ALDOT contract 20260227031 bid tabulation
PLANING, RESURFACING, AND TRAFFIC STRIPE ON SR-295 FROM THE JUNCTION OF CR-18 (LOVE ROAD) TO THE JUNCTION OF SR-13 (US-43) IN GROVE HILL. Let by Alabama DOT on February 27, 2026, Clarke, 0804. 2 bids received; low bid $1,466,192 by Apac-Alabama, Inc..
- Owner
- Alabama DOT
- Letting
- 27 FEB 2026
- Pay items
- 33
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Apac-Alabama, Inc. | $1,466,192 | Low |
| 2 | Wiregrass Construction Company, Inc. | $2,075,000 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Apac-Alabama, Inc. | 2. Wiregrass Construction Company, Inc. |
|---|---|---|---|---|---|
| 0010 | Machine grading shoulders (212A000) | STA | 34 | $152.31 | $593.39 |
| 0020 | Tack coat (405A000) | GAL | 10,247 | $4.53 | $4.18 |
| 0030 | Planing existing pavement (approximately 1.10" thru 2.0" thick) (408A052) | SY | 102,463 | $1.19 | $3.60 |
| 0040 | Material remixing device (410H000) | EACH | 1 | $18,713 | $0.01 |
| 0050 | Superpave bituminous concrete wearing surface layer, 3/4" maximum aggregate size mix, esal range A/B (424A341) | TON | 8,348 | $112.12 | $143.74 |
| 0060 | Superpave bituminous concrete wearing surface layer, widening, 3/4" maximum aggregate size mix, esal range A/B (424A350) | TON | 360 | $160.09 | $226.05 |
| 0070 | Superpave bituminous concrete upper binder layer, patching, 1" maximum aggregate size mix, esal range A/B (424B640) | TON | 200 | $169.92 | $319.04 |
| 0080 | Superpave bituminous concrete upper binder layer, leveling, 3/4" maximum aggregate size mix, esal range A/B (424B643) | TON | 200 | $112.78 | $179.43 |
| 0090 | Aggregate surfacing (1" down, crusher run) (430B043) | TON | 100 | $71.35 | $147.98 |
| 0100 | Mobilization (600A000) | LS | 1 | $20,405 | $65,104 |
| 0110 | Topsoil (650A000) | CY | 150 | $89.65 | $62.07 |
| 0120 | Seeding (652A100) | ACRE | 1 | $1,783.63 | $1,957.50 |
| 0130 | Mulching (656A010) | ACRE | 1 | $1,426.90 | $1,566.00 |
| 0140 | Sand bags (665G000) | EACH | 150 | $16.65 | $18.27 |
| 0150 | Wattle (665Q002) | LF | 100 | $16.65 | $18.27 |
| 0160 | Construction fuel (maximum bid limited to $ 70,000.00) (698A000) | LS | 1 | $0.00 | $0.00 |
| 0170 | Solid white, class 2, type A traffic stripe (5" wide) (701A227) | MI | 3 | $4,459.06 | $4,893.75 |
| 0180 | Solid yellow, class 2, type A traffic stripe (5" wide) (701A230) | MI | 7 | $4,459.06 | $4,893.75 |
| 0190 | Broken white, class 2, type A traffic stripe (5" wide) (701A239) | MI | 2 | $2,259.26 | $2,479.50 |
| 0200 | Broken yellow, class 2, type A traffic stripe (5" wide) (701A244) | MI | 6 | $2,259.26 | $2,479.50 |
| 0210 | Dotted, class 2, type A traffic stripe (5" wide) (701B207) | LF | 472 | $1.78 | $1.96 |
| 0220 | Broken temporary traffic stripe (701C000) | MI | 22 | $909.65 | $998.33 |
| 0230 | Solid temporary traffic stripe (701C001) | MI | 25 | $951.27 | $1,044.00 |
| 0240 | Traffic control markings, class 2, type A (703A002) | SF | 3,159 | $5.35 | $5.87 |
| 0250 | Traffic control legends, class 2, type A (703B002) | SF | 135 | $6.84 | $7.50 |
| 0260 | Temporary traffic control markings (703D001) | SF | 2,744 | $1.19 | $1.31 |
| 0270 | Pavement markers, class A-H, type 2-C (705A030) | EACH | 301 | $5.95 | $6.53 |
| 0280 | Pavement markers, class A-H, type 1-B (705A032) | EACH | 344 | $5.95 | $6.53 |
| 0290 | Pavement markers, class A-H, type 2-D (705A037) | EACH | 64 | $5.95 | $6.53 |
| 0300 | Construction signs (740B000) | SF | 1,262 | $7.43 | $7.18 |
| 0310 | Channelizing drums (740D000) | EACH | 250 | $36.86 | $0.01 |
| 0320 | Pilot car (740O000) | EACH | 1 | $21,388 | $696.73 |
| 0330 | Portable sequential arrow and chevron sign unit (741C010) | EACH | 2 | $1,426.90 | $4,753.17 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of February 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.