Unit-price pay estimate calculator for bid item contracts

Enter your bid items with their unit prices, contract quantities and the quantities measured to date, and get the amount earned this period and to date, the percent of each contract quantity, retainage and the payment due. Items that run past their contract quantity are flagged against the federal-aid rule on significant changes in quantities.

Bid items

Item line 1

Enter 0 on a first estimate.

Lets the tool check a final quantity below 75%.

Retainage and payments

As your contract sets it. Enter 0 if none is held.

Total paid on earlier estimates. Enter 0 on the first one.

Send a month of measurements, see what an agent would prepare

Mirage has no published deployment on unit-price pay estimates. What it does in production is read construction documents and tie each quantity to its source: at OCBM, three agents are in production and 100% of quantities are tied to a source drawing.

See pay application automation

Document

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy

How the estimate is calculated

Amount this period = unit price × quantity this period

Quantity to date = quantity previous + quantity this period

Amount to date = unit price × quantity to date

Retainage = amount to date × retainage rate

Payment due = amount to date − retainage − previous payments

On a unit-price contract every bid item has a unit and a price per unit, and what is paid is the quantity measured in the field times that price. Alberta Transportation's specification for reinforcing steel is one example: the steel is measured in kilograms and paid at the unit price bid per kilogram (Section 5, 5.10). The contract quantities are estimates and the measured quantities decide the amount, except where the contract pays an item at its plan quantity, as FDOT's design manual describes for some earthwork (FDOT Design Manual, 216.4.3).

Excavation at $12.50 per cubic yard, 10,000 CY in the contract, 6,000 CY measured before and 2,500 CY this period: 8,500 CY to date, $31,250 earned this period and $106,250 to date, 85% of the contract quantity. A negative quantity this period is accepted, as a correction of an earlier measurement.

An empty field is never read as zero. An item with no previous quantity shows its to-date figures as a lower bound, and the payment due waits until every previous quantity, the retainage rate and the previous payments are entered.

Overruns, underruns and 23 CFR 635.109

Federal-aid highway contracts must include standard clauses on changed conditions, one of them on significant changes in the character of work (23 CFR 635.109(a)). Under it, a significant change includes the case where a major item of work, as the contract defines it, is increased in excess of 125 percent or decreased below 75 percent of the original contract quantity. Any allowance for an increase applies only to the portion above 125 percent; for a decrease, to the actual amount of work performed (635.109(a)(3)(iv)(B)).

The calculator therefore flags any item whose quantity to date passes 125% of its contract quantity, with the quantity above that line, and any item marked complete that ends below 75%. It cannot know which items your contract defines as major, so read the flag against that definition. An item between 100% and 125% is shown as over its contract quantity only.

The clause has limits of its own: where a state statute does not permit it, the statute prevails; a clause a state DOT has developed under a specific state statute may be used in its place, subject to the FHWA Division Administrator's approval; and on design-build projects state DOTs may consider it rather than having to include it (635.109(b) and (c)). Check the clause in your contract's standard specifications.

How this differs from an AIA G702 pay application

The AIA G702 is the contractor's application and the architect's certificate for payment, used with the G703 continuation sheet, which breaks the contract sum into portions of the work according to a schedule of values (AIA, G702-1992 summary). Progress there is billed against the value of each portion. A unit-price estimate bills measured quantities at bid prices, and the contract amount moves with the quantities. For a schedule of values, use the AIA G702 pay application calculator.

Retainage and previous payments

The retainage rate and when it is released come from the contract and the rules it is let under: the calculator does not assume either. Enter the rate your contract sets, or 0 where nothing is held, and the total of the payments already made. The payment due is the amount earned to date, less retainage on it, less those payments.

Progress payment certificates

A progress payment certificate records, for one period, the quantities measured, their value at the bid prices, retainage and the payments already made, and the amount the owner's representative certifies as due. The lines of this calculator follow that order; the form, the signatures and the deadlines are the contract's.

Sources

FAQ

  • A contract in which each bid item has a unit of measure and a price per unit, and the contractor is paid the quantity actually measured times that price, unless the contract pays an item at its plan quantity. The quantities in the bid are estimates, so the final contract amount depends on what is measured.

  • On a federal-aid highway contract, 23 CFR 635.109 requires a clause under which an increase of a major item in excess of 125 percent of the original contract quantity is a significant change, and any adjustment applies only to the portion above 125 percent. Which items are major is defined in the contract. A decrease below 75 percent is a significant change too, with the adjustment based on the work actually performed.

  • A G702 is used with a G703 continuation sheet that breaks a contract sum into portions of the work by a schedule of values, and progress is billed against those portions. A unit-price estimate pays measured quantities at bid prices, and the contract amount moves with the quantities.

  • Multiply the amount earned to date by the retainage rate your contract sets, then subtract it and the payments already made from the amount earned to date to get the payment due. The calculator does not assume a rate: enter 0 if none is held.

  • The record for one period of the quantities measured, their value at the bid prices, retainage and earlier payments, with the amount the owner's representative certifies as due. The calculator lays out those lines; the form, signatures and deadlines come from the contract.