Foothill Gold Line from Glendora to Pomona
- Location
- Pomona, CA, United States. Location shown at city level. See it on the map
- Stage
- Opened, as of September 2025 (LA Metro).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | LA Metro (built by the Foothill Gold Line Construction Authority) | |
| Category | Urban transit | |
| Route length | 9.1 mi | Foothill Gold Line Construction Authority |
| New stations | 4 | Foothill Gold Line Construction Authority |
| Amount | US$1.5 billion (US dollars), as of January 2025 | Foothill Gold Line Construction Authority |
| What the amount covers | Project value. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$1.5 bn | Project value | Whole project | Jan 2025 | Foothill Gold Line Construction Authority |
| US$907 M | Contract value | One package | Jan 2025 | Foothill Gold Line Construction Authority |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Kiewit-Parsons, a Joint Venture (KPJV) | design-build contractor | Glendora to Pomona design-build | Foothill Gold Line Construction Authority |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| October 2019 | award | Whole project | Foothill Gold Line Construction Authority |
| July 2020 | construction start | Whole project | Foothill Gold Line Construction Authority |
| January 3, 2025 | substantial completion | Whole project | Foothill Gold Line Construction Authority |
| September 30, 2025 | opening | Whole project | LA Metro |
About the project
A 9.1-mile, four-station light rail extension of the Metro A Line from Glendora through San Dimas and La Verne to Pomona, delivered by the Foothill Gold Line Construction Authority under a $906.5 million design-build contract with Kiewit-Parsons JV executed in October 2019. The $1.5 billion project reached substantial completion on January 3, 2025, on time and on budget, and Metro officially opened the extension on September 30, 2025. Funding came mainly from Measure M, residual Measure R funds and a state TIRCP grant.
Sources
- Foothill Gold Line from Glendora to Pomona Reaches Substantial Completion (press release), Foothill Gold Line Construction Authority, 3 Jan 2025. First paragraph: '$1.5 billion, four-station ... project', '$906.5 million contract', 9.1-mile, Kiewit-Parsons JV, contract executed October 2019, major construction July 2020. Consulted 12 Nov 2026.
- Possibility Travels with You: Metro A Line Extension Between Azusa, Pomona Officially Opens, LA Metro, 30 Sep 2025. Body: '$1.5 billion rail extension project', adds nine miles, four new stations, officially opens. Consulted 12 Nov 2026.