ARDOT contract SA6346 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.72 MILE OF COUNTY ROAD 300 IN SCOTT COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, AGGREGATE BASE COURSE, BASE REPLACEMENT, MAINTENANCE OF TRAFFIC, PATCHING OF EXISTING ROADWAY, AND MISC. ITEMS. Let by Arkansas DOT on April 9, 2025, Scott. 3 bids received; low bid $266,163 by Blackstone Construction, LLC.
- Owner
- Arkansas DOT
- Letting
- 09 APR 2025
- Pay items
- 12
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Blackstone Construction, LLC | $266,163 | Low |
| 2 | Emery Sapp & Sons, Inc. | $362,208 | +36% |
| 3 | Robinson Construction, LLC | $436,759 | +64% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Blackstone Construction, LLC | 2. Emery Sapp & Sons, Inc. | 3. Robinson Construction, LLC |
|---|---|---|---|---|---|---|
| 0001 | Stone backfill (207011) | TON | 980 | $57.35 | $112.57 | $78.20 |
| 0002 | Aggregate base course (class 7) (303117) | TON | 171 | $45.13 | $67.75 | $65.55 |
| 0003 | Prime coat (401002) | GAL | 430 | $6.00 | $4.79 | $12.50 |
| 0004 | Tack coat (401011) | GAL | 965 | $4.25 | $3.76 | $8.25 |
| 0005 | Mineral aggregate in achm surface course (3/8") (407161) | TON | 816 | $124.17 | $130.13 | $192.45 |
| 0006 | Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431) | TON | 53 | $120.00 | $120.00 | $120.00 |
| 0007 | Achm patching of existing roadway (415011) | TON | 415 | $145.00 | $174.28 | $262.00 |
| 0008 | Maintenance of traffic (603009) | LS | 1 | $5,500.00 | $20,086 | $18,000 |
| 0009 | Signs (604003) | SF | 120 | $35.20 | $18.04 | $28.35 |
| 0010 | Geotextile fabric (type 10) (625020) | SY | 1,075 | $6.00 | $7.04 | $15.80 |
| 0011 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 7,603 | $0.53 | $0.54 | $0.60 |
| 0012 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $7,500.00 | $15,819 | $20,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 9, 2025. Compiled by Mirage Metrics.