)EACH1$77,740$77,740$77,740$77,740
116Temporary pedestrian curb ramp (644.1601)DAY88$4.00$20.00$4.00$4.00
117Temporary pedestrian detectable warning field (644.1605)SF70$2.00$50.00$2.00$2.00
118Temporary pedestrian barricade (644.1810)LF1,573$3.00$3.00$3.00$3.00
119Temporary audible message devices (644.1900.S)DAY2,384$1.50$1.50$1.50$1.50
120Geogrid type SR (645.0220)SY1,436$2.42$6.00$3.00$4.90
121Marking line epoxy 4-inch (646.1020)LF2,931$1.75$1.75$1.75$1.75
122Marking line grooved black epoxy 6-inch (646.2025)LF213$5.65$5.65$5.65$5.65
123Marking line grooved wet ref epoxy 6-inch (646.2040)LF20,522$2.10$2.10$2.10$2.10
124Marking line grooved permanent tape 6-inch (646.2050)LF213$15.55$15.55$15.55$15.55
125Marking line epoxy 8-inch (646.3020)LF1,356$3.50$3.50$3.50$3.50
126Marking line grooved black epoxy 10-inch (646.4025)LF172$10.50$10.50$10.50$10.50
127Marking line grooved wet ref epoxy 10-inch (646.4040)LF6,853$3.50$3.50$3.50$3.50
128Marking line grooved permanent tape 10-inch (646.4050)LF126$25.85$25.85$25.85$25.85
129Marking arrow epoxy (646.5020)EACH40$250.00$250.00$250.00$250.00
130Marking word epoxy (646.5120)EACH6$300.00$300.00$300.00$300.00
131Marking symbol epoxy (646.5220)EACH4$300.00$300.00$300.00$300.00
132Marking stop line epoxy 18-inch (646.6120)LF676$13.50$13.50$13.50$13.50
133Marking diagonal epoxy 12-inch (646.7120)LF78$12.50$12.50$12.50$12.50
134Marking chevron epoxy 24-inch (646.7220)LF731$15.00$15.00$15.00$15.00
135Marking crosswalk epoxy transverse line 6-inch (646.7420)LF48$20.00$20.00$20.00$20.00
136Marking curb epoxy (646.8120)LF240$10.00$10.00$10.00$10.00
137Marking island nose epoxy (646.8220)EACH5$300.00$300.00$300.00$300.00
138Marking removal line wide (646.9200)LF1,552$1.20$1.20$1.20$1.20
139Conduit rigid nonmetallic schedule 40 1-inch (652.0210)LF4$18.41$18.41$18.41$18.41
140Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF910$10.53$10.53$10.53$10.53
141Conduit rigid nonmetallic schedule 40 2 1/2-inch (652.0230)LF251$20.16$20.16$20.16$20.16
142Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF630$11.71$11.71$11.71$11.71
143Conduit special 2-inch (652.0605)LF425$29.22$29.22$29.22$29.22
144Conduit special 3-inch (652.0615)LF1,190$32.18$32.18$32.18$32.18
145Conduit loop detector (652.0800)LF2,250$15.68$15.68$15.68$15.68
146Pull boxes steel 24X36-inch (653.0135)EACH8$1,401.89$1,401.89$1,401.89$1,401.89
147Pull boxes steel 24X42-inch (653.0140)EACH23$1,467.40$1,467.40$1,467.40$1,467.40
148Junction boxes 18X12X6-inch (653.0222)EACH1$3,344.70$3,344.70$3,344.70$3,344.70
149Removing pull boxes (653.0905)EACH3$101.09$101.09$101.09$101.09
150Concrete bases type 1 (654.0101)EACH16$951.84$951.84$951.84$951.84
151Concrete bases type 2 (654.0102)EACH5$1,243.41$1,243.41$1,243.41$1,243.41
152Concrete bases type 10 (654.0110)EACH4$6,263.52$6,263.52$6,263.52$6,263.52
153Concrete bases type 10-special (654.0120)EACH3$9,589.39$9,589.39$9,589.39$9,589.39
154Concrete control cabinet bases type 9 special (654.0217)EACH2$2,166.23$2,166.23$2,166.23$2,166.23
155Cable traffic signal 3-14 AWG (655.0210)LF1,390$1.51$1.51$1.51$1.51
156Cable traffic signal 5-14 AWG (655.0230)LF1,100$1.86$1.86$1.86$1.86
157Cable traffic signal 7-14 AWG (655.0240)LF2,425$2.93$2.93$2.93$2.93
158Cable traffic signal 12-14 AWG (655.0260)LF2,405$4.04$4.04$4.04$4.04
159Cable type UF 2-12 AWG grounded (655.0305)LF1,075$1.97$1.97$1.97$1.97
160Electrical wire traffic signals 10 AWG (655.0515)LF3,800$2.23$2.23$2.23$2.23
161Electrical wire lighting 12 AWG (655.0610)LF1,450$0.77$0.77$0.77$0.77
162Loop detector lead in cable (655.0700)LF5,200$1.28$1.28$1.28$1.28
163Loop detector wire (655.0800)LF7,667$1.12$1.12$1.12$1.12
