WisDOT contract 20250812008 bid tabulation

Milton to Whitewater; Wcl to Willis Ray Road (STH 059, Walworth County Milton to Whitewater). Let by Wisconsin DOT on August 12, 2025, Walworth. 2 bids received; low bid $1,813,813 by Payne and Dolan, Inc.

Owner
Wisconsin DOT
Letting
12 AUG 2025
Pay items
169
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Payne and Dolan, Inc$1,813,813Low
2Rock Road Companies, Inc.$2,332,717+29%
WisDOT contract 20250812008: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Payne and Dolan, Inc2. Rock Road Companies, Inc.
1Clearing (201.0110)SY59$43.43$43.00
2Grubbing (201.0210)SY59$43.43$43.00
3Removing concrete pavement (204.0100)SY200$14.30$9.40
4Removing asphaltic surface butt joints (204.0115)SY270$0.01$18.19
5Removing asphaltic surface milling (204.0120)SY56,733$1.35$3.85
6Removing curb & gutter (204.0150)LF480$16.60$9.75
7Removing concrete sidewalk (204.0155)SY220$18.25$23.95
8Removing concrete bases (204.0195)EACH9$275.79$275.79
9Removing (item description) 01. traffic signals (ush 12/STH 59/89 & STH 59/89) (204.9060.S)EACH1$4,589.06$4,589.06
10Removing (item description) 02. loop detector wire & lead-in cable (ush 12/STH 59/89 & STH 59/89) (204.9060.S)EACH1$1,378.93$1,378.93
11Excavation common (205.0100)CY40$100.00$28.19
12Prepare foundation for asphaltic paving (project) 01. 3110-03-73 (211.0101)EACH1$0.01$0.01
13Finishing roadway (project) 01. 3110-03-73 (213.0100)EACH1$1,600.00$5,999.34
14Base aggregate dense 3/4-inch (305.0110)TON600$31.30$40.07
15Base aggregate dense 1 1/4-inch (305.0120)TON70$68.75$22.72
16Concrete pavement 10-inch (415.0100)SY21$179.30$179.30
17Drilled tie bars (416.0610)EACH345$12.50$12.50
18Drilled dowel bars (416.0620)EACH180$17.50$17.50
19Concrete pavement repair (416.1710)SY45$120.65$120.65
20Concrete pavement repair shes (416.1715)SY70$246.30$246.30
21Concrete pavement replacement (416.1720)SY280$97.40$97.40
22Concrete pavement replacement shes (416.1725)SY300$158.95$158.95
23Tack coat (455.0605)GAL6,289$3.00$2.94
24HMA percent within limits (PWL) test strip volumetrics (460.0105.S)EACH1$100.00$3,500.00
25HMA percent within limits (PWL) test strip density (460.0110.S)EACH2$100.00$3,500.00
26Incentive density PWL HMA pavement (460.2005)DOL8,770$1.00$1.00
27Incentive density HMA pavement longitudinal joints (460.2007)DOL5,470$1.00$1.00
28Incentive air voids HMA pavement (460.2010)DOL10,010$1.00$1.00
29HMA pavement 4 LT 58-28 H (460.5424)TON10,010$73.00$100.00
30Asphaltic surface patching (465.0110)TON38$185.00$165.00
31Asphaltic surface driveways and field entrances (465.0120)TON7$220.00$325.00
32Asphaltic rumble strips, shoulder (465.0520)LF19,620$0.33$0.20
33Asphaltic rumble strips, centerline (465.0560)LF9,400$0.33$0.20
34Cleaning culvert pipes (520.8700)EACH1$2,165.00$1,500.00
35Apron endwalls for culvert pipe salvaged 24-inch (524.0624)EACH2$1,014.00$2,083.60
36Concrete curb & gutter 6-inch sloped 30-inch type G (601.0413)LF15$65.00$65.00
37Concrete curb & gutter 6-inch sloped 30-inch type J (601.0415)LF112$60.90$60.90
38Concrete curb & gutter integral 30- inch type D (601.0452)LF72$55.70$70.10
39Concrete curb & gutter 6-inch sloped 36-inch type A (601.0555)LF15$70.10$59.60
40Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF381$59.60$55.70
41Concrete curb pedestrian (601.0600)LF27$28.70$28.70
42Concrete sidewalk 5-inch (602.0410)SF1,541$12.35$12.35
43Curb ramp detectable warning field yellow (602.0505)SF20$46.20$46.20
44Curb ramp detectable warning field radial yellow (602.0605)SF56$68.55$68.55
45Slope paving concrete (604.0400)SY220$100.30$100.00
46Slope paving repair crushed aggregate (604.9010.S)CY2$150.00$150.00
47Reseal crushed aggregate slope paving (604.9015.S)SY460$16.46$16.46
48Riprap heavy (606.0300)CY30$120.00$229.71
49Adjusting manhole covers (611.8110)EACH1$1,190.00$1,510.77
50Adjusting inlet covers (611.8115)EACH1$1,190.00$737.56
51Cover plates temporary (611.8120.S)EACH2$275.00$679.53
52Pipe underdrain wrapped 6-inch (612.0406)LF210$24.70$10.00
