FDOT contract T3946 bid tabulation
SR 87 FROM N OF SR 4 TO ALABAMA STATE LINE. Let by Florida DOT on October 29, 2025, Santa Rosa, District 3. 4 bids received; low bid $2,162,098 by Anderson Columbia Co., Inc..
- Owner
- Florida DOT
- Letting
- 29 OCT 2025
- Pay items
- 40
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Anderson Columbia Co., Inc. | $2,162,098 | Low |
| 2 | Panhandle Grading & Paving, Inc. | $2,813,248 | +30% |
| 3 | C.W. Roberts Contracting, Inc. | $2,944,975 | +36% |
| 4 | Roads, Inc. of NWF | $3,162,802 | +46% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Anderson Columbia Co., Inc. | 2. Panhandle Grading & Paving, Inc. | 3. C.W. Roberts Contracting, Inc. | 4. Roads, Inc. of NWF |
|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $116,789 | $107,500 | $110,000 | $170,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $36,852 | $92,500 | $108,374 | $108,145 |
| 0015 | Work zone sign (0102-60) | ED | 21,645 | $0.15 | $0.28 | $0.40 | $0.40 |
| 0020 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 25,457 | $0.05 | $0.13 | $0.20 | $0.18 |
| 0025 | Portable changeable message sign, temporary (0102-99) | ED | 398 | $15.00 | $27.50 | $30.00 | $30.00 |
| 0030 | Type III barricade (0102-115) | ED | 370 | $0.50 | $0.72 | $0.75 | $1.20 |
| 0035 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 185 | $10.00 | $44.00 | $47.00 | $49.00 |
| 0040 | Sediment barrier (0104-10-3) | LF | 1,930 | $3.20 | $3.43 | $2.95 | $4.00 |
| 0045 | Inlet protection system (0104-18) | EACH | 1 | $233.19 | $500.00 | $470.00 | $350.00 |
| 0050 | Litter removal (0107-1) | ACRE | 456.64 | $20.00 | $60.50 | $53.00 | $60.00 |
| 0055 | Mowing (0107-2) | ACRE | 406.98 | $20.00 | $60.50 | $53.00 | $60.00 |
| 0060 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $10,708 | $10,500 | $8,100.00 | $25,000 |
| 0065 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $11,575 | $11,625 | $47,000 | $25,000 |
| 0070 | Optional base, base group 01 (0285-701) | SY | 1,932 | $9.62 | $6.89 | $27.00 | $30.00 |
| 0075 | Milling existing asphalt pavement, 1" avg depth (0327-70-1) | SY | 133,740 | $0.53 | $2.24 | $2.25 | $1.80 |
| 0080 | Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8) | SY | 117 | $5.07 | $10.50 | $3.05 | $6.40 |
| 0085 | Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52) | TN | 9.60 | $216.04 | $600.00 | $480.00 | $260.00 |
| 0090 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 11,048.80 | $129.04 | $161.65 | $162.50 | $182.00 |
| 0095 | Valve boxes, adjust (0425-6) | EACH | 2 | $695.22 | $950.00 | $930.00 | $800.00 |
| 0100 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 69.20 | $179.30 | $150.00 | $150.00 | $170.00 |
| 0105 | Bedding stone (0530-74) | TN | 37.30 | $202.86 | $150.00 | $220.00 | $200.00 |
| 0110 | Performance turf, sod (0570-1-2) | SY | 20,044 | $3.32 | $3.97 | $4.70 | $3.00 |
| 0115 | Raised pavement marker, type B (0706-1-3) | EACH | 1,329 | $5.83 | $5.50 | $5.90 | $6.00 |
| 0120 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 13.84 | $1,457.40 | $1,815.00 | $2,000.00 | $1,530.00 |
| 0125 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 187 | $5.83 | $2.75 | $2.95 | $6.00 |
| 0130 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 5.13 | $1,457.40 | $1,815.00 | $2,000.00 | $1,530.00 |
| 0135 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 5.04 | $1,165.92 | $390.50 | $420.00 | $1,200.00 |
| 0140 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0145 | Raised rumble strip set- permanent (0546-71-1) | EACH | 1 | $291.48 | $1,760.00 | $1,900.00 | $300.00 |
| 0150 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 19.68 | $2,127.88 | $1,761.82 | $1,900.00 | $1,800.00 |
| 0155 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 10 | $582.96 | $605.00 | $590.00 | $600.00 |
| 0160 | Single column ground sign assembly, remove (0700-1600) | EACH | 8 | $116.59 | $55.00 | $120.00 | $120.00 |
| 0165 | Object marker, type 1 (0705-10-1) | EACH | 3 | $291.48 | $220.00 | $300.00 | $300.00 |
| 0170 | Object marker, type 2 (0705-10-2) | EACH | 13 | $215.70 | $385.00 | $220.00 | $220.00 |
| 0175 | Raised pavement marker, type B (0706-1-3) | EACH | 1,329 | $5.83 | $5.50 | $5.90 | $6.00 |
| 0180 | Painted pavement markings, surface (0710-90) | LS | 1 | $69,218 | $56,650 | $61,000 | $70,000 |
| 0185 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 187 | $11.66 | $9.35 | $10.00 | $12.00 |
| 0190 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 13.84 | $5,246.64 | $4,400.00 | $4,700.00 | $5,500.00 |
| 0195 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 5.13 | $5,246.64 | $4,400.00 | $4,700.00 | $5,500.00 |
| 0200 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 5.04 | $4,080.72 | $1,540.00 | $1,700.00 | $4,200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of October 29, 2025. Compiled by Mirage Metrics.