FDOT contract T3926 bid tabulation

SR 263 (CAPITAL CIRCLE NW) FROM S OF SR 10 (US 90/TENNESS... Let by Florida DOT on April 30, 2025, Leon, District 3. 4 bids received; low bid $4,037,653 by Peavy & Son Construction Co., Inc..

Owner
Florida DOT
Letting
30 APR 2025
Pay items
107
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Peavy & Son Construction Co., Inc.$4,037,653Low
2C.W. Roberts Contracting, Inc.$4,782,742+18%
3Anderson Columbia Co., Inc.$4,816,562+19%
4Capital Asphalt Inc$11,906,182+195%
FDOT contract T3926: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Peavy & Son Construction Co., Inc.2. C.W. Roberts Contracting, Inc.3. Anderson Columbia Co., Inc.4. Capital Asphalt Inc
0005Mobilization (0101-1)LS1$70,000$286,500$425,785$3,000,000
0010Mobilization (0101-1)LS1$70,000$20,000$50,000$500,000
0015Maintenance of traffic (0102-1)DA1$70,000$262,500$135,047$1,500,000
0020Maintenance of traffic (0102-1)DA1$70,000$35,800$50,000$50,000
0025Traffic control officer (0102-14)HR192$100.00$101.50$100.93$125.00
0030Work zone sign (0102-60)ED19,264$0.25$0.27$0.28$0.30
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED33,404$0.15$0.12$0.05$0.12
0040Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD1,100$0.10$1.10$1.12$1.20
0045Arrow board / advance warning arrow panel (0102-76)ED280$5.50$5.45$5.61$6.00
0050Portable changeable message sign, temporary (0102-99)ED3,520$12.00$11.00$11.22$12.00
0055Temporary signalization and maintenance, intersection (0102-104)ED2,040$23.10$11.00$11.22$12.00
0060Temporary traffic detection and maintenance, intersection (0102-107-1)ED2,040$19.00$16.40$16.82$18.00
0065Type III barricade (0102-115)ED1,008$0.30$0.25$0.28$0.30
0070Sediment barrier (0104-10-3)LF1,073$3.00$2.20$3.36$10.00
0075Inlet protection system (0104-18)EACH100$250.00$160.00$117.12$250.00
0080Litter removal (0107-1)ACRE227.37$50.00$98.00$60.00$540.00
0085Mowing (0107-2)ACRE197.05$50.00$120.00$60.00$670.00
0090Clearing & grubbing (0110-1-1)ACRE1$10,000$1,580.00$4,684.81$25,000
0095Clearing & grubbing (0110-1-1)ACRE1$10,000$6,800.00$8,852.96$5,000.00
0100Removal of existing concrete (0110-4-10)SY485$36.00$34.00$33.27$200.00
0105Regular excavation (0120-1)CY33.90$100.00$47.00$129.81$100.00
0110Borrow excavation, truck measure (0120-2-2)CY50.70$30.00$37.00$5.61$100.00
0115Type B stabilization (0160-4)SY715$8.00$19.00$19.28$50.00
0120Optional base, base group 06 (0285-706)SY461$25.00$34.00$39.04$50.00
0125Milling existing asphalt pavement, 2" avg depth (0327-70-5)SY100,357$0.75$1.32$1.50$7.00
0130Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY34,605$0.75$5.65$1.50$7.00
0135Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN38.20$130.00$230.00$428.65$500.00
0140Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN13,913.60$130.00$147.50$150.00$240.00
0145Reinforcing steel- roadway (0415-1-1)LB69$1.00$4.05$14.67$100.00
0150Inlets, DT bot, type C,<10' (0425-1521)EACH1$7,500.00$5,900.00$3,901.99$25,000
0155Junction box, drainage, P-7, partial (0425-3-43)EACH1$2,500.00$3,100.00$1,830.45$15,000
0160Manhole, adjust (0425-5)EACH9$2,100.00$2,200.00$2,803.38$2,400.00
0165Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF7$150.00$520.00$436.88$1,500.00
0170Concrete curb & gutter, type E (0520-1-7)LF269$45.00$64.00$79.14$270.00
0175Concrete curb & gutter, type F (0520-1-10)LF141$40.00$69.00$103.80$270.00
0180Concrete sidewalk and driveways, 4" thick (0522-1)SY273$95.00$141.50$118.65$270.00
0185Concrete sidewalk and driveways, 6" thick (0522-2)SY151$130.00$184.00$178.74$340.00
0190Detectable warnings (0527-2)SF67$40.00$27.50$38.13$54.00
0195Performance turf, sod (0570-1-2)SY1,644$6.50$7.25$9.37$49.00
0200Raised pavement marker, type B (0706-1-3)EACH3,401$4.20$4.90$5.05$4.80
0205Painted pavement markings, standard, white, solid, 6" (0710-11101)GM9.44$1,575.00$1,300.00$1,345.86$1,800.00
0210Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.55$2,257.00$2,200.00$2,243.10$2,580.00
0215Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF5,186$3.15$3.30$3.36$3.60
0220Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF1,216$3.42$5.45$5.61$3.90
0225Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF3,285$4.00$7.65$7.85$4.50
0230Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM6.31$1,575.00$1,000.00$1,065.47$1,800.00
0235Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM2.61$1,575.00$1,000.00$1,065.47$1,800.00
0240Painted pavement markings, standard, white, message or symbol (0710-11160)EACH68$69.00$76.00$78.51$78.00
0245Painted pavement markings, standard, white, arrows (0710-11170)EACH263$57.75$66.00$67.29$66.00
0250Painted pavement markings, standard, white, yield line (0710-11180)LF36$7.35$11.00$11.22$8.40
0255Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM4.33$1,628.00$1,300.00$1,345.86$1,860.00
0260Painted pavement markings, standard, yellow, solid for interchange and urban island, (0710-11202)GM0.02$2,257.00$1,100.00$2,243.10$2,580.00
