ARDOT contract C22005 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO REPLACE ONE BRIDGE STRUCTURE AND CONSTRUCT APPROACHES ON 0.043 MILE OF 7TH STREET IN WILMAR IN DREW COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, EARTHWORK, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, MAINTENANCE OF TRAFFIC, EROSION CONTROL ITEMS, PAVEMENT MARKING, ONE TRIPLE R.C. BOX CULVERT (TOTAL SPAN 35.33'), AND MISC. ITEMS. Let by Arkansas DOT on June 24, 2026, Drew. 6 bids received; low bid $609,121 by T & T Construction, LLC.
- Owner
- Arkansas DOT
- Letting
- 24 JUN 2026
- Pay items
- 39
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | T & T Construction, LLC | $609,121 | Low |
| 2 | Thomco, Inc. | $651,353 | +7.0% |
| 3 | 1911 Construction Company, Inc. | $686,551 | +13% |
| 4 | Mobley Contractors, Inc. | $739,240 | +21% |
| 5 | Kesser International, Inc. | $951,539 | +56% |
| 6 | Central Arkansas Contractors, Inc. | $982,854 | +61% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. T & T Construction, LLC | 2. Thomco, Inc. | 3. 1911 Construction Company, Inc. | 4. Mobley Contractors, Inc. | 5. Kesser International, Inc. | 6. Central Arkansas Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201012) | STA | 3 | $1,800.00 | $2,700.00 | $850.00 | $3,253.11 | $4,480.00 | $4,500.00 |
| 0002 | Grubbing (201111) | STA | 3 | $1,800.00 | $2,725.00 | $850.00 | $3,253.11 | $4,480.00 | $3,500.00 |
| 0003 | Removal and disposal of guardrail (202132) | LF | 78 | $6.42 | $10.00 | $20.00 | $19.77 | $44.80 | $22.50 |
| 0004 | Removal and disposal of signs (202191) | EACH | 6 | $50.00 | $100.00 | $250.00 | $187.47 | $224.00 | $500.00 |
| 0005 | Removal of existing bridge structure (site no. 1) (205011) | LS | 1 | $23,000 | $20,000 | $40,000 | $89,142 | $56,000 | $55,000 |
| 0006 | Unclassified excavation (210210) | CY | 1,898 | $14.40 | $29.00 | $20.00 | $30.95 | $28.00 | $34.50 |
| 0007 | Compacted embankment (210601) | CY | 89 | $25.00 | $87.00 | $18.00 | $103.41 | $33.60 | $120.00 |
| 0008 | Aggregate base course (class 7) (303107) | TON | 214 | $65.00 | $61.00 | $55.00 | $130.25 | $140.00 | $92.50 |
| 0009 | Tack coat (401011) | GAL | 50 | $0.01 | $0.01 | $18.00 | $10.00 | $13.44 | $6.00 |
| 0010 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 149 | $248.00 | $237.50 | $385.00 | $237.50 | $386.40 | $325.00 |
| 0011 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 9 | $271.00 | $260.80 | $385.00 | $260.80 | $386.40 | $325.00 |
| 0012 | Cold milling asphalt pavement (412001) | SY | 311 | $43.41 | $29.00 | $40.00 | $29.00 | $52.81 | $45.00 |
| 0013 | Maintenance of traffic (603009) | LS | 1 | $30,000 | $25,000 | $38,000 | $15,795 | $61,600 | $47,000 |
| 0014 | Signs (604003) | SF | 337 | $25.00 | $6.00 | $23.00 | $20.00 | $25.76 | $20.00 |
| 0015 | Barricades (604013) | LF | 32 | $60.00 | $23.00 | $35.00 | $30.00 | $41.44 | $40.00 |
| 0016 | Concrete ditch paving (type B) (605002) | SY | 89 | $90.00 | $150.00 | $105.00 | $270.36 | $224.00 | $172.00 |
| 0017 | 4" pipe underdrains (611008) | LF | 200 | $19.50 | $27.20 | $15.00 | $25.24 | $5.60 | $21.50 |
| 0018 | Underdrain outlet protectors (611013) | EACH | 4 | $700.00 | $487.00 | $200.00 | $937.10 | $616.00 | $875.00 |
| 0019 | Lime (620001) | TON | 1 | $420.00 | $400.00 | $460.00 | $125.00 | $161.28 | $200.00 |
| 0020 | Seeding (620011) | ACRE | 0.42 | $5,357.14 | $5,000.00 | $5,750.00 | $3,898.64 | $5,040.00 | $3,500.00 |
| 0021 | Mulch cover (620022) | ACRE | 0.84 | $5,238.10 | $5,000.00 | $5,750.00 | $3,898.65 | $5,040.00 | $2,500.00 |
| 0022 | Water (620030) | MGAL | 52.90 | $10.00 | $10.00 | $10.00 | $10.00 | $12.88 | $12.00 |
| 0023 | Temporary seeding (621001) | ACRE | 0.42 | $4,285.70 | $4,000.00 | $4,600.00 | $1,987.29 | $2,576.00 | $1,000.00 |
| 0024 | Silt fence (621021) | LF | 375 | $12.00 | $10.00 | $12.00 | $6.86 | $9.02 | $6.75 |
| 0025 | Sand bag ditch checks (621031) | BAG | 132 | $14.50 | $12.50 | $15.00 | $12.93 | $18.03 | $20.00 |
| 0026 | Sediment removal and disposal (621111) | CY | 32 | $10.00 | $40.00 | $30.00 | $1.00 | $22.40 | $22.50 |
| 0027 | Rock ditch checks (621151) | CY | 36 | $140.00 | $117.00 | $175.00 | $207.45 | $112.00 | $175.00 |
| 0028 | Filter sock (18") (621169) | LF | 1,600 | $2.50 | $13.50 | $15.75 | $13.98 | $18.03 | $16.20 |
| 0029 | Second seeding application (623001) | ACRE | 0.42 | $1,428.57 | $1,000.00 | $1,150.00 | $896.43 | $1,154.05 | $1,000.00 |
| 0030 | Solid sodding (624001) | SY | 120 | $16.25 | $15.25 | $17.50 | $6.87 | $9.02 | $12.50 |
| 0031 | Roadway construction control (635001) | LS | 1 | $30,000 | $30,000 | $30,000 | $9,869.11 | $61,600 | $45,000 |
| 0032 | Reflectorized paint pavement marking white (4") (718001) | LF | 450 | $12.00 | $3.00 | $10.65 | $9.00 | $11.59 | $12.50 |
| 0033 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 285 | $12.00 | $3.00 | $10.65 | $9.00 | $11.59 | $12.50 |
| 0034 | Standard sign (726002) | SF | 12 | $60.00 | $12.00 | $33.00 | $28.00 | $25.76 | $15.00 |
| 0035 | Channel post sign support (type C) (729003) | EACH | 4 | $165.00 | $90.00 | $106.00 | $90.00 | $115.92 | $120.00 |
| 0036 | Unclassified excavation for structures-roadway (801101) | CY | 79 | $45.00 | $100.00 | $175.00 | $617.25 | $134.40 | $180.00 |
| 0037 | Class S concrete-roadway (802012) | CY | 179.29 | $1,484.00 | $1,600.00 | $1,500.00 | $1,313.37 | $1,948.80 | $2,250.00 |
| 0038 | Reinforcing steel-roadway (grade 60) (804003) | LB | 25,825 | $2.50 | $1.80 | $1.85 | $2.08 | $3.08 | $3.75 |
| 0039 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $21,000 | $25,000 | $32,000 | $31,603 | $44,800 | $45,200 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of June 24, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.