164Traffic signal evp detector cable (655.0900)LF1,390$1.58$1.58$1.58$1.58
165Electrical service meter breaker pedestal (location) 01. electrical service meter breaker pedestal, holt at 4TH (656.0201)EACH1$1,498.12$1,498.12$1,498.12$1,498.12
166Electrical service meter breaker pedestal (location) 02. electrical service meter breaker pedestal, mineral at 6TH (656.0201)EACH1$1,498.12$1,498.12$1,498.12$1,498.12
167Pedestal bases (657.0100)EACH16$373.07$373.07$373.07$373.07
168Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH5$655.98$655.98$655.98$655.98
169Poles type 3 (657.0310)EACH5$4,025.40$4,025.40$4,025.40$4,025.40
170Traffic signal standards aluminum 3.5-FT (657.0405)EACH5$455.02$455.02$455.02$455.02
171Traffic signal standards aluminum 13-FT (657.0420)EACH7$865.33$865.33$865.33$865.33
172Traffic signal standards aluminum 15-FT (657.0425)EACH3$905.06$905.06$905.06$905.06
173Traffic signal standards aluminum 10-FT (657.0430)EACH2$811.58$811.58$811.58$811.58
174Luminaire arms single member 4- inch clamp 6-FT (657.0609)EACH6$330.85$330.85$330.85$330.85
175Traffic signal face 3S 12-inch (658.0173)EACH25$911.29$911.29$911.29$911.29
176Traffic signal face 4S 12-inch (658.0174)EACH8$1,236.14$1,236.14$1,236.14$1,236.14
177Pedestrian signal face 16-inch (658.0416)EACH14$557.70$557.70$557.70$557.70
178Signal mounting hardware (location) 01. holt at 4TH (658.5070)EACH1$3,717.83$3,717.83$3,717.83$3,717.83
179Signal mounting hardware (location) 02. 6TH at mineral (658.5070)EACH1$4,258.88$4,258.88$4,258.88$4,258.88
180Luminaires utility LED C (659.1125)EACH10$477.22$477.22$477.22$477.22
181Temporary traffic signals for intersections (location) 01. holt at 4TH (661.0201)EACH1$45,805$45,805$45,805$45,805
182Temporary traffic signals for intersections (location) 02. 6TH at mineral (661.0201)EACH1$47,423$47,423$47,423$47,423
183Field system integrator (670.0101)EACH1$177.91$177.91$177.91$177.91
184Sawing asphalt (690.0150)LF1,875$2.23$2.23$5.00$1.75
185Sawing concrete (690.0250)LF10,509$2.28$2.28$5.00$2.35
186Incentive strength concrete structures (715.0502)DOL500$1.00$1.00$1.00$1.00
187Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00$1.00
188On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,200$5.00$5.00$5.00$5.00
189On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS4,800$5.00$5.00$5.00$5.00
190Special 01. cleaning and sealing concrete girder ends (SPV.0060)EACH11$550.00$550.00$550.00$550.00
191Special 02. embedded galvanic anodes (SPV.0060)EACH14$60.00$60.00$60.00$60.00
192Special 03. adjusting water boxes (SPV.0060)EACH13$434.00$500.00$700.00$350.00
193Special 05. blinders for type II signs (SPV.0060)EACH1$150.00$300.00$300.00$300.00
194Special 06. install wireless traffic sensor (SPV.0060)EACH26$582.97$582.97$582.97$582.97
195Special 07. remove pole and wire (SPV.0060)EACH18$385.04$385.04$385.04$385.04
196Special 08. remove traffic signal face (SPV.0060)EACH35$88.96$88.96$88.96$88.98
197Special 09. voice instruction audible pushbutton (SPV.0060)EACH1$3,430.93$3,430.93$3,430.93$3,430.93
198Special 10. temporary infrared evp system, holt at 4TH (SPV.0060)EACH1$3,003.53$3,003.53$3,003.53$3,003.53
199Special 11. temporary infrared evp system, 6TH at mineral (SPV.0060)EACH1$3,715.19$3,715.19$3,715.19$3,715.19
200Special 12. install type 9 pole (SPV.0060)EACH1$1,301.79$1,301.79$1,301.79$1,301.79
201Special 13. install type 10 pole (SPV.0060)EACH3$1,479.71$1,479.71$1,479.71$1,479.71
202Special 14. install type 9 special pole (SPV.0060)EACH2$1,301.79$1,301.79$1,301.79$1,301.79
203Special 15. install type 10 special pole (SPV.0060)EACH1$1,479.71$1,479.71$1,479.71$1,479.71
