ARDOT contract SA6346 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.72 MILE OF COUNTY ROAD 300 IN SCOTT COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, AGGREGATE BASE COURSE, BASE REPLACEMENT, MAINTENANCE OF TRAFFIC, PATCHING OF EXISTING ROADWAY, AND MISC. ITEMS. Let by Arkansas DOT on April 9, 2025, Scott. 3 bids received; low bid $266,163 by Blackstone Construction, LLC.

Owner
Arkansas DOT
Letting
09 APR 2025
Pay items
12
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Blackstone Construction, LLC$266,163Low
2Emery Sapp & Sons, Inc.$362,208+36%
3Robinson Construction, LLC$436,759+64%
ARDOT contract SA6346: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Blackstone Construction, LLC2. Emery Sapp & Sons, Inc.3. Robinson Construction, LLC
0001Stone backfill (207011)TON980$57.35$112.57$78.20
0002Aggregate base course (class 7) (303117)TON171$45.13$67.75$65.55
0003Prime coat (401002)GAL430$6.00$4.79$12.50
0004Tack coat (401011)GAL965$4.25$3.76$8.25
0005Mineral aggregate in achm surface course (3/8") (407161)TON816$124.17$130.13$192.45
0006Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431)TON53$120.00$120.00$120.00
0007Achm patching of existing roadway (415011)TON415$145.00$174.28$262.00
0008Maintenance of traffic (603009)LS1$5,500.00$20,086$18,000
0009Signs (604003)SF120$35.20$18.04$28.35
0010Geotextile fabric (type 10) (625020)SY1,075$6.00$7.04$15.80
0011Reflectorized paint pavement marking yellow (4") (718101)LF7,603$0.53$0.54$0.60
0012Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$7,500.00$15,819$20,500
ARDOT contract SA6346: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of April 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy