IDOT contract 61K61 bid tabulation
Bolingbrook, section 10-00055-00-BR. Let by Illinois DOT on April 25, 2025, Will, District 01. 6 bids received; low bid $753,049 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 48
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $753,049 | Low |
| 2 | Austin Tyler Construction, Inc. | $797,761 | +6.0% |
| 3 | Alliance Contractors, Inc. | $884,175 | +17% |
| 4 | Everlast Blacktop Inc. | $940,193 | +25% |
| 5 | Scanlon Excavating & Concrete, Inc. | $965,355 | +28% |
| 6 | Acqua Contractors Corp | $1,060,000 | +41% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Austin Tyler Construction, Inc. | 3. Alliance Contractors, Inc. | 4. Everlast Blacktop Inc. | 5. Scanlon Excavating & Concrete, Inc. | 6. Acqua Contractors Corp |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Ornamental fence (XX001249) | LF | 78 | $267.11 | $242.00 | $546.60 | $359.00 | $425.00 | $280.00 |
| 2 | Slope wall rem var (XX009707) | LS | 1 | $6,500.00 | $2,000.00 | $3,500.00 | $12,000 | $20,000 | $12,000 |
| 3 | Inl RSR STR (O B) (X1200058) | EACH | 4 | $2,750.00 | $1,230.00 | $1,250.00 | $3,950.00 | $6,500.00 | $1,035.00 |
| 4 | Selective clearing (X2010514) | ACRE | 0.10 | $18,150 | $15,000 | $15,000 | $1,000.00 | $150,000 | $12,000 |
| 5 | Eros cont blanket SPL (X2511630) | SY | 239 | $3.03 | $2.50 | $2.50 | $8.00 | $7.00 | $3.50 |
| 6 | Dewatering (X5021507) | LS | 1 | $10,000 | $25,000 | $1.00 | $80,000 | $55,000 | $50,000 |
| 7 | Memb WTRPRF sys B STR (X5810103) | SY | 375 | $50.00 | $46.00 | $50.00 | $70.00 | $75.00 | $60.00 |
| 8 | Traf cont & prot SPL (X7010216) | LS | 1 | $15,000 | $13,000 | $7,525.00 | $32,000 | $50,000 | $13,000 |
| 9 | Maint lighting systm (X8000003) | CAL MO | 1 | $11,000 | $1,200.00 | $19,000 | $1,450.00 | $2,500.00 | $1,400.00 |
| 10 | Construction layout (Z0013798) | LS | 1 | $10,500 | $9,200.00 | $5,500.00 | $8,000.00 | $15,000 | $6,400.00 |
| 11 | Rock fill (Z0054400) | CY | 145 | $55.00 | $129.00 | $65.00 | $68.00 | $100.00 | $140.00 |
| 12 | Tree remov 6-15 (20100110) | UNIT | 20 | $60.50 | $75.00 | $75.00 | $80.00 | $25.00 | $23.00 |
| 13 | Earth excavation (20200100) | CY | 37 | $100.00 | $82.00 | $10.00 | $60.00 | $55.00 | $150.00 |
| 14 | Rem & disp uns matl (20201200) | CY | 145 | $50.00 | $43.00 | $15.00 | $60.00 | $70.00 | $150.00 |
| 15 | Channel excavation (20300100) | CY | 83 | $50.00 | $87.00 | $15.00 | $100.00 | $65.00 | $150.00 |
| 16 | Porous gran embank (20700220) | CY | 198 | $55.00 | $84.00 | $50.00 | $68.00 | $70.00 | $225.00 |
| 17 | Topsoil F & P 6 (21101625) | SY | 423 | $11.00 | $12.00 | $12.00 | $9.00 | $12.00 | $15.00 |
| 18 | Seeding CL 1 (25000100) | ACRE | 0.25 | $4,180.00 | $3,600.00 | $3,600.00 | $2,000.00 | $5,000.00 | $26,715 |
| 19 | Sodding salt tolerant (25200110) | SY | 184 | $36.30 | $28.00 | $28.00 | $18.00 | $25.00 | $14.00 |
| 20 | Temp eros contr seed (28000250) | LB | 10 | $6.60 | $6.00 | $6.00 | $10.00 | $5.00 | $6.00 |