53Maintenance and repair of haul roads (project) 01. 3110-03-73 (618.0100)EACH1$0.01$0.01
54Mobilization (619.1000)EACH1$20,058$97,087
55Water (624.0100)MGAL13$36.00$0.01
56Topsoil (625.0100)SY180$12.55$0.01
57Mulching (627.0200)SY180$1.00$1.00
58Silt fence (628.1504)LF224$3.00$3.00
59Silt fence maintenance (628.1520)LF224$0.01$0.01
60Mobilizations erosion control (628.1905)EACH4$100.00$100.00
61Mobilizations emergency erosion control (628.1910)EACH2$100.00$100.00
62Erosion mat class I type B (628.2004)SY330$2.00$2.00
63Erosion mat urban class I type A (628.2006)SY230$3.00$3.00
64Inlet protection type B (628.7010)EACH6$75.00$75.00
65Inlet protection type C (628.7015)EACH1$75.00$75.00
66Temporary ditch checks (628.7504)LF48$15.00$15.00
67Fertilizer type B (629.0210)CWT0.20$250.00$250.00
68Seeding mixture no. 20 (630.0120)LB9$20.00$20.00
69Seeding temporary (630.0200)LB2$20.00$20.00
70Seed water (630.0500)MGAL7$10.00$10.00
71Markers culvert end (633.5200)EACH11$70.00$70.00
72Posts wood 4X6-inch X 18-FT (634.0618)EACH27$95.00$95.00
73Signs type II reflective H (637.2210)SF117.10$21.00$21.00
74Signs type II reflective F (637.2230)SF53.75$23.00$23.00
75Moving signs type II (638.2102)EACH5$225.00$225.00
76Removing signs type II (638.2602)EACH34$35.00$35.00
77Removing small sign supports (638.3000)EACH27$35.00$35.00
78Field office type B (642.5001)EACH1$7,730.00$6,750.00
79Traffic control drums (643.0300)DAY2,097$0.25$0.25
80Traffic control barricades type III (643.0420)DAY705$0.95$0.95
81Traffic control warning lights type A (643.0705)DAY1,410$0.12$0.12
82Traffic control warning lights type C (643.0715)DAY196$0.77$0.77
83Connected arrow board (643.0810.S)DAY28$14.67$14.67
84Traffic control signs (643.0900)DAY10,402$0.25$0.25
85Traffic control covering signs type I (643.0910)EACH24$150.00$150.00
86Traffic control covering signs type II (643.0920)EACH8$56.98$56.98
87Traffic control signs fixed message (643.1000)SF162$13.37$13.37
88Traffic control signs PCMS (643.1050)DAY36$60.00$60.00
89Connected work zone start and end location markers (643.1220.S)DAY56$13.54$13.54
90Temporary marking line paint 4- inch (643.3105)LF2,030$0.61$0.61
91Temporary marking line paint 6- inch (643.3165)LF19,880$0.64$0.64
92Temporary marking crosswalk paint 6-inch (643.3305)LF414$11.00$11.00
93Traffic control (643.5000)EACH1$5,966.41$5,966.41
94Temporary pedestrian surface matting (644.1440)SF715$2.69$2.69
95Temporary pedestrian curb ramp (644.1601)DAY50$17.54$17.54
96Temporary pedestrian detectable warning field (644.1605)SF60$15.42$15.42
97Temporary pedestrian barricade (644.1810)LF668$4.00$4.00
98Geotextile type HR (645.0120)SY80$2.90$1.95
99Marking line epoxy 4-inch (646.1020)LF8,510$0.60$0.60
100Marking line grooved wet ref epoxy 6-inch (646.2040)LF41,720$1.35$1.35
101Marking line epoxy 8-inch (646.3020)LF1,810$1.20$1.20
102Marking line grooved wet ref epoxy 10-inch (646.4040)LF1,470$2.50$2.50
103Marking arrow epoxy (646.5020)EACH29$280.00$280.00
104Marking word epoxy (646.5120)EACH17$475.00$475.00
105Marking stop line epoxy 18-inch (646.6120)LF244$17.00$17.00
106Marking diagonal epoxy 12-inch (646.7120)LF360$14.00$14.00
107Marking crosswalk epoxy transverse line 6-inch (646.7420)LF190$15.00$15.00
108Marking curb epoxy (646.8120)LF70$10.00$10.00
109Marking island nose epoxy (646.8220)EACH5$285.00$285.00
110Construction staking curb gutter and curb & gutter (650.5500)LF610$3.50$1.75
111Construction staking concrete pavement (650.7000)LF67$10.00$0.01
112Construction staking resurfacing reference (650.8000)LF13,668$0.20$0.19
113Construction staking curb ramps (650.9000)EACH6$220.00$235.00
114Construction staking supplemental control (project) 01. 3110-03-73 (650.9911)EACH1$1,800.00$1,500.00
115Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF1,499$6.88$6.88
116Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF882$9.00$9.00
117Conduit special 3-inch (652.0615)LF775$21.60$21.60
118Conduit loop detector (652.0800)LF1,918$6.04$6.04
119Pull boxes steel 24X36-inch (653.0135)EACH7$1,317.61$1,317.61