0265Painted pavement markings, standard, yellow, skip, 6" (0710-11231)GM0.07$1,331.00$960.00$1,065.47$1,500.00
0270Initial contingency amount, DO not bid (0999-25)LS1$55,889$55,889$55,889$55,889
0275Initial contingency amount, DO not bid (0999-25)LS1$3,250.28$3,250.28$3,250.28$3,250.28
0280Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH16$525.00$490.00$504.61$540.00
0285Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH8$2,890.00$2,500.00$2,607.14$2,790.00
0290Single column ground sign assembly, remove (0700-1600)EACH19$53.00$55.00$56.07$60.00
0295Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114)EACH3$7,508.00$8,500.00$8,712.89$9,324.00
0300Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH86$210.00$170.00$173.80$186.00
0305Sign panel, furnish & install ground mount, 12-20 SF (0700-3102)EACH3$315.00$330.00$336.40$360.00
0310Sign panel, relocate, UP to 12 SF (0700-3501)EACH6$210.00$66.00$67.28$72.00
0315Sign panel, remove, UP to 12 SF (0700-3601)EACH86$47.25$38.00$39.25$42.00
0320Sign panel, remove, 12-20 SF (0700-3602)EACH3$47.25$66.00$67.28$72.00
0325Sign panel, remove, 31-50 SF (0700-3604)EACH3$105.00$130.00$134.57$144.00
0330Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH16$121.00$87.00$89.71$96.00
0335Object marker, type 2 (0705-10-2)EACH9$163.00$60.00$61.67$66.00
0340Raised pavement marker, type B (0706-1-3)EACH3,442$4.20$4.90$5.05$5.40
0345Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF186$3.68$11.00$11.22$12.00
0350Painted pavement markings, surface (0710-90)LS1$73,500$61,000$62,771$67,162
0355Painted pavement markings, surface (0710-90)LS1$3,675.00$940.00$967.11$1,034.00
0360Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF5,186$5.78$4.35$4.49$4.80
0365Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF1,216$6.83$8.75$8.97$9.60
0370Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF1,117$8.40$11.00$11.22$12.00
0375Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM2.66$5,250.00$3,800.00$3,925.42$4,200.00
0380Thermoplastic, standard, message or symbol (0711-11160)EACH19$300.00$140.00$145.80$156.00
0385Thermoplastic, standard, arrow (0711-11170)EACH234$90.00$87.00$89.72$96.00
0390Thermoplastic, standard, yield line (0711-11180)LF36$22.05$22.00$22.43$24.00
0395Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF291$6.83$8.75$8.97$9.60
0400Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.09$5,250.00$3,700.00$3,925.42$4,200.00
0405Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF2,869$16.80$16.40$16.82$18.00
0410Thermoplastic, preformed, white, message (0711-14160)EACH51$168.00$160.00$168.23$180.00
0415Thermoplastic, preformed, white, arrow (0711-14170)EACH51$132.00$120.00$123.37$132.00
0420Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM9.56$6,300.00$4,600.00$4,710.50$5,040.00
0425Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.62$9,450.00$6,500.00$6,729.29$7,200.00
0430Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM6.31$2,678.00$3,800.00$3,925.42$4,200.00
0435Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM4.43$6,300.00$4,600.00$4,710.50$5,040.00
0440Thermoplastic, standard-other surfaces, yellow, solid, 8" (0711-16202)GM0.02$6,825.00$11,000$22,431$24,000
0445Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM0.07$2,678.00$3,500.00$3,925.42$4,200.00
0450Conduit, furnish & install, open trench (0630-2-11)LF2,845$18.00$13.00$13.46$14.40
0455Conduit, furnish & install, directional bore (0630-2-12)LF4,002$37.00$33.00$33.65$36.00
0460Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$11,025$11,000$11,213$12,000
0465Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH54$1,680.00$1,640.00$1,682.03$1,800.00
0470Aluminum signals pole, (0646-1-11)EACH5$3,150.00$4,900.00$5,046.07$5,400.00
0475Steel mast arm assembly, and install, single arm 40' (0649-21-3)EACH1$106,050$120,000$123,348$132,000
0480Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS5$2,310.00$2,200.00$2,242.70$2,400.00
0485Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS4$1,470.00$1,700.00$1,743.69$1,866.00
0490Loop detector inductive, F&I, type 9 (0660-1109)EACH34$420.00$550.00$560.67$600.00
0495Loop assembly- F&I, type A (0660-2101)AS24$1,575.00$1,100.00$1,121.35$1,200.00
0500Loop assembly, F&I, type B (0660-2102)AS58$1,890.00$1,300.00$1,345.62$1,440.00
0505Loop assembly, F&I, type F (0660-2106)AS18$2,310.00$2,200.00$2,242.70$2,400.00
0510Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH2$39,900$48,000$49,339$52,800
0515Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH2$13,000$17,000$17,381$18,600
0520Pedestrian detector, furnish & install, standard (0665-1-11)EACH4$475.00$660.00$672.81$720.00
0525Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH2$1,050.00$870.00$897.08$960.00
0530Manhole, adjust, utilities (0425-5-1)EACH19$2,100.00$2,400.00$2,803.38$2,400.00
0535Valve boxes, adjust (0425-6)EACH62$1,100.00$980.00$1,401.68$1,200.00
FDOT contract T3926: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of April 30, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy