IDOT contract 61L12 bid tabulation
Matteson, section 23-00068-00-RS. Let by Illinois DOT on March 7, 2025, Cook, District 01. 5 bids received; low bid $824,771 by Gallagher Asphalt Corporation.
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 64
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Gallagher Asphalt Corporation | $824,771 | Low |
| 2 | P. T. Ferro Construction Co. | $826,420 | 0.0% |
| 3 | Iroquois Paving Corporation | $828,232 | 0.0% |
| 4 | K-Five Construction Corporation | $880,515 | +7.0% |
| 5 | D. Construction, Inc. | $1,002,651 | +22% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gallagher Asphalt Corporation | 2. P. T. Ferro Construction Co. | 3. Iroquois Paving Corporation | 4. K-Five Construction Corporation | 5. D. Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Prun safety/equip CLR (K1004595) | LS | 1 | $7,605.00 | $1.00 | $8,200.00 | $7,000.00 | $9,652.50 |
| 2 | Det loop repl (X8860105) | LF | 80 | $37.00 | $34.13 | $0.01 | $34.13 | $37.54 |
| 3 | HMA driveway pavt 4 (Z0004514) | SY | 60 | $56.00 | $60.00 | $100.00 | $130.00 | $40.00 |
| 4 | Drain util STR adj (Z0017400) | EACH | 90 | $967.00 | $1.00 | $550.00 | $800.00 | $800.00 |
| 5 | Drain util STR recon (Z0017700) | EACH | 3 | $2,336.00 | $1,500.00 | $1,500.00 | $1,800.00 | $1,200.00 |
| 6 | Temp info signing (Z0030850) | SF | 26 | $32.60 | $25.00 | $0.80 | $30.00 | $30.00 |
| 7 | Tree trunk protection (20101100) | EACH | 2 | $217.25 | $250.00 | $210.00 | $200.00 | $330.00 |
| 8 | Tree root pruning (20101200) | EACH | 2 | $217.25 | $800.00 | $210.00 | $200.00 | $880.00 |
| 9 | Rem & disp uns matl (20201200) | CY | 15 | $75.60 | $100.00 | $0.01 | $1.00 | $100.00 |
| 10 | Topsoil F & P 4 (21101615) | SY | 750 | $14.15 | $15.00 | $6.00 | $10.00 | $6.60 |
| 11 | Nitrogen fert nutr (25000400) | LB | 9 | $8.70 | $10.00 | $4.15 | $3.00 | $4.40 |
| 12 | Phosphorus fert nutr (25000500) | LB | 9 | $8.70 | $10.00 | $4.15 | $3.00 | $4.40 |
| 13 | Potassium fert nutr (25000600) | LB | 9 | $8.70 | $10.00 | $4.15 | $3.00 | $4.40 |
| 14 | Sodding salt tolerant (25200110) | SY | 750 | $15.20 | $50.00 | $18.00 | $18.00 | $18.70 |
| 15 | Supple watering (25200200) | UNIT | 40 | $97.80 | $0.75 | $0.01 | $20.00 | $0.01 |
| 16 | Inlet filters (28000510) | EACH | 37 | $217.25 | $0.01 | $135.00 | $175.00 | $138.60 |
| 17 | Agg subgrade improve (30300001) | CY | 15 | $103.00 | $100.00 | $0.01 | $1.00 | $65.00 |
| 18 | Agg base cse B 4 (35101600) | SY | 620 | $7.50 | $0.01 | $0.01 | $17.86 | $9.00 |
| 19 | Aggregate-temp access (40201000) | TON | 85 | $0.01 | $0.01 | $0.01 | $140.50 | $30.00 |
| 20 | Bit matls tack CT (40600290) | LB | 9,310 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 21 | Long joint sealant (40600370) | LF | 3,755 | $3.95 | $4.00 | $4.50 | $4.50 | $4.25 |
| 22 | Mix CR JTS flangewys (40600400) | TON | 21 | $280.00 | $0.01 | $0.01 | $50.00 | $0.01 |
| 23 | HMA surf rem butt JT (40600982) | SY | 230 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 24 | HMA BC IL-19.0 N50 (40603080) | TON | 1,790 | $76.00 | $83.00 | $82.00 | $82.00 | $82.00 |
| 25 | HMA SC IL-9.5 D N50 (40604060) | TON | 1,195 | $88.00 | $88.00 | $90.00 | $95.00 | $87.00 |
| 26 | PCC driveway pavt 7 (42300300) | SY | 160 | $101.00 | $110.00 | $100.00 | $89.00 | $104.50 |
| 27 | PC conc sidewalk 5 (42400200) | SF | 5,550 | $8.10 | $10.50 | $10.50 | $6.06 | $10.73 |
| 28 | Detectable warnings (42400800) | SF | 590 | $17.40 | $23.00 | $45.00 | $33.61 | $46.20 |
