Lansing, section 24-00179-00-RS. Let by Illinois DOT on March 7, 2025, Cook, District 01. 2 bids received; low bid $592,913 by Gallagher Asphalt Corporation.

Owner
Illinois DOT
Letting
07 MAR 2025
Pay items
62
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Gallagher Asphalt Corporation$592,913Low
2D. Construction, Inc.$628,067+6.0%
IDOT contract 61L27: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Gallagher Asphalt Corporation2. D. Construction, Inc.
1Rem and reinst dec stone (X2003001)SF90$29.00$50.00
2High vis temp fence (X2011001)LF175$5.25$12.00
3HMA driveway pavt 4 (X4060282)SY1,265$52.00$35.00
4Temp info signing (X7200061)SF20$32.00$35.00
5Drain util STR adj (Z0017400)EACH3$800.00$600.00
6Drain util STR recon (Z0017700)EACH1$1,300.00$1,500.00
7Tree root pruning (20101200)EACH3$175.00$616.00
8Earth excavation (20200100)CY30$90.00$60.00
9Trench backfill (20800150)CY45$86.00$100.00
10Topsoil F & P 4 (21101615)SY2,230$13.00$7.70
11Grading & shap ditch (21400100)LF740$22.00$30.00
12Seeding CL 2A (25000210)ACRE0.50$12,000$3,960.00
13Nitrogen fert nutr (25000400)LB45$8.50$3.30
14Potassium fert nutr (25000600)LB45$8.50$3.30
15Erosion contr blanket (25100630)SY2,230$3.75$1.54
16Temp eros contr seed (28000250)LB50$7.50$8.80
17Agg base cse B 4 (35101600)SY12$17.00$45.00
18Aggregate-temp access (40201000)TON435$1.00$60.00
19Bit matls tack CT (40600290)LB7,765$0.01$0.01
20Long joint sealant (40600370)LF3,780$4.15$3.16
21Mix CR JTS flangewys (40600400)TON17$50.00$0.01
22HMA surf rem butt JT (40600982)SY140$14.00$0.01
23P HMA BC IL-4.75 N50 (40603200)TON468$144.00$105.00
24HMA SC IL-9.5 D N50 (40604060)TON985$93.00$95.00
25PCC driveway pavt 7 (42300300)SY50$190.00$165.00
26PC conc sidewalk 5 (42400200)SF110$17.00$38.50
27Detectable warnings (42400800)SF20$72.00$44.00
28HMA surf rem 2 1/4 (44000158)SY11,350$3.00$4.00
29Drive pavement rem (44000200)SY1,315$22.00$14.00
30Comb curb gutter rem (44000500)LF175$11.50$6.00
31Sidewalk rem (44000600)SF110$5.75$12.00
32CL D patch T3 8 (44201745)SY35$166.00$130.00
33CL D patch T4 8 (44201747)SY250$115.00$130.00
34Aggregate SHLDS B 4 (48101498)SY250$59.00$10.00
35Pipe culvert remov (50105220)LF335$16.25$20.00
36P cul CL A 1 12 (542A0217)LF22$65.00$95.00
37P cul CL A 1 24 (542A0229)LF231$84.00$105.00
38P cul CL A 1 27 (542A0232)LF82$99.00$125.00
39PRC flar end sec 12 (54213657)EACH2$1,050.00$1,500.00
40PRC flar end sec 24 (54213669)EACH10$1,600.00$2,200.00
41PRC flar end sec 27 (54213672)EACH2$1,750.00$2,600.00
42Comb CC&G TM4.12 (60608562)LF175$62.00$82.50
43Non SPL waste disposl (66900200)CY95$135.00$100.00
44Soil disposal analy (66900530)EACH1$1,650.00$1,815.00
45Reg sub P-const plan (66901001)LS1$3,500.00$2,475.00
46Reg sub F con report (66901003)LS1$525.00$2,475.00
47Reg sub mon (66901006)CAL DAY5$750.00$1,045.00
48Mobilization (67100100)LS1$35,500$35,000
49TR cont & prot 701501 (70102620)LS1$1,800.00$50,000
50TR cont & prot 701801 (70102640)LS1$150.00$0.01
51Changeable message SN (70107025)CAL DAY70$21.00$35.00
52Short term pavt mking (70300100)LF380$6.00$3.00
53SHRT TRM pavt MK rem (70300150)SF130$0.01$2.00
54Sign panel T1 (72000100)SF55$31.50$27.50
55Remov sin pan assy TA (72400100)EACH13$80.00$82.50
56Teles STL sin support (72800100)LF120$15.00$16.50
57THPL PVT MK LTR & sym (78000100)SF75$5.75$6.33
58THPL PVT MK line 4 (78000200)LF11,515$0.75$0.78
59THPL PVT MK line 6 (78000400)LF315$1.10$1.21
60THPL PVT MK line 12 (78000600)LF75$2.20$2.42
61THPL PVT MK line 24 (78000650)LF170$5.75$6.33
62PVT MKG rem WTR blast (78300202)SF1,550$0.01$3.30
IDOT contract 61L27: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy