ARDOT contract A40049 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 10.901 MILES OF HIGHWAY 64 IN CRAWFORD COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL OF GUARDRAIL, TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL, MUMBLE STRIPS AND STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on April 8, 2026, Crawford. 3 bids received; low bid $4,838,281 by Forsgren, Inc..
- Owner
- Arkansas DOT
- Letting
- 08 APR 2026
- Pay items
- 41
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Forsgren, Inc. | $4,838,281 | Low |
| 2 | Emery Sapp & Sons, Inc. | $4,972,162 | +3.0% |
| 3 | Robinson Construction, LLC | $6,103,262 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Forsgren, Inc. | 2. Emery Sapp & Sons, Inc. | 3. Robinson Construction, LLC |
|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of guardrail (202132) | LF | 1,825 | $15.65 | $16.70 | $4.00 |
| 0002 | Trenching and shoulder preparation (215011) | STA | 28 | $475.00 | $1,037.29 | $955.00 |
| 0003 | Aggregate base course (class 7) (303117) | TON | 911 | $35.00 | $53.59 | $36.00 |
| 0004 | Tack coat (401011) | GAL | 47,947 | $3.00 | $0.01 | $4.10 |
| 0005 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 29,092 | $99.95 | $109.94 | $122.22 |
| 0006 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 30 | $120.00 | $120.00 | $120.00 |
| 0007 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 1,859 | $120.00 | $120.00 | $120.00 |
| 0008 | Cold milling asphalt pavement (412002) | SY | 237,645 | $1.65 | $1.02 | $3.81 |
| 0009 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 300 | $215.00 | $154.02 | $255.00 |
| 0010 | Achm patching of existing roadway (415011) | TON | 1,000 | $155.00 | $115.09 | $235.00 |
| 0011 | Approach gutters (504264) | CY | 90.48 | $1,791.50 | $1,908.65 | $320.00 |
| 0012 | Maintenance of traffic (603010) | LS | 1 | $38,900 | $42,609 | $45,000 |
| 0013 | Signs (604003) | SF | 2,796 | $8.35 | $8.91 | $8.80 |
| 0014 | Traffic drums (604023) | EACH | 50 | $47.00 | $50.10 | $49.50 |
| 0015 | Construction pavement markings (604041) | LF | 277,500 | $0.16 | $0.17 | $0.16 |
| 0016 | Construction pavement markings (words) (604045) | EACH | 10 | $130.00 | $139.17 | $137.50 |
| 0017 | Construction pavement markings (arrows) (604046) | EACH | 4 | $105.00 | $111.33 | $110.00 |
| 0018 | Removal of permanent pavement markings (604061) | LF | 3,200 | $0.31 | $0.33 | $0.33 |
| 0019 | Guardrail (type A) (617005) | LF | 1,125 | $41.80 | $44.53 | $44.00 |
| 0020 | Guardrail terminal (type 2) (617312) | EACH | 28 | $4,493.50 | $4,787.34 | $4,730.00 |
| 0021 | Lime (620001) | TON | 1 | $130.60 | $139.17 | $300.00 |
| 0022 | Seeding (620011) | ACRE | 0.50 | $2,703.00 | $2,879.41 | $550.00 |
| 0023 | Mulch cover (620022) | ACRE | 1 | $2,234.00 | $2,379.68 | $1,500.00 |
| 0024 | Water (620030) | MGAL | 61.20 | $10.45 | $11.13 | $10.00 |
| 0025 | Temporary seeding (621001) | ACRE | 0.50 | $1,505.00 | $1,602.80 | $550.00 |
| 0026 | Silt fence (621021) | LF | 4,500 | $3.60 | $3.85 | $3.45 |
| 0027 | Sediment removal and disposal (621111) | CY | 167 | $12.00 | $5.51 | $45.00 |
| 0028 | Second seeding application (623001) | ACRE | 0.50 | $825.00 | $878.69 | $280.00 |
| 0029 | Roadway construction control (635011) | LS | 1 | $15,725 | $11,941 | $65,000 |
| 0030 | Mumble strips in asphalt shoulders (642301) | LF | 68,460 | $0.23 | $0.23 | $0.23 |
| 0031 | Centerline mumble stripes in asphalt roadways (642402) | LF | 34,230 | $0.24 | $0.23 | $0.23 |
| 0032 | Portable traffic signal system - actuated (701603) | WEEK | 15 | $2,156.00 | $1,670.00 | $1,650.00 |
| 0033 | Thermoplastic pavement marking white (6") (719002) | LF | 122,000 | $0.73 | $0.78 | $0.77 |
| 0034 | Thermoplastic pavement marking white (12") (719005) | LF | 580 | $6.27 | $6.68 | $6.60 |
| 0035 | Thermoplastic pavement marking yellow (6") (719102) | LF | 130,000 | $0.61 | $0.65 | $0.63 |
| 0036 | Thermoplastic pavement marking (words) (719201) | EACH | 10 | $313.50 | $334.00 | $330.00 |
| 0037 | Thermoplastic pavement marking (arrows) (719202) | EACH | 4 | $261.25 | $278.33 | $275.00 |
| 0038 | Raised pavement markers (type II) (721002) | EACH | 950 | $7.32 | $7.79 | $7.70 |
| 0039 | Bridge end terminal (734011) | EACH | 1 | $36,575 | $38,967 | $45,000 |
| 0040 | Reinforcing steel-roadway (grade 60) (804003) | LB | 7,182 | $3.14 | $3.34 | $4.80 |
| 0041 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $90,000 | $214,584 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 8, 2026. Compiled by Mirage Metrics.