Free tools / Construction

Cut and fill calculator: average end area earthwork volumes

Enter your cross sections, station by station, with the cut and fill end areas, and get the excavation and embankment volumes between them by the average end area method, in cubic yards or cubic metres. Add the shrink or swell your soils report gives and the tool balances the job and draws the mass ordinate at every station.

Units
Cross sections

Enter 0 where a section has no cut or no fill. An empty area is not read as zero.

Section 1

Section 2

Shrink or swell

One of the two, from the soils report or the geotechnical engineer. Empty: cut and fill are not balanced.

Send the plans, get the quantities

Earthwork quantities start on the plans and cross sections. Mirage reads plan sets in metric or imperial units and ties each quantity to the drawing it came from: at OCBM, three agents are in production and 100% of quantities are tied to a source drawing.

See AI for heavy civil estimating

Document

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy

How the volumes are calculated

Volume between two sections = (A1 + A2) ÷ 2 × L

Cubic yards = (A1 + A2) ÷ 2 × L ÷ 27, with A in ft² and L in ft

Mass ordinate M2 = M1 + cut(1 to 2) − factor × fill(1 to 2)

This is the average end area method, which the Florida DOT's design manual uses for earthwork quantities: the average of the two end areas times the distance between them, divided by 27 for cubic yards (FDOT Design Manual, 216.4). With sections at stations 1+00 and 2+00, fill areas of 100 and 120 ft² and cut areas of 150 and 50 ft², the fill is 407 CY and the cut 370 CY, the worked example of the Wyoming DOT's Road Design Manual.

The method treats the ground between two sections as a prism with their average area. Wyoming DOT notes that it is exact only when the two areas are equal, that the error is largest when one of them is zero, and that a shorter interval between sections makes it more accurate (WYDOT Road Design Manual, section 3-03). Add a section where the ground breaks, at a ridge or a ditch bottom, rather than relying on even stations. The tool applies no prismoidal correction.

Stations are read the way plans write them: 12+50 is 1,250 ft from the start of the alignment (100 ft stations), and in metric 1+250 is 1,250 m (1,000 m before the plus). A plain number is read as a distance. Stations must increase down the list.

Shrink, swell and the compaction factor

Excavated soil usually takes less room once compacted in an embankment, and rock usually more. Wyoming DOT turns this into a compaction factor applied to embankment: a soil with a 20% shrink gives a factor of 1.2, so Fill × 1.2 = Cut, and a rock with a 10% swell gives 0.9 (WYDOT 3-03, Compaction Factors). The tool uses the same convention: factor = 1 + shrink, or 1 − swell.

Wyoming DOT takes the factors from the soils profile or the geology and field offices, calls them subjective, and warns that a project of thin cuts and fills can need a much higher one than the laboratory figure. That is why both fields start empty: with no factor, the tool shows the two volumes and does not balance them.

Agencies and contracts define shrink and swell differently, some against bank volume, some against the compacted one. Check the definition your contract or your geotechnical report uses before you enter a percentage.

From volumes to pay quantities

FDOT computes its earthwork quantities in cubic yards for its pay items (FDM 216.4 and 216.5), and on a unit-price contract those quantities are paid at the bid price per cubic yard. To turn measured quantities into a progress payment, use the unit-price pay estimate calculator, which also flags an item that runs over its contract quantity.

Sources

FAQ

  • With the average end area method: for each pair of adjacent cross sections, average their cut areas and multiply by the distance between them, then do the same for fill. In US units, divide square feet times feet by 27 to get cubic yards. Sections at 1+00 and 2+00 with fill areas of 100 and 120 ft² give (100 + 120) ÷ 2 × 100 ÷ 27 = 407 CY of fill.

  • It is exact only when the two end areas are equal, and the error is largest when one of them is zero, as Wyoming DOT's design manual notes. Shorter intervals, and a section wherever the ground breaks, make it more accurate.

  • They turn compacted embankment into the bank volume needed to build it. Under Wyoming DOT's convention a 20% shrink gives a factor of 1.2, so 100 CY of fill needs 120 CY of cut; a 10% swell gives 0.9. The calculator subtracts factor × fill from cut to show the excess to waste or the shortfall to borrow.

  • Because the right figure depends on the soil and the job, and comes from the soils report or the geotechnical engineer. Wyoming DOT calls these factors subjective and notes that a project of thin cuts and fills can need a higher one than the laboratory figure.

  • Type it as written: 12+50 is read as 1,250 ft in US units, and 1+250 as 1,250 m in metric. A plain number is read as a distance along the alignment.

Every quantity, tied to its drawing.

See how OCBM's estimators review a takeoff in which every quantity points back to the sheet it came from.

See the OCBM case study