FDOT contract T3990 bid tabulation
SR 30 (US 98) FROM WAKULLA CO LINE TO TAYLOR CO LINE. Let by Florida DOT on January 28, 2026, Jefferson, District 3. 5 bids received; low bid $4,358,438 by Anderson Columbia Co., Inc..
- Owner
- Florida DOT
- Letting
- 28 JAN 2026
- Pay items
- 60
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Anderson Columbia Co., Inc. | $4,358,438 | Low |
| 2 | Capital Asphalt Inc | $4,776,153 | +10% |
| 3 | C.W. Roberts Contracting, Inc. | $4,782,835 | +10% |
| 4 | Peavy & Son Construction Co., Inc. | $5,331,217 | +22% |
| 5 | Pigott Asphalt and Sitework LLC | $5,394,054 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Anderson Columbia Co., Inc. | 2. Capital Asphalt Inc | 3. C.W. Roberts Contracting, Inc. | 4. Peavy & Son Construction Co., Inc. | 5. Pigott Asphalt and Sitework LLC |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $277,424 | $380,000 | $238,000 | $300,000 | $500,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $155,799 | $145,000 | $226,000 | $250,000 | $185,000 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $9,909.16 | $75,000 | $5,000.00 | $40,000 | $7,500.00 |
| 0020 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $8,136.65 | $110,000 | $5,000.00 | $50,000 | $5,000.00 |
| 0025 | Work zone sign (0102-60) | ED | 5,545 | $0.15 | $0.30 | $0.30 | $0.25 | $0.30 |
| 0030 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 1,210 | $22.61 | $40.00 | $12.00 | $17.00 | $1.00 |
| 0035 | Temporary barrier, relocate, anchored (0102-71-25) | LF | 1,009 | $7.70 | $15.00 | $5.00 | $10.00 | $1.00 |
| 0040 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 12,838 | $0.05 | $0.15 | $0.10 | $0.13 | $4.00 |
| 0045 | Temporary raised/retroreflective pavement marker, type D (0102-78-1) | EACH | 1,956 | $5.61 | $5.25 | $5.60 | $31.00 | $5.00 |
| 0050 | Temporary crash cushion, redirective option (0102-89-1) | LO | 8 | $750.43 | $1,050.00 | $1,117.95 | $1,030.00 | $100.00 |
| 0055 | Portable changeable message sign, temporary (0102-99) | ED | 942 | $7.58 | $13.50 | $14.55 | $13.40 | $1.00 |
| 0060 | Type III barricade (0102-115) | ED | 30 | $1.00 | $1.50 | $1.10 | $1.03 | $5.00 |
| 0065 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 195 | $5.64 | $35.00 | $33.55 | $31.00 | $25.00 |
| 0070 | Artificial coverings /rolled erosion control products (0104-1) | SY | 229 | $11.21 | $35.00 | $10.55 | $300.00 | $5.00 |
| 0075 | Sediment barrier (0104-10-3) | LF | 32,594 | $3.36 | $2.00 | $2.20 | $5.00 | $1.00 |
| 0080 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 1,240 | $22.43 | $12.00 | $11.20 | $15.00 | $1.00 |
| 0085 | Soil tracking prevention device (0104-15) | EACH | 2 | $280.36 | $4,000.00 | $3,009.60 | $5,000.00 | $1,500.00 |
| 0090 | Inlet protection system (0104-18) | EACH | 2 | $392.50 | $250.00 | $167.70 | $250.00 | $150.00 |
| 0095 | Litter removal (0107-1) | ACRE | 654.75 | $5.61 | $15.00 | $25.00 | $60.00 | $10.00 |
| 0100 | Mowing (0107-2) | ACRE | 565.77 | $5.61 | $50.00 | $25.00 | $60.00 | $40.00 |
| 0105 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $19,212 | $10,000 | $107,406 | $20,000 | $50,000 |
| 0110 | Borrow excavation, truck measure (0120-2-2) | CY | 54 | $55.94 | $55.00 | $46.40 | $40.00 | $150.00 |
| 0115 | Type B stabilization (0160-4) | SY | 55 | $61.82 | $50.00 | $25.90 | $10.00 | $50.00 |
| 0120 | Optional base, base group 03 (0285-703) | SY | 821 | $45.39 | $25.00 | $25.95 | $30.00 | $50.00 |
| 0125 | Optional base, base group 09 (0285-709) | SY | 58 | $73.52 | $84.00 | $114.55 | $35.00 | $185.00 |
| 0130 | Optional base, base group 11 (0285-711) | SY | 36 | $246.15 | $140.00 | $210.30 | $30.00 | $250.00 |
| 0135 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 141 | $2.55 | $25.00 | $7.50 | $3.00 | $10.00 |
| 0140 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 99,923 | $0.88 | $1.25 | $3.05 | $2.55 | $2.00 |