| 29 | HMA surf rem 3 1/2 (44000163) | SY | 13,790 | $3.35 | $5.00 | $4.85 | $4.00 | $4.00 |
| 30 | Drive pavement rem (44000200) | SY | 220 | $29.20 | $22.00 | $35.00 | $32.50 | $12.00 |
| 31 | Comb curb gutter rem (44000500) | LF | 2,765 | $13.10 | $18.00 | $12.50 | $15.90 | $10.00 |
| 32 | Sidewalk rem (44000600) | SF | 5,600 | $2.80 | $3.00 | $2.65 | $2.89 | $3.00 |
| 33 | CL D patch T1 11 (44201773) | SY | 15 | $421.00 | $175.00 | $35.00 | $34.00 | $110.00 |
| 34 | CL D patch T2 11 (44201777) | SY | 20 | $250.00 | $150.00 | $35.00 | $34.00 | $110.00 |
| 35 | CL D patch T3 11 (44201781) | SY | 25 | $147.00 | $125.00 | $35.00 | $34.00 | $110.00 |
| 36 | CL D patch T4 11 (44201783) | SY | 130 | $126.00 | $105.00 | $35.00 | $34.00 | $110.00 |
| 37 | Valve box adj (60266600) | EACH | 4 | $600.00 | $350.00 | $850.00 | $900.00 | $500.00 |
| 38 | FR & grates T11 (60404800) | EACH | 4 | $955.00 | $600.00 | $625.00 | $900.00 | $800.00 |
| 39 | Comb CC&G TY B-6.24 (60605000) | LF | 2,765 | $46.00 | $44.00 | $58.00 | $45.21 | $56.10 |
| 40 | Mobilization (67100100) | LS | 1 | $39,500 | $45,000 | $46,000 | $53,000 | $60,150 |
| 41 | TR cont & prot 701501 (70102620) | LS | 1 | $1,630.00 | $10,000 | $2,500.00 | $11,700 | $31,440 |
| 42 | TR cont & prot 701606 (70102625) | LS | 1 | $1,630.00 | $10,000 | $1.00 | $10,500 | $0.01 |
| 43 | TR cont & prot 701701 (70102635) | LS | 1 | $54.30 | $50.00 | $1.00 | $500.00 | $0.01 |
| 44 | TR cont & prot 701801 (70102640) | LS | 1 | $1,195.00 | $10,000 | $1.00 | $2,500.00 | $0.01 |
| 45 | Changeable message SN (70107025) | CAL DAY | 150 | $16.30 | $15.00 | $0.01 | $15.00 | $60.00 |
| 46 | Short term pavt mking (70300100) | LF | 1,420 | $0.85 | $0.01 | $0.01 | $1.00 | $1.00 |
| 47 | SHRT TRM pavt MK rem (70300150) | SF | 475 | $0.01 | $0.01 | $0.01 | $2.00 | $2.00 |
| 48 | Temp PVT MK LTR & sym paint (70300211) | SF | 450 | $0.01 | $0.01 | $0.01 | $1.60 | $10.00 |
| 49 | Temp PVT MK line 4 - paint (70300221) | LF | 5,970 | $0.01 | $0.01 | $0.01 | $0.23 | $1.00 |
| 50 | Temp PVT MK line 6 - paint (70300241) | LF | 9,105 | $0.01 | $0.01 | $0.01 | $0.33 | $2.00 |
| 51 | Temp PVT MK line 8 - paint (70300251) | LF | 540 | $0.01 | $0.01 | $0.01 | $0.44 | $3.00 |
| 52 | Temp PVT MK line 12 - paint (70300261) | LF | 4,005 | $0.01 | $0.01 | $0.01 | $0.75 | $5.00 |
| 53 | Temp PVT MK line 24 - paint (70300281) | LF | 930 | $0.01 | $0.01 | $0.01 | $1.60 | $6.00 |
| 54 | Sign panel T1 (72000100) | SF | 35 | $32.60 | $30.00 | $37.00 | $30.00 | $27.50 |
| 55 | Remov sin pan assy TA (72400100) | EACH | 4 | $65.15 | $60.00 | $94.00 | $60.00 | $82.50 |
| 56 | Metal post TY A (72900100) | LF | 72 | $22.80 | $21.00 | $21.00 | $21.00 | $16.50 |
| 57 | THPL PVT MK LTR & sym (78000100) | SF | 150 | $6.25 | $5.75 | $6.15 | $5.85 | $6.44 |
| 58 | THPL PVT MK line 4 (78000200) | LF | 1,990 | $1.30 | $1.20 | $1.05 | $1.00 | $1.10 |
| 59 | THPL PVT MK line 6 (78000400) | LF | 3,035 | $1.60 | $1.45 | $1.15 | $1.10 | $1.21 |
| 60 | THPL PVT MK line 8 (78000500) | LF | 180 | $2.15 | $1.95 | $2.85 | $2.75 | $3.03 |
| 61 | THPL PVT MK line 12 (78000600) | LF | 1,335 | $3.25 | $3.00 | $3.30 | $3.15 | $3.47 |
| 62 | THPL PVT MK line 24 (78000650) | LF | 310 | $6.25 | $5.75 | $6.05 | $5.85 | $6.44 |
| 63 | Polyurea PM T1 LN 6 (78008230) | LF | 80 | $59.75 | $55.00 | $20.75 | $20.00 | $22.00 |
| 64 | PVT MKG rem WTR blast (78300202) | SF | 13,050 | $0.01 | $1.20 | $0.01 | $1.20 | $3.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.