IDOT contract 46941 bid tabulation
Section SR. Let by Illinois DOT on June 13, 2025, Lasalle, District 03. 6 bids received; low bid $513,534 by Advanced Asphalt Company.
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 14
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Advanced Asphalt Company | $513,534 | Low |
| 2 | Gillan Construction LLC | $534,444 | +4.0% |
| 3 | G. M. Sipes Construction, Inc. | $612,830 | +19% |
| 4 | D. Construction, Inc. | $627,474 | +22% |
| 5 | Gensini Excavating, Inc. | $765,466 | +49% |
| 6 | Davis Concrete Construction Co. | $811,053 | +58% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Advanced Asphalt Company | 2. Gillan Construction LLC | 3. G. M. Sipes Construction, Inc. | 4. D. Construction, Inc. | 5. Gensini Excavating, Inc. | 6. Davis Concrete Construction Co. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Traf cont & prot SPL (X7010216) | LS | 1 | $8,325.00 | $8,250.00 | $1,000.00 | $5,000.00 | $7,500.00 | $10,000 |
| 2 | Stone riprap CL A4 (28100107) | SY | 11 | $114.00 | $90.00 | $250.00 | $200.00 | $90.00 | $100.00 |
| 3 | Comb curb gutter rem (44000500) | LF | 50 | $80.00 | $52.00 | $40.00 | $20.00 | $25.00 | $20.00 |
| 4 | Welded wire reinf (44200050) | SY | 3,484 | $9.00 | $8.50 | $0.01 | $15.00 | $10.00 | $10.00 |
| 5 | CL B patch T2 6 (44200905) | SY | 256 | $110.00 | $86.00 | $180.00 | $110.00 | $151.28 | $155.00 |
| 6 | CL B patch T3 6 (44200909) | SY | 382 | $100.00 | $86.00 | $180.00 | $110.00 | $151.28 | $145.00 |
| 7 | CL B patch T4 6 (44200911) | SY | 2,847 | $85.00 | $86.00 | $130.00 | $110.00 | $151.28 | $135.00 |
| 8 | Dowel bars 1 (44201297) | EACH | 3,474 | $12.00 | $20.00 | $0.01 | $18.00 | $20.00 | $12.00 |
| 9 | Saw cuts (44213200) | LF | 7,000 | $1.75 | $3.00 | $8.50 | $5.00 | $3.30 | $3.00 |
| 10 | Tie bars 3/4 (44213204) | EACH | 2,046 | $11.00 | $15.00 | $0.01 | $12.00 | $15.00 | $10.00 |
| 11 | Insert cul lin 36 (54390230) | LF | 60 | $490.00 | $330.00 | $345.00 | $450.00 | $450.00 | $2,225.00 |
| 12 | Mobilization (67100100) | LS | 1 | $28,750 | $24,000 | $16,000 | $0.01 | $15,000 | $40,500 |
| 13 | Mod ureth PM line 4 (78009004) | LF | 9,500 | $1.35 | $1.49 | $1.42 | $1.82 | $1.56 | $1.50 |
| 14 | GRV RCSD PVT MRKG 5 (78011025) | LF | 9,500 | $1.35 | $1.49 | $1.30 | $1.82 | $1.43 | $1.40 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.