| 0145 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 940 | $1.76 | $7.00 | $2.35 | $1.75 | $5.00 |
| 0150 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 41,603 | $0.78 | $2.50 | $2.25 | $1.00 | $1.90 |
| 0155 | Milling existing asphalt pavement, 3 1/4" avg depth (0327-70-17) | SY | 2,029 | $2.39 | $3.50 | $2.95 | $3.00 | $5.00 |
| 0160 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 8,493 | $159.57 | $150.00 | $136.00 | $158.00 | $171.00 |
| 0165 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 12,271.10 | $132.70 | $140.00 | $145.05 | $158.00 | $168.00 |
| 0170 | Pipe culvert, opt material, round, 36"S/CD (0430-175136) | LF | 77 | $304.95 | $420.00 | $928.00 | $250.00 | $600.00 |
| 0175 | Straight concrete endwalls, single, 0 degrees, round (0430-536100) | EACH | 1 | $10,166 | $12,500 | $15,816 | $20,000 | $10,000 |
| 0180 | Mitered end section, optional round, 36" CD (0430-982138) | EACH | 1 | $8,404.34 | $8,650.00 | $6,609.55 | $7,000.00 | $7,500.00 |
| 0185 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 8 | $502.13 | $420.00 | $444.15 | $150.00 | $300.00 |
| 0190 | Bedding stone (0530-74) | TN | 5.80 | $543.96 | $420.00 | $299.80 | $200.00 | $300.00 |
| 0195 | Performance turf, sod (0570-1-2) | SY | 22,940 | $1.12 | $3.00 | $3.20 | $3.50 | $4.00 |
| 0200 | Raised pavement marker, type B (0706-1-3) | EACH | 4,739 | $5.31 | $5.25 | $5.60 | $4.65 | $5.00 |
| 0205 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 37.70 | $1,434.15 | $1,415.00 | $1,509.50 | $1,545.00 | $1,500.00 |
| 0210 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 140 | $5.31 | $5.25 | $5.60 | $3.61 | $7.00 |
| 0215 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 13.78 | $1,434.15 | $1,415.00 | $1,508.75 | $1,545.00 | $1,500.00 |
| 0220 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 13.39 | $743.63 | $725.00 | $782.50 | $1,500.00 | $1,000.00 |
| 0225 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0230 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 22.15 | $2,110.70 | $1,500.00 | $2,487.80 | $2,200.00 | $1,450.00 |
| 0235 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 8 | $478.05 | $470.00 | $503.05 | $565.00 | $575.00 |
| 0240 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 4 | $2,124.67 | $2,100.00 | $2,235.90 | $2,138.00 | $2,100.00 |
| 0245 | Single column ground sign assembly, remove (0700-1600) | EACH | 12 | $42.49 | $42.00 | $44.70 | $67.00 | $100.00 |
| 0250 | Multi-column ground sign assembly, F&I ground mount, than 12 SF (0700-2111) | EACH | 2 | $3,293.24 | $3,200.00 | $3,465.65 | $4,640.00 | $5,000.00 |
| 0255 | Multi-column ground sign assembly, F&I ground mount, 20.0 SF (0700-2112) | EACH | 8 | $4,143.10 | $4,000.00 | $4,360.00 | $5,871.00 | $6,000.00 |
| 0260 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 8 | $265.58 | $260.00 | $279.50 | $465.00 | $500.00 |
| 0265 | Object marker, type 1 (0705-10-1) | EACH | 3 | $292.14 | $285.00 | $307.45 | $310.00 | $350.00 |
| 0270 | Object marker, type 2 (0705-10-2) | EACH | 20 | $69.05 | $68.00 | $72.65 | $180.00 | $185.00 |
| 0275 | Raised pavement marker, type B (0706-1-3) | EACH | 1,327 | $5.31 | $5.25 | $5.60 | $4.65 | $5.00 |
| 0280 | Painted pavement markings, surface (0710-90) | LS | 1 | $39,416 | $36,750 | $39,142 | $40,170 | $45,000 |
| 0285 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 56 | $10.62 | $10.50 | $11.20 | $8.00 | $13.00 |
| 0290 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 14.82 | $5,099.20 | $5,000.00 | $5,366.60 | $5,665.00 | $5,600.00 |
| 0295 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 5.23 | $5,099.20 | $5,000.00 | $5,359.80 | $5,665.00 | $5,600.00 |
| 0300 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 5.35 | $4,249.34 | $4,200.00 | $4,470.00 | $2,175.00 | $4,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of January 28, 2026. Compiled by Mirage Metrics.