ARDOT contract C65016 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.17 MILES OF VARIOUS CITY STREETS IN THE CITY OF GREENWOOD AND APPROXIMATELY 1.02 MILES OF CITY STREETS IN THE CITY OF HACKETT IN SEBASTIAN COUNTY. THIS PROJECT CONSISTS OF BORROW, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, PAVEMENT MARKING, MAINTENANCE OF TRAFFIC, AND MISC. ITEMS. Let by Arkansas DOT on January 15, 2025, Sebastian. 5 bids received; low bid $542,986 by Emery Sapp & Sons, Inc..
- Owner
- Arkansas DOT
- Letting
- 15 JAN 2025
- Pay items
- 14
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Emery Sapp & Sons, Inc. | $542,986 | Low |
| 2 | Robinson Construction, LLC | $599,497 | +10% |
| 3 | Forsgren, Inc. | $612,971 | +13% |
| 4 | Apac-Central, Inc. | $698,694 | +29% |
| 5 | McKenzie Asphalt, LLC | $705,203 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Emery Sapp & Sons, Inc. | 2. Robinson Construction, LLC | 3. Forsgren, Inc. | 4. Apac-Central, Inc. | 5. McKenzie Asphalt, LLC |
|---|---|---|---|---|---|---|---|---|
| 0001 | Borrow (210412) | TON | 173 | $39.55 | $25.00 | $38.50 | $74.00 | $34.70 |
| 0002 | Tack coat (401011) | GAL | 3,035 | $3.81 | $4.50 | $4.00 | $3.65 | $5.00 |
| 0003 | Mineral aggregate in achm surface course (3/8") (407161) | TON | 3,132 | $122.55 | $124.55 | $133.75 | $141.00 | $145.60 |
| 0004 | Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431) | TON | 215 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 0005 | Cold milling asphalt pavement (412001) | SY | 2,110 | $7.13 | $4.85 | $7.80 | $8.50 | $17.75 |
| 0006 | Achm patching of existing roadway (415011) | TON | 345 | $145.66 | $250.00 | $215.00 | $269.00 | $275.00 |
| 0007 | Maintenance of traffic (603009) | LS | 1 | $16,706 | $32,000 | $14,450 | $47,500 | $20,000 |
| 0008 | Signs (604003) | SF | 272 | $30.84 | $15.50 | $26.00 | $27.36 | $25.00 |
| 0009 | Reflectorized paint pavement marking white (4") (718001) | LF | 12,355 | $0.43 | $0.35 | $0.36 | $0.38 | $0.35 |
| 0010 | Reflectorized paint pavement marking white (12") (718005) | LF | 291 | $6.17 | $4.90 | $5.20 | $5.47 | $5.00 |
| 0011 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 12,355 | $0.43 | $0.35 | $0.36 | $0.38 | $0.35 |
| 0012 | Reflectorized paint pavement marking (words) (718201) | EACH | 1 | $339.25 | $350.00 | $286.00 | $300.99 | $275.00 |
| 0013 | Reflectorized paint pavement marking (arrows) (718202) | EACH | 2 | $246.73 | $250.00 | $208.00 | $218.90 | $200.00 |
| 0014 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $11,308 | $22,000 | $26,200 | $30,000 | $32,300 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of January 15, 2025. Compiled by Mirage Metrics.