| 21 | Perimeter eros bar (28000400) | LF | 625 | $3.03 | $3.00 | $3.00 | $2.00 | $5.00 | $3.50 |
| 22 | Inlet filters (28000510) | EACH | 4 | $313.50 | $0.01 | $25.00 | $200.00 | $150.00 | $190.00 |
| 23 | Temp eros contr blank (28001100) | SY | 423 | $1.93 | $1.50 | $1.50 | $2.00 | $1.00 | $2.60 |
| 24 | Stone riprap CL B4 (28100127) | SY | 248 | $75.00 | $80.00 | $135.00 | $92.00 | $75.00 | $112.00 |
| 25 | Filter fabric (28200200) | SY | 248 | $5.00 | $5.00 | $1.00 | $2.00 | $5.00 | $1.20 |
| 26 | Agg subgrade impr 12 (30300112) | SY | 426 | $20.00 | $18.00 | $24.00 | $18.00 | $21.00 | $64.00 |
| 27 | Bit matls PR CT (40600275) | LB | 825 | $0.01 | $0.01 | $0.01 | $0.01 | $0.10 | $0.12 |
| 28 | Bit matls tack CT (40600290) | LB | 330 | $0.01 | $0.01 | $0.01 | $0.01 | $0.10 | $0.12 |
| 29 | HMA BC IL-19.0 N50 (40603080) | TON | 144 | $9.00 | $100.00 | $195.94 | $170.00 | $225.00 | $228.00 |
| 30 | HMA SC IL-9.5 D N50 (40604060) | TON | 42 | $100.00 | $110.00 | $232.95 | $170.00 | $320.00 | $270.00 |
| 31 | PC conc sidewalk 5 (42400200) | SF | 675 | $10.00 | $11.50 | $13.00 | $13.00 | $13.00 | $14.00 |
| 32 | Pavement rem (44000100) | SY | 367 | $12.00 | $18.00 | $25.00 | $18.00 | $15.00 | $40.00 |
| 33 | Comb curb gutter rem (44000500) | LF | 200 | $10.00 | $15.00 | $15.00 | $8.00 | $8.00 | $29.00 |
| 34 | Sidewalk rem (44000600) | SF | 608 | $5.00 | $4.00 | $3.00 | $2.00 | $2.00 | $10.00 |
| 35 | Pipe culvert remov (50105220) | LF | 362 | $35.00 | $45.00 | $50.00 | $80.00 | $85.00 | $50.00 |
| 36 | Structure excavation (50200100) | CY | 673 | $35.00 | $47.50 | $15.00 | $57.00 | $55.00 | $105.00 |
| 37 | Reinf bars, epoxy CTD (50800205) | LB | 3,430 | $4.00 | $2.50 | $6.80 | $4.00 | $10.00 | $2.90 |
| 38 | Name plates (51500100) | EACH | 1 | $1,000.00 | $870.00 | $1,000.00 | $1,100.00 | $1,000.00 | $1,000.00 |
| 39 | Box cul end sec C1 (54001001) | EACH | 3 | $8,000.00 | $8,530.00 | $6,180.00 | $12,400 | $12,000 | $13,300 |
| 40 | Conc box cul (54003000) | CY | 21.70 | $1,400.00 | $2,940.00 | $3,215.00 | $3,600.00 | $1,850.00 | $2,560.00 |
| 41 | PCBC 7X5 (54010705) | LF | 360 | $1,000.00 | $985.00 | $1,110.00 | $867.00 | $800.00 | $1,010.00 |
| 42 | FR & grates T3 (60404300) | EACH | 4 | $700.00 | $500.00 | $750.00 | $800.00 | $550.00 | $600.00 |
| 43 | Comb CC&G TM6.12 (60609200) | LF | 200 | $44.00 | $68.00 | $44.50 | $60.00 | $50.00 | $98.00 |
| 44 | Mobilization (67100100) | LS | 1 | $42,000 | $32,000 | $53,000 | $52,275 | $50,000 | $62,434 |
| 45 | Changeable message SN (70107025) | CAL DAY | 28 | $100.00 | $45.00 | $40.00 | $50.00 | $50.00 | $40.00 |
| 46 | Remov sin pan assy TA (72400100) | EACH | 4 | $330.00 | $100.00 | $75.00 | $110.00 | $150.00 | $120.00 |
| 47 | Undrgrd C galvs 2 (81028200) | LF | 308 | $55.00 | $46.00 | $86.20 | $50.00 | $95.00 | $53.00 |
| 48 | EC C XLP use 3-1C 6 (81702415) | LF | 321 | $16.50 | $14.00 | $11.60 | $15.00 | $15.00 | $16.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way