204Special 16. install monotube arms 30-FT (SPV.0060)EACH4$1,888.12$1,888.12$1,888.12$1,888.12
205Special 17. install monotube arms 40-FT special (SPV.0060)EACH1$2,243.95$2,243.95$2,243.95$2,243.95
206Special 18. install monotube arms 45-FT special (SPV.0060)EACH2$2,243.95$2,243.95$2,243.95$2,243.95
207Special 19. install luminaire arms steel 15-FT (SPV.0060)EACH4$242.41$242.41$242.41$242.41
208Special 20. traffic control close- open freeway entrance ramp (SPV.0060)EACH47$450.00$450.00$450.00$450.00
209Special 21. traffic control full freeway closure (SPV.0060)EACH8$1,250.00$1,250.00$1,250.00$1,250.00
210Special 22. traffic control local road lane closures (SPV.0060)EACH99$400.00$400.00$400.00$400.00
211Special 23. field facilities office space (SPV.0060)EACH1$28,660$10,000$15,400$17,555
212Special 24. traffic flashing beacon system, IH 43 exit ramp at mineral ST (RT side ahead (SPV.0060)EACH1$5,022.73$5,022.73$5,022.73$5,022.73
213Special 25. traffic flashing beacon system, IH 43 exit ramp at mineral ST (RT turn bypas (SPV.0060)EACH1$5,022.73$5,022.73$5,022.73$5,022.73
214Special 26. traffic flashing beacon system, IH 43 exit ramp at mineral ST (median) (SPV.0060)EACH1$5,022.73$5,022.73$5,022.73$5,022.73
215Special 27. traffic flashing beacon system, IH 43 exit ramp at walker ST (right side ahe (SPV.0060)EACH1$5,022.73$5,022.73$5,022.73$5,022.73
216Special 28. traffic flashing beacon system, IH 43 exit ramp at walker ST (RT turn bypass (SPV.0060)EACH1$5,022.73$5,022.73$5,022.73$5,022.73
217Special 29. traffic flashing beacon system, IH 43 exit ramp at walker ST (median) (SPV.0060)EACH1$5,022.73$5,022.73$5,022.73$5,022.73
218Special 30. adjusting sanitary manhole (SPV.0060)EACH1$4,000.00$1,500.00$4,000.00$2,500.00
219Special 31. temporary marking removable mask out tape, words and arrows (SPV.0060)EACH3$55.00$55.00$55.00$55.00
220Special 32. transport and install state furnished evp detector heads, holt at 4TH (SPV.0060)EACH3$543.85$543.85$543.85$543.85
221Special 33. transport and install state furnished evp detector heads, 6TH at mineral (SPV.0060)EACH4$543.85$543.85$543.85$543.85
222Special 34. transport and install state furnished traffic signal cabinet, holt at 4TH (SPV.0060)EACH1$8,517.07$8,517.07$8,517.07$8,517.07
223Special 35. transport and install state furnished traffic signal cabinet, 6TH at mineral (SPV.0060)EACH1$7,983.33$7,983.33$7,983.33$7,983.33
224Special 36. transport and install state furnished radar detection system, 6TH at mineral (SPV.0060)EACH1$4,981.62$4,981.62$4,981.62$4,981.62
225Special 37. transport traffic signal and intersection lighting materials, holt at 4TH (SPV.0060)EACH1$711.66$711.66$711.66$711.66
226Special 38. transport traffic signal and intersection lighting materials, 6TH at mineral (SPV.0060)EACH1$711.66$711.66$711.66$711.66
227Special 39. transport and install state furnished APS buttons, holt at 4TH (SPV.0060)EACH1$2,824.40$2,824.40$2,824.40$2,824.40
228Special 40. transport and install state furnished APS buttons, 6TH at mineral (SPV.0060)EACH1$2,468.57$2,468.57$2,468.57$2,468.57
229Special 41. survey project 1228-09- 76 (SPV.0060)EACH1$34,355$34,355$34,355$34,355
230Special 01. pavement cleanup project 1228-09-76 (SPV.0075)HRS20$200.00$500.00$225.00$361.28
231Special 01. marking crosswalk epoxy 12-inch (SPV.0090)LF3,371$12.50$12.50$12.50$12.50
232Special 02. temporary fence chain link 6-FT (SPV.0090)LF280$40.00$50.00$62.00$50.00
233Special 03. concrete barrier temporary precast left in place (SPV.0090)LF100$56.00$56.00$56.00$56.00
234Special 01. removing loose concrete (SPV.0165)SF73$35.00$35.00$35.00$35.00
WisDOT contract 20250513009: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy