FDOT contract T3984 bid tabulation
SR 77 FROM 23RD ST TO CR 2312 (BALDWIN RD). Let by Florida DOT on October 29, 2025, Bay, District 3. 4 bids received; low bid $2,787,910 by Phoenix Construction Services, Inc..
- Owner
- Florida DOT
- Letting
- 29 OCT 2025
- Pay items
- 42
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Phoenix Construction Services, Inc. | $2,787,910 | Low |
| 2 | Anderson Columbia Co., Inc. | $2,790,079 | 0.0% |
| 3 | C.W. Roberts Contracting, Inc. | $3,394,844 | +22% |
| 4 | Maer Homes, LLC | $3,559,116 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Phoenix Construction Services, Inc. | 2. Anderson Columbia Co., Inc. | 3. C.W. Roberts Contracting, Inc. | 4. Maer Homes, LLC |
|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $278,000 | $274,046 | $385,000 | $344,210 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $366,002 | $160,612 | $377,789 | $259,800 |
| 0015 | Commercial material for temporary driveway maintenance (0102-3) | CY | 48.20 | $62.50 | $74.27 | $173.60 | $150.00 |
| 0020 | Work zone sign (0102-60) | ED | 20,300 | $0.26 | $0.15 | $0.33 | $1.00 |
| 0025 | Business sign (0102-61) | EACH | 22 | $60.00 | $57.63 | $54.67 | $75.00 |
| 0030 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 1,074 | $65.00 | $10.00 | $75.00 | $65.00 |
| 0035 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 10,950 | $13.00 | $1.00 | $16.40 | $22.00 |
| 0040 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 15,600 | $0.20 | $0.12 | $0.12 | $1.00 |
| 0045 | Arrow board / advance warning arrow panel (0102-76) | ED | 700 | $8.00 | $2.67 | $5.47 | $15.00 |
| 0050 | Portable changeable message sign, temporary (0102-99) | ED | 700 | $20.00 | $4.83 | $13.12 | $25.00 |
| 0055 | Type III barricade (0102-115) | ED | 1,400 | $1.20 | $0.10 | $0.38 | $1.00 |
| 0060 | Sediment barrier (0104-10-3) | LF | 6,336 | $3.80 | $2.85 | $5.60 | $6.00 |
| 0065 | Inlet protection system (0104-18) | EACH | 11 | $500.00 | $293.30 | $379.77 | $1,500.00 |
| 0070 | Litter removal (0107-1) | ACRE | 22.40 | $205.00 | $51.46 | $437.40 | $550.00 |
| 0075 | Mowing (0107-2) | ACRE | 22.40 | $205.00 | $51.46 | $437.40 | $550.00 |
| 0080 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $154,000 | $158,061 | $100,000 | $100,000 |
| 0085 | Removal of existing concrete (0110-4-10) | SY | 1,029 | $13.00 | $69.73 | $16.22 | $25.00 |
| 0090 | Regular excavation (0120-1) | CY | 749.90 | $129.00 | $135.84 | $202.58 | $25.00 |
| 0095 | Borrow excavation, truck measure (0120-2-2) | CY | 4,020.50 | $20.50 | $10.00 | $6.00 | $41.00 |
| 0100 | Optional base, base group 01 (0285-701) | SY | 3,075 | $22.60 | $45.95 | $48.90 | $25.00 |
| 0105 | Turnout base- optional materials (0286-1) | SY | 355 | $26.00 | $57.64 | $39.27 | $65.00 |
| 0110 | Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52) | TN | 29.30 | $280.00 | $524.87 | $530.57 | $399.00 |
| 0115 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 165.20 | $1,855.00 | $1,584.93 | $1,683.77 | $2,000.00 |
| 0120 | Inlets, closed flume (0425-1910) | EACH | 41 | $3,800.00 | $4,798.04 | $5,076.07 | $5,900.00 |
| 0125 | Inlets, adjust (0425-4) | EACH | 10 | $2,500.00 | $11,296 | $1,576.31 | $3,950.00 |
| 0130 | Manhole, adjust, utilities (0425-5-1) | EACH | 4 | $2,500.00 | $1,531.66 | $1,693.32 | $3,950.00 |
| 0135 | Valve boxes, adjust (0425-6) | EACH | 3 | $1,900.00 | $1,780.68 | $1,019.67 | $1,000.00 |
| 0140 | Pedestrian / bicycle railing, NS, 42" type 1 (0515-2111) | LF | 890 | $75.00 | $90.66 | $101.15 | $131.00 |
| 0145 | Concrete curb & gutter, type E (0520-1-7) | LF | 5,920 | $25.50 | $47.49 | $47.45 | $62.00 |
| 0150 | Concrete curb & gutter, type F (0520-1-10) | LF | 5,495 | $25.65 | $46.17 | $64.22 | $62.00 |
| 0155 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 3,572 | $89.50 | $74.01 | $70.39 | $85.00 |
| 0160 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 1,305 | $106.50 | $103.49 | $143.26 | $110.00 |
| 0165 | Detectable warnings (0527-2) | SF | 309 | $40.00 | $38.62 | $24.60 | $55.00 |
| 0170 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 3.80 | $249.00 | $528.65 | $1,089.75 | $320.00 |
| 0175 | Bedding stone (0530-74) | TN | 2.80 | $95.00 | $738.82 | $381.09 | $300.00 |
| 0180 | Performance turf, sod (0570-1-2) | SY | 6,036 | $5.00 | $11.57 | $10.21 | $11.00 |
| 0185 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 2 | $622.00 | $518.70 | $546.75 | $725.00 |
| 0190 | Single column ground sign assembly, relocate (0700-1500) | EACH | 22 | $250.00 | $144.09 | $164.02 | $250.00 |
| 0195 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 521 | $7.00 | $11.53 | $7.07 | $35.00 |
| 0200 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 43 | $13.00 | $17.29 | $14.14 | $48.00 |
| 0205 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 152 | $3.50 | $8.07 | $5.89 | $35.00 |
| 0210 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of October 29, 2025. Compiled by Mirage Metrics.