120Pull boxes steel 24X42-inch (653.0140)EACH12$1,197.16$1,197.16
121Removing pull boxes (653.0905)EACH20$123.98$123.98
122Concrete bases type 1 (654.0101)EACH4$983.87$983.87
123Concrete bases type 13 (654.0113)EACH2$16,372$16,372
124Concrete bases type 10-special (654.0120)EACH2$12,062$12,062
125Concrete control cabinet bases type 9 special (654.0217)EACH1$2,837.15$2,837.15
126Cable traffic signal 5-14 AWG (655.0230)LF488$1.66$1.66
127Cable traffic signal 7-14 AWG (655.0240)LF392$2.12$2.12
128Cable traffic signal 12-14 AWG (655.0260)LF2,317$3.20$3.20
129Cable type UF 2-10 AWG grounded (655.0320)LF884$2.02$2.02
130Electrical wire traffic signals 10 AWG (655.0515)LF2,157$1.43$1.43
131Electrical wire lighting 12 AWG (655.0610)LF576$1.16$1.16
132Loop detector lead in cable (655.0700)LF5,835$1.75$1.75
133Loop detector wire (655.0800)LF6,852$1.30$1.30
134Traffic signal evp detector cable (655.0900)LF1,312$1.48$1.48
135Electrical service meter breaker pedestal (location) 01. ush 12/STH 59/89 & STH 59/89 (656.0201)EACH1$1,891.35$1,891.35
136Pedestal bases (657.0100)EACH4$350.84$350.84
137Traffic signal standards aluminum 15-FT (657.0425)EACH4$1,044.10$1,044.10
138Traffic signal face 3S 12-inch (658.0173)EACH12$1,015.75$1,015.75
139Traffic signal face 4S 12-inch (658.0174)EACH8$1,312.18$1,312.18
140Signal mounting hardware (location) 01. ush 12/STH 59/89 & STH 59/89 (658.5070)EACH1$7,520.01$7,520.01
141Luminaires utility LED C (659.1125)EACH4$375.94$375.94
142Lamp, ballast, LED, switch disposal by contractor (659.5000.S)EACH21$88.13$88.13
143Temporary traffic signals for intersections (location) 01. ush 12/STH 59/89 & STH 59/89 (661.0201)EACH1$40,402$40,402
144Generators (661.0300)DAY1$542.50$542.50
145Install camera assembly (677.0200)EACH1$3,179.36$3,179.36
146Sawing asphalt (690.0150)LF805$1.75$1.60
147Sawing concrete (690.0250)LF2,080$2.55$2.20
148Incentive iri ride (740.0440)DOL10,360$1.00$1.00
149On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS400$5.00$5.00
150On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS900$5.00$5.00
151Special 01. section corner monuments (SPV.0060)EACH2$0.01$550.00
152Special 02. install poles type 10 special (SPV.0060)EACH2$1,533.53$1,533.53
153Special 03. install poles type 13 OH (SPV.0060)EACH2$1,533.53$1,533.53
154Special 04. install monotube arms 45-FT type 9/10 special pole (SPV.0060)EACH2$1,843.30$1,843.30
155Special 05. install monotube arms 40-FT type 12/13 OH pole (SPV.0060)EACH1$1,537.36$1,537.36
156Special 06. install monotube arms 45-FT type 12/13 OH pole (SPV.0060)EACH1$1,843.30$1,843.30
157Special 07. install luminaire arms steel 15-FT (SPV.0060)EACH4$544.45$544.45
158Special 08. transport & install state furnished traffic signal cabinet ush 12/STH 59/89 (SPV.0060)EACH1$2,757.87$2,757.87
159Special 09. temporary infrared emergency vehicle preemption system ush 12/STH 59/89 & ST (SPV.0060)EACH1$2,684.00$2,684.00
160Special 10. transport and install state furnished radar detect system ush 12/STH 59/89 & (SPV.0060)EACH1$2,684.00$2,684.00
161Special 11. transport traffic signal & intersection lighting materials ush 12/STH 59/89 (SPV.0060)EACH1$2,684.00$2,684.00
162Special 12. transport & install state furnished evp detector heads ush 12/STH 59/89 & ST (SPV.0060)EACH1$2,013.00$2,013.00
163Special 13. cleaning inlets (SPV.0060)EACH1$1,090.00$341.55
164Special 14. grading, shaping, finishing driveway removal (SPV.0060)EACH1$1,950.00$2,532.40
165Special 15. curb ramp grading, shaping and finishing (SPV.0060)EACH6$685.00$819.65
166Special 16. wing grading, shaping and finishing (SPV.0060)EACH1$2,575.00$2,762.34
167Special 17. adjusting water valve boxes (SPV.0060)EACH2$275.00$679.53
168Special 01. resin binder high friction surface treatment (SPV.0180)SY5,100$24.53$23.09
169Special 01. asphaltic repair (SPV.0195)TON333$96.00$180.00
WisDOT contract 20250812008: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of August 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy