Research record, not reviewed
I-5 South County Improvements Project
- Location
- Mission Viejo, CA, United States. Location shown at city level. See it on the map
- Stage
- Opened, as of April 2025 (Orange County Transportation Authority).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Orange County Transportation Authority (with Caltrans) | |
| Category | Highways | |
| Route length | 6.5 mi | Orange County Transportation Authority |
| Amount | US$611 million (US dollars), as of November 2026 | Federal Highway Administration |
| What the amount covers | Capital estimate. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$687 M | Project value | Whole project | Apr 2025 | Orange County Transportation Authority |
| US$611 M | Capital estimate | Whole project | Nov 2026 | Federal Highway Administration |
Contracts and teams
Contracts and teams: Not found in the sources consulted.
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| 2019 | construction start | Whole project | Orange County Transportation Authority |
| April 16, 2025 | opening | Whole project | Orange County Transportation Authority |
About the project
A widening of 6.5 miles of I-5 between SR-73 and El Toro Road in south Orange County, extending a second carpool lane from Alicia Parkway to El Toro Road and adding a regular lane between Avery Parkway and Alicia Parkway in each direction, and rebuilding interchange ramps at La Paz Road, Avery Parkway and Los Alisos Boulevard. OCTA's completion release calls it a $687 million project. Construction began in summer 2019; OCTA marked completion of the major roadway improvements at a dedication on April 16, 2025, funded mainly by Measure M.
Sources
- I-5 South County Improvements Open with Dedication Event Celebrating Smoother Travel Through South Orange County, Orange County Transportation Authority, 16 Apr 2025. '$687 million project', 6.5 miles between SR-73 and El Toro Road; crews began in summer 2019. Consulted 12 Nov 2026.
- FHWA Active Major Project Status Report (FOIS), Federal Highway Administration. Project 'I-5 South County Improvements (SR 73 - El Toro Rd)': Total Cost Baseline $620 Current $611; Completion Current Feb-2026. Consulted 12 Nov 2026.
- I-5 South County Improvements Project (project page), Orange County Transportation Authority. 'This project was completed in 2025.'; 'Total estimated cost' '$664 million'; 'New auxiliary lanes at seven locations'. Consulted 19 Nov 2026.