ARDOT contract SA6650 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO REPLACE A DRAINAGE STRUCTURE ON COUNTY ROAD 12 IN SEVIER COUNTY. THIS PROJECT CONSISTS OF STONE BACKFILL, AGGREGATE BASE COURSE, MAINTENANCE OF TRAFFIC, MINOR DRAINAGE STRUCTURES, PAVEMENT REPAIR OVER CULVERTS, EROSION CONTROL ITEMS, AND MISC. ITEMS. Let by Arkansas DOT on April 9, 2025, Sevier. 5 bids received; low bid $311,510 by Tri State Asphalt, Inc..
- Owner
- Arkansas DOT
- Letting
- 09 APR 2025
- Pay items
- 21
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Tri State Asphalt, Inc. | $311,510 | Low |
| 2 | Redstone Construction Group, Inc. | $402,350 | +29% |
| 3 | Taylor-Hendrix, LLC | $402,634 | +29% |
| 4 | Mobley Contractors, Inc. | $731,778 | +135% |
| 5 | Robinson Construction, LLC | $742,852 | +138% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Tri State Asphalt, Inc. | 2. Redstone Construction Group, Inc. | 3. Taylor-Hendrix, LLC | 4. Mobley Contractors, Inc. | 5. Robinson Construction, LLC |
|---|---|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of pipe culverts (202096) | EACH | 3 | $1,000.00 | $5,629.65 | $4,500.00 | $26,259 | $2,500.00 |
| 0002 | Stone backfill (207001) | TON | 1,800 | $65.00 | $72.62 | $49.25 | $118.89 | $78.65 |
| 0003 | Aggregate base course (class 7) (303117) | TON | 40 | $90.00 | $220.36 | $80.00 | $137.83 | $85.00 |
| 0004 | Maintenance of traffic (603009) | LS | 1 | $12,000 | $37,750 | $40,000 | $156,446 | $165,000 |
| 0005 | Signs (604003) | SF | 262 | $6.00 | $9.45 | $8.40 | $8.10 | $17.25 |
| 0006 | Barricades (604013) | LF | 64 | $25.00 | $18.90 | $35.00 | $33.75 | $26.55 |
| 0007 | Selected pipe bedding (606990) | CY | 85 | $116.30 | $130.00 | $50.00 | $30.74 | $135.00 |
| 0008 | Pavement repair over culverts (asphalt) (615002) | TON | 125 | $250.00 | $325.00 | $535.50 | $573.75 | $425.00 |
| 0009 | Silt fence (621021) | LF | 200 | $20.00 | $5.23 | $7.20 | $6.72 | $25.00 |
| 0010 | Sand bag ditch checks (621031) | BAG | 88 | $44.00 | $14.55 | $12.00 | $18.71 | $24.00 |
| 0011 | Sediment removal and disposal (621111) | CY | 40 | $100.00 | $15.00 | $2.00 | $56.53 | $75.00 |
| 0012 | Rock ditch checks (621151) | CY | 12 | $160.00 | $185.00 | $50.00 | $151.30 | $155.00 |
| 0013 | Filter blanket (816001) | SY | 150 | $80.00 | $16.00 | $6.00 | $34.24 | $85.00 |
| 0014 | Dumped riprap (816011) | CY | 102 | $120.00 | $205.00 | $130.00 | $284.18 | $165.00 |
| 0016 | 117" X 79" aluminum coated corrugated steel arch pipe culvert (12 gauge) (606558) | LF | 180 | $390.00 | $575.00 | $797.00 | $661.31 | |
| 0017 | 117" X 79" polymer precoated metallic coated corrugated steel arch pipe culvert (12 gauge) (606617) | LF | 180 | $1,535.00 | ||||
| 0018 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $14,800 | $18,000 | $17,740 | $34,520 | $35,000 |
| 0019 | Lime (620001) | TON | 1 | $2,500.00 | $131.25 | $500.00 | $168.75 | $650.00 |
| 0020 | Seeding (620011) | ACRE | 0.10 | $12,500 | $13,125 | $8,000.00 | $16,875 | $2,500.00 |
| 0021 | Mulch cover (620022) | ACRE | 0.10 | $12,500 | $13,125 | $8,000.00 | $16,875 | $2,500.00 |
| 0022 | Water (620030) | MGAL | 10.20 | $350.00 | $10.50 | $100.00 | $13.50 | $55.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 9, 2025. Compiled by Mirage